The Planning Board approved several applications on May 21, 2026. Eversource Energy received a Wetland Conditional Use Permit (CUP) for utility pole replacement at 19 Morgan Drive, approved unanimously. 1494 Route 3A, LLC secured approval for two contractor bay buildings (8,400 and 3,990 sq. ft.) and an associated Wetland CUP, voting unanimously with conditions including invasive species removal and no bulk chemical storage. Timothy Polson’s lot line adjustment was continued to June 18, 2026, pending a waiver request. J.E. Belanger’s lot line adjustment and after-the-fact Wetland CUP were approved unanimously, requiring shed removal and buffer establishment. Kearsarge Bow LF LLC’s 1.76 MW solar array application and Wetland CUP were continued to June 18, 2026, with a site walk scheduled for June 15. The Board approved a 2,375 sq. ft. warehouse addition at 506 Hall Street for Amoskeag Realty, subject to state permit receipt. Appointments and specific dollar amounts were not present in the record.
Source: https://www.bownh.gov/AgendaCenter/ViewFile/Minutes/_05212026-2720
The Recycling and Solid Waste Committee met September 1, 2026. Sherri Cheney reported tipping fees increased to $143.77 per ton in July. The committee decided to continue monitoring fees. Irene Hou reported Terracycle will pay out $463.37 from 46,337 points in January 2027. For Household Hazardous Waste Day on October 17, 2026, Bow will pay Dunbarton $350 for Greg Rule to manage transportation and disposal of local items. Greg and Sherri will decide on waste oil disposal options. Sherri updated the HHWD contract with vendor NH Recycles and forwarded it to Town Manager David Stack. Specific tasks were assigned to members for event publicity and logistics. The Trex program will restart in April 2027 to work toward the next $100 gift. HELPYSY collected 559 pounds recently. The next meeting is October 6, 2026, and Sherri will attend the Joint Selectmen meeting October 13.
Source: https://www.bownh.gov/AgendaCenter/ViewFile/Minutes/_09012026-2767
The Capital Improvements Committee met on August 31, 2026. They unanimously approved the July 28, 2026 minutes with a revision clarifying Parks and Recreation contributions. The Bow School District reported drawing $46,000 of approved $500,000 CIP funds for the completed elementary school renovation. Upcoming 2027-28 projects include Blue Light Warning Systems ($40,000 each), flooring asbestos abatement ($62,974), irrigation extension ($75,000), LED lighting ($50,000), and roof replacement ($252,000). A proposed three- to four-year HVAC replacement project totaling $2,850,000 aims to avoid bonding. Committee members requested the Library Director return with revised project information and explanations. The Facilities Manager discussed paving projects and vehicle replacement. The next meeting is scheduled for September 14, 2026, at 5:30 PM in Room B. The meeting adjourned at 8:15 PM.
Source: https://www.bownh.gov/AgendaCenter/ViewFile/Minutes/_08312026-2773
The BDC approved the August 5, 2026 minutes by a 6:0:2 vote, with Chair Hickey and Selectman Flanagan abstaining. Regarding the Bow Mills Redevelopment Strategy, a selected consultant is gathering data, with a feasibility report expected around December or January; the project is funded by a grant. Amber Bow Associates received approval for bulk gas storage, and Dow Road/Route 3-A intersection construction is nearly complete. The I-89 Exit 1 toll increase funding begins January 1. A water extension feasibility study for the Bow Mills area is underway. For 8-12 Ferry Road, property owners were directed to stop work until an Intent to Cut was filed and wetlands concerns addressed; the matter will proceed through the regular process. The meeting adjourned by unanimous vote at 8:05 a.m.
Source: https://www.bownh.gov/AgendaCenter/ViewFile/Minutes/_09022026-2769
The Commission unanimously approved the June 3, 2026 minutes, with Mr. Foote abstaining. The Board of Selectmen allocated $300,000 in Tax Increment Financing for the Dow Road/Route 3-A intersection improvements, which are nearing completion despite member frustration over the reduced funding level. The Northern Border Regional Commission grant-funded feasibility study for the Bow Mills area water extension is underway, with Resilience Planning and Design selected as the consultant; the economic development strategy report is anticipated by Town meeting. Hoptimystic Brewing plans to operate through October before reassessing permanent construction options. Mr. Boynton will contact a representative from McGovern to provide an update to Ms. Makinen. Future Planning Board agenda items include the Mariner Tower application and the Amber Bow gas storage change of use on August 20, 2026. The meeting adjourned at 8:16 a.m. by unanimous vote.