Wolfeboro Waters Meeting (minutes)
The Select Board approved a $21,900 budget for 2027. Libby moved and Mary seconded; the motion carried. Funds include $11,900 for the Assessment Committee, $4,000 for Communications, and $6,000 for Mitigation and Prevention. The budget clarifies $5,000 is for Elisa plates. Regarding the Carry Beach Petition, the state confirmed hand-raking debris does not require a wetlands permit; next steps include moving the swim line. Beach signs for Carry and Brewster will be installed late fall or early spring. The Water Quality non-Capital Reserve fund received $23,500 for the Wentworth Watershed Association, split between Wentworth Estates and a Watershed Management Plan. A $40,000 match was approved for the Rust Pond grant. The committee coordinates with LWA for a Town Hall presentation on October 22. The next meeting is October 20, 2026. Source: https://www.wolfeboronh.us/AgendaCenter/ViewFile/Minutes/_09152026-397
Wolfeboro Waters Committee
September 15, 2026
Meeting Minutes
Present: Linda, Beth, Paul, Steve, Julie, Dana Al, Libby, Warren, Mary
1). The meeting was called to order at 1:00pm
2). Minutes: Minutes could not be approved due to a computer glitch
3). Election of new Chair—Co-chairs?
Julie stated she will consider becoming a co-chair after her strategic planning is completed and
only if the Wentworth Board agrees. Abby was nominated as a potential co-chair with Julie.
4). Develop the Budget 2027.
Linda presented the proposed a total 2027 budget of $21,900 as follows:
a.
Assessment Committee -- $11,900
1.
UNH
6,000 – Toxin Testing
2.
UNH
Stream Analyses
2,000
3.
Toxin Test Strips
1,400
4.
Stream Consultant
2,500
Paul asked if there were specific locations for future toxin testing in 2027.
Committee members indicated that testing is done when blooms appear and that we
could provide areas of concern rather than a listing specific sites. The budget will be
revised to clarify that $5,000 of the $6,000 for toxin testing is for the purchase of
Elisa plates used in toxin testing. The Assessment Committee will provide more
specifics on each of the budget items.
b.
Communications Committee ----- $4,000
1.
This budget will be used for Beach signs for Albee Beach and boat ramps
Linda stated she needs invoices for signs already made for Carry and Brewster
beaches that were completed this year.
c.
Mitigation and Prevention ----- $6,000
Julie will write up a paragraph clarifying this request.
Libby moved and Mary seconded a motion to approve the proposed budget request.
The motion carried.
5). Dockside Parking Lot Puddle
a. All water testing will be done by Stantec. None of the testing has come back. They are
still working on this.
6). Carry Beach Petition
a. Review
b. The state replied that manual removal of debris from a swimming area does not require
wetlands permit. Hand raking of leaves and other organic debris from the shoreline or lake bed
may be conducted without a wetlands permit so long as the area is exposed by drawdown or
other lower water conditions. Raking does not disturb the vegetation roots, and the area being
raked is no larger than 900 square feet. Hand removal of tree branches, construction material,
and fish lures may be done without a state wetland permit.
The next step is moving the swim line out, dealing with anchoring outside the swim line, and
considering limitation on rafting.
7). Communications Committee
a. Update report
b. Beach signs – Carry Beach and Brewster Beach
c. Later Albee Beach
d. Boat Ramps
Beach signs for Carry Beach and Brewster Beach will be installed late fall or early
spring. The Entire budget was used for the creation of these signs. Signs for Albee
Beach and the Boat ramps will be created with the 2027 budget.
An article on benthic mats was submitted.
Wolfeboro waters is coordinating with LWA on their presentation at the Town Hall on
Oct. 22 from 4:30 – 6pm.
Winnipesaukee Day –
The committee discussed whether the staff time required for Winnipesaukee Day is justified
by its educational value. Members suggested developing a more interactive approach that
would better promote participating organizations while educating the public about water
quality. One idea was a shared tent, with participating organizations contributing to the cost
and development of engaging educational activities.
8). Assessment Committee
a. Benthic mats – Samples were collected from 6 sites and were sent to UNH for toxin
testing including one rock scraping and one sample suctioned using a turkey baster from
each site. Samples were sent to UNH for analyses and we are waiting for results.
b. Stream Sampling –we continue to take samples from 4 sites. In August and again in
September T-20 and T-40 were dry. Beaver Brook and Knight’s pond (McLeod Dr) were both
low, but flowing. Samples from Beaver Brook and Knight’s Pond were taken and sent to UNH
for processing and analyses.
c. Work with UNH
Wentworth has sampled streams at 16 sites for 30 years. WW is working to develop a stream
sampling network, and LWA does some sampling in Back Bay. The committee discussed the
long-term coordination of stream sampling among Wolfeboro Waters and watershed
organizations, including how to use WW resources effectively and avoid duplication of effort.
With respect to Winter Harbor, Warren stated that Winter Harbor was included under the
Tuftonboro Water Management Plan. He stated that at the time there was no sampling and
monitoring of the lake by LWA – it was all done by modeling. Winter Harbor is all intermittent
streams and there has never been measurement of their contributions. Priority for which
streams should be monitored have taken into account what is to be done with the results,
especially if there are no mitigation options. T20 and T40 were sampled because they are
looking at mitigation options and because the town has done a project related to it. Paul
stated that if an organization wants to get organized, there is a model here. We should get
organized and tell them what we are doing – Don’t tell LWA what to do. Dana stated 2
organizations don’t need to duplicate efforts.
Warren stated cyanobacteria is being fed by nutrients on the top layers of the water and in the
shorelines, not from the deep sites. This is evidenced by data collected. Measuring the
streams will provide information about the sources of risks of cyanobacteria.
Warren received a prepublication of a peer-reviewed paper written by scientists from Bigelow
Labs. Scientists used water samples containing gloeotrichia from 6 lakes across the nation
including Winnipesaukee and Wentworth. A full DNA analysis found that all gloeotrichia was
the same. They also determined that none of the gloeotrichia contained a gene for any of the
known cyanobacteria toxin. Therefore, gloeotrichia is non-toxic.
The committee discussed having Warren provide a layman’s summary of the article with a link
to the publication. Warren indicated it is premature to send it to the state because the article
will be published in November. Once published, the summary and link could be shared with
the state by Warren because of his direct involvement in the project.
Land based phosphorous is increasing the risk for all cyanobacteria.
9). Rust Pond - Libby
a. Update --319 grant for the watershed for the north end of Rust Pond- grant has been
signed by all but the GNC. Hoping to get funds released soon. List of 7 areas of concern
identified. On hold for now.
b.
Update on NHDOT project for Rt 28 South below Pleasant Valley Road – Nancy
has turned over a construction plan and they are doing work to identify what can happen on
the west side of 28 and continues to talk about creating a time line. Conversation continues.
This Thursday NH DOT will present a plan for rt 28 starting at 6pm.
Primary purpose is looking at acquisition of property abutting this project. Soil samples need to
be done. Big problem will be Kingswood Acres – will take some of the water, but not all of it.
The committee discussed the importance of involving the Public Works Director and
incorporating the remaining project needs into the 10-year plan. Linda suggested working
through the Lakes Region Planning Commission. Paul and Linda will follow up with Steve and
the new Town Manager regarding inclusion in the next 10-year plan.
10). Mitigation and Prevention
a.
Rewrite the Shoreland Ordinance
Shanna Saunders Lakes Region Planning Commission – Water Grant
1.
Cost - $6,000
b.
Library Parking Lot
Library plan is being pushed out 3 years
c.
Crescent Lake - Water levels have been kept at mid-range. Continued complaints about
low water levels were attributed to drought conditions, and the committee noted
progress.
The Mitigation and Prevention Committee is beginning work on shoreline regulations and still
needs to meet with the health regulations inspector. Dave attended the septic system
workshop, and a recording will be shared with Wolfeboro Waters. Formal committee
meetings are needed to develop the work plan for next year. Shoreline regulations are being
considered for 2028, with community buy-in needed first.
Warren asked about future plans to address uphill water. The committee discussed
prioritizing shoreline regulations first because uphill and shoreline issues are governed
differently and shoreline impacts associated with real estate activity are an immediate
concern. The goal is to develop regulations that are clear and usable, with uphill regulations
to be considered in the future.
The committee also discussed the need for additional environmental inspection and building-
code enforcement capacity. Linda suggested that Mitigation develop a proposal or job
description. Steve indicated the Conservation Commission's role would be consultative.
Mitigation will put together a plan.
11.) Septic Systems- Update
a. Next step --- will meet with health inspector.
12). Wentworth Watershed Association
a. Meeting with NHDOT on RT 28
b. Wentworth Estates – Done
c. Septic Workshop report
WWA reported that its two current grants have closed. WWA will organize a tour of Pleasant
Valley and a Red Brook Circle (Wentworth Estates) in construction site in October.
13). The Lake Winnipesaukee Alliance
a. Update --NO UPDATE
b.
Dana stated they are ready to roll out the Fate and State of the lake presentations.
14). Possible land for stormwater Containment structures
a. Update-Steve Towne Cricket Hill development- Partridge Drive, Berrywood etc. effect
on Winter Harbor-
b.
Solutions
Met with Steve Randal and Dan Coons re: lot in Berrywood in the White Gate Rd area. Got
good information. Looked at a lot with small watershed that drains into it. Determined that
not much can be done to impact water flow; expensive and not worth all the effort. Talked to
Steve about what can be done in area of Maple wood and he created a flow splitter in
spring– Has connected it so it should more equalize the flow, but won’t reduce the flow into
the lake. Haven’t yet seen impact due to drought. One idea is to hold water in a pond to let
nutrients settle out in pond before running down into the lake. Permitting will be expensive.
Much more involved than a neighborhood can afford. Dana feels a 319 grant would be
possible. Al indicated this could be used as a model to solve this same problem in other
areas of the lakes.
Linda asked if it is possible to get a cost estimate. The committee discussed whether the
project could become a concept plan, be supported through a municipal grant, be
incorporated into an existing grant, or involve the Town Planner. Linda recommended
meeting with LWA to determine the status of 319 grant funding and exploring a partnership
with LWA on Winter Harbor.
15). Water Quality non-Capital Reserve fund
a. How to rank projects to receive funds? WWC needs to use its tracking sheet and
write criteria- what committee?
b.
Select Board-approved Rust Pond grant match at $40,000
c.
After 2 Select Board meetings, the full $23,500 was approved for the Wentworth
Watershed Association, to be allocated as $10,000 for the Wentworth Estates project
and $13,500 for the Watershed Management Plan.
The committee discussed what should be included in the Water Quality Reserve Fund.
Linda proposed requesting $100,000 and developing a list of the top 10 projects that could
be supported. The reserve fund would become its own warrant article. WWA will pull the
priority projects from the existing project-ranking tool to support development of the list.
16). Dockside pipe issue- Downtown Grille/Wick Loon Building -capped
17). Milfoil application of ProcellaCOR
a. In 2026, ProcellaCor will be used in Back Bay’s frog pond and in Goodwin Basin.
b.
Treatment of ProcellaCor took place, and it was followed by DASH and hand-pulling for
7 days.
Their budget is going in.
18). Six Legged Society
Will report next meeting
19). Spiny Water Flea watch
a.Support
Dana reported that very few were seen in deep water site.
20). Wolfeboro Bay Watershed Management Plan
a.
What is next
21). Other Business--
22). Public input
23). Select Board approved budget of $21,900.
August monthly budget report shows nothing spent. Invoices need to be sent to me for approval
and then to Amy.
a.Estimated 2026 amounts equal $21,900-
b.Assessment Committee $17,900
UNH Intern
5,000.00
Consultant-
2,000.00- UNH or Bigelow for data analysis and direction
UNH- Stream Analysis 2,000.00
Eliza plates
5,000.00
Toxin test Strips 1,400.00
Stream Consultant 2,500.00
Communication Committee $2,000
Mitigation and Prevention $2 000
24). Next meeting Date: October 20, 2026 Time 1:00
Respectfully submitted
Beth Marcoux