Commissioners unanimously approved minutes from July 6 and July 20, 2026, by a 3-0-0 voice vote. They also voted 3-0-0 to reimburse the Village at Kearsarge Condominium Association $319,550 from the Sewer Infrastructure Capital Reserve Fund. Checks for payroll and accounts payable dated July 30, 2026, were ratified 3-0-0. The Fire Department scheduled a public hearing for September 23rd at 7PM regarding its Master Plan. Project updates include the delivery of the WWTF pickup truck, expected delivery of a compact wheel loader at the end of August, and initiation of the Skimobile-Artist Falls Water Main construction this week. An alternatives analysis recommended upgrades at the Remoat Trail Pump Station and a new force main to Grove Street, with a design kick-off meeting set for early August. Source: https://www.ncwp.nh.gov/AgendaCenter/ViewFile/Minutes/_08032026-50

Document

Commission Meeting 08/03/2026 
 
Adopted: 08/17/2026 
Page | 1  
 
Board of Commissioners 
Public Minutes 
August 3, 2026 
 
The Commission meeting convened at 10:00 AM in the conference room at the North Conway Water Precinct, 104 Sawmill Lane 
North Conway, NH. The following were present: 
 
Commissioner James Umberger  
 
 
 
 
Fire Chief Chad McCarthy 
Commissioner Rodney Morrison  
 
 
 
 
Business Administrator Molly Donley 
Commissioner Deborah Fauver 
 
 
 
 
 
Treasurer Kristine Cluff 
 
 
 
  
Superintendent Jason Gagnon 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
CALL TO ORDER 
The meeting was called to order at 10:00AM by Commissioner Umberger. 
 
PUBLIC HEARINGS 
None.  
 
APPROVAL OF MINUTES 
Motion of Commissioner Fauver to adopt the following minutes,  
A. Public meeting minutes from July 6, 2026 
B. Non-public session minutes from July 6, 2026 
C. Public meeting minutes from July 20, 2026 
D. Non-public session minutes from July 20, 2026 
Second by Commissioner Morrison. 
Motion carried by a 3-0-0 voice vote. 
 
 
FIRE CHIEF 
Membership 
42 
 
Personnel 
Two members on leave of absence. 
 
Training 
Department Training: Relay pumping tonight if the rain holds off. 
Engine 1 Training: Undetermined.                                                                        
Rescue Training: Ground school with Med flight, landing zones and procedures. With Conway Fire.   
 
Department Activities 
Place of assembly inspections and life safety inspections on going. 
Fire Department’s Master plan – Waiting to hear back from ESCI (Jeff) for dates that he can make it up for a presentation.  
Emailed completed draft. Talked to Jeff about doing the presentation in September. Scheduling public hearing for September 
23rd at 7PM.  
Fire Department’s Anti-Nepotism Policy approval. Emailed last week. Putting on hold until next meeting. 
Conway police department is looking to replace dispatch equipment. It is over 10 years old. Waiting on quote. Asked NCFD, 
Center Conway and Town of Conway to chip in as the PD dispatches all of those calls. This would come out of next years budget.  
 
Emergency Calls 
Five-year call average is 1,500 calls a year. 
Five-year monthly call average is 125 calls a month. 

Commission Meeting 08/03/2026 
 
Adopted: 08/17/2026 
Page | 2  
 
Five-year daily call average is 4.11 calls a day. 
 
Year to Date Call Average  
The department has responded to 921 calls year to date for 2026  
Monthly call average is 130 calls a month for 2026.   
Daily call average is 4.31 calls a day for 2026. 
The department has responded to 172 calls for the month of July 2026. 
The department responded to 140 calls in June 2026. 
 
Apparatus / Trucks 
Having the Cafs system worked on Engine 3. Waiting for parts delivery.  
 
Equipment Issues 
No change. 
   
Purchase of New Equipment 
No change. 
 
 
COMMISSIONERS/SUPERINTENDENT REPORT 
Project Status 
 
Vehicle Purchases 
 
Compact Wheel Loader 
The latest delivery update from CAT is at the end of August. 
 
10-Wheel Dump Truck 
Truck is at the body shop. Should be here in a couple of weeks. 
 
WWTF Pickup Truck 
The truck was delivered. 
 
6-Wheel Dump Truck 
Grant paperwork has been submitted to the State of NH, and the buyers order has been placed with Ballard Trucks for the new 
Mack 6-wheeler.  Estimated delivery is October – November. 
 
Equipment Trailer 
No new updates. 
 
NCWP Master Plan Updates 
The Precinct’s original water and wastewater master plans were completed in 1999, with subsequent updates in 2005 and 2011.  We 
have reached the end of the planning period for the original master plan, and it is time to develop an updated plan that focuses on 
the next 20 years. 
 
Precinct leadership staff met with Black & Veatch to review Key Performance Indicators (KPIs).  Staff are reviewing proposed KPIs 
and will provide feedback to Black & Veatch. 
 
Landfill Leachate 
The initial phase of this project is 100% funded through the NHDES Emerging Contaminants program.  Its purpose is to identify the 
best available technology for PFAS removal from landfill leachate with the expectation that a new treatment process will be 

Commission Meeting 08/03/2026 
 
Adopted: 08/17/2026 
Page | 3  
 
constructed based on the findings of this project phase.  Annual Meeting 2026 approved up to $8M in borrowing to move forward 
with design and construction.  NCWP will work with the Town of Conway to advance this project thoughtfully and share costs 
equitably. 
 
Precinct wastewater staff met with the Black & Veatch Industrial Hygienist (think: environmental health and safety engineer) last 
week to discuss potential risks from working with a system that is intentionally concentrating PFAS.  The conversation was a good 
first step and Black & Veatch understands the Precinct’s commitment to keeping our staff safe and healthy.  BV will be doing 
some additional research with vendors who have these systems in place now to get a better understanding of the risks, as well as 
engineering controls to reduce that risk. 
 
Saco River Erosion 
This project is currently in design phase with the goal of addressing erosion of the Saco River banks that threatens WWTF 
infrastructure.  NCWP has received $15.2M in CWSRF funding through NHDES for the future construction phase.  
 
No new updates. 
 
North End Sewer Collections Capacity 
Analysis of the NCWP collections system in preparation to receive Lower Bartlett sewer flow revealed that the Remoat Trail Pump 
Station and 12” sewer main from Memorial Hospital to Grove Street have limited remaining capacity.  An alternatives analysis was 
performed by Wright-Pierce with a recommendation for upgrades at Remoat Trail Pump Station and construction of a new force 
main from the pump station to Grove Street within the Route 16 corridor as the least cost option. 
 
The design contract has been signed and a kick-off meeting will be scheduled in early August. 
 
WWTF Aeration Upgrades 
This project renews aging infrastructure and adds additional aeration capacity in the east carousel of the WWTF to meet increasing 
flows and loads at the WWTF.  It is funded by NHDES CWSRF in the amount of $2.99M, including ARPA Grant of $997,000; Principal 
Forgiveness of up to $369,300; Energy Audit Implementation Grant of $200,000; and State Aid Grant of at least 20% of remaining 
principal/interest balance.  NCWP also received $859,000 in CWSRF funding to add the backup generator replacement to this 
project. 
 
As part of the generator replacement portion of the project, the Precinct’s SPCC (Spill Prevention Control Countermeasures – 
required by NHDES Oil Spill & Remediation Bureau) plan is being updated.  That is expected to be finalized soon, at which point 
the new generator can be filled with fuel and startup testing can begin. Final version came in last week. 
 
No updated lead time on the replacement part from Ovivo. Could be 30-45 weeks. Very slow leak, the part in there is fine for 
now. Would want to do the swap at a low period anyways. 
 
Skimobile-Artist Falls Water Main 
This project is currently in design.  It will add a second piping connection between the north and south pressure zones of the water 
distribution system to improve resiliency.  It is funded by a DWGTF loan/grant ($1,357,200 loan, $150,800 grant). 
 
Piping and equipment have begun to be delivered to the site, with work expected to begin soon. This week or next. 
 
Country Road Sewer 
This project extends sewer into the Country Road portion of the Village at Kearsarge.  It is funded through a NHDES CWSRF loan of 
$1,390,000 with 10% principal forgiveness.  An additional $600,000 CWSRF Loan was approved in 2025 along with $322,708 in 
capital reserve funds. 
 
No new updates – working through the process of project closeout. Meeting scheduled with Eric at HEB this week. 
 

Commission Meeting 08/03/2026 
 
Adopted: 08/17/2026 
Page | 4  
 
Village at Kearsarge Condos – Sewer 
$443,000 was appropriated at Annual Meeting 2024 through a Petitioned Article to put toward the estimated cost of $922,000 for 
the Condos to connect to existing Precinct sewer (48% of total project cost).  Work was to include gravity sewer, a sewer pump 
station, and sewer force main.  This project has been awarded and is due to begin construction. 
 
We have received the invoice from the Village at Kearsarge Condo Association in the amount of $319,550.  I have reviewed the 
project pay applications and test results and find everything to be in order.  I am recommending that the Commission vote to 
approve reimbursement of the Village at Kearsarge Condominium Association in the amount of $319,550 to be paid from the 
Sewer Infrastructure Capital Reserve Fund. 
 
Motion of Commissioner Fauver to approve the reimbursement of the Village at Kearsarge Condominium Association in the 
amount of $319,550 to be paid from the Sewer Infrastructure Capital Reserve Fund. 
Second by Commissioner Morrison.  
Motion carried by a 3-0-0 voice vote. 
 
Town of Conway – CVFD Transition 
With Conway Village Fire District dissolving, the Town will assume responsibility for their water/sewer systems.  NCWP is engaging 
with the Town to develop a new Inter-Municipal Agreement (IMA) based on fair and equitable sharing of wastewater treatment 
costs. 
 
I was able to connect with the Attorney General’s office.  The IMA is currently in review, with a due date of August 7th. 
 
Lower Bartlett – IMA Discussion 
Lower Bartlett Water Precinct has received funding through USDA Rural Development to construct a sewer collection system.  NCWP 
is working with LBWP to develop an IMA to establish what LBWP will pay for NCWP to receive and treat its sewage. 
 
NCWP received a letter from LBWP’s engineer, Verdantas, highlighting the shared benefit for both NCWP and LBWP with respect 
to groundwater protection.  Using that premise, the letter further suggested that NCWP consider sharing in the capital cost of the 
sewer project.  This is the first time LBWP has proposed something like this to NCWP.  While the shared groundwater protection 
benefits are clear, there are many questions about potential sharing of capital costs that need to be carefully considered before 
moving forward down the path of project cost sharing.  NCWP has asked Black & Veatch to provide assistance and support with 
this process, given their depth of experience with intermunicipal agreements across the country and the strength of their work 
helping to develop the cost sharing approach of the new Town of Conway IMA.  It is important that NCWP have a good 
understanding of how such a cost-sharing proposal could work – from legal, operational, and equity perspectives – before we 
engage with LBWP on further discussion. 
 
Potential Water & Sewer Easement – Eastman Road 
NCWP is seeking a water/sewer easement on the lot just east of Walmart to provide a path for the water main to continue from 
Hemlock Lane to Eastman Road for resiliency of connection to Pine Hill Tank. 
 
No new updates. DOT put pause on this because of the potential lawsuit. Not granting any easements until litigation is wrapped 
up.  
 
Lead Service Line Investigation / Replacement 
Revisions to USEPA’s Lead and Copper Rule require that all public water systems identify material type for every water service line in 
the system and then replace certain types that may increase the risk of lead exposure.  NCWP approved $925,850 for this project, 
which will include purchase of a vacuum excavation trailer, 20-ton equipment trailer, and mini excavator.  The project is funded by 
NHDES with 71% principal forgiveness. 
 
No new updates. Vac trailer delivered, doing training today. 
 

Commission Meeting 08/03/2026 
 
Adopted: 08/17/2026 
Page | 5  
 
Manhole Raising 
No new updates – Silas is working with the equipment vendor to schedule a demo in August. Demo date is August 12th. 
Coordinated with DOT and Town of Conway. 
 
River Access and Camping 
This summer, we seem to have an extra influx of people parking near the railroad tracks to access the river in tubes.  Additionally, 
we’ve had people parking and camping at our Well 4/5 building.  To try and discourage that, we’re having signs made noticing 
the area as private property, prohibiting camping and river access, and publishing state and federal regulations that allow fines 
up to $25,000 per day and/or imprisonment for negligent trespass. 
 
Well 4/5 Apron Paving 
We will be paving the access apron at our Well 4/5 control building for two important reasons in the coming weeks: 
 
1. 
Improve safety when bringing pallets of NaOH (sodium hydroxide – used to raise the pH and limit corrosion in the pipes) 
into the building; and 
 
2. Reduce erosion during heavy rains that causes us to frequently have to clean out the drainage swales along the road. 
 
Abatement Requests 
None. 
 
 
OLD BUSINESS 
• 
Election Rules, and Precinct Moderator and Clerk Job Descriptions  
• 
Treasurer Job Description 
 
NEW BUSINESS 
None.  
 
OTHER BUSINESS 
None.  
 
PUBLIC COMMENTS/MEDIA QUESTIONS 
• 
Treasurer Kristine Cluff raised concerns about paying for employee training in the water and sewer departments and if 
there is a policy in place similar to the Fire Department where the employee has to agree to stay in position for X amount 
of time after training, and if not they have to reimburse NCFD for the training. 
• 
The Superintendent stated that the Precinct does not have a policy for that. It has always been that the Precinct will pay 
for the trainings for Operators to gain licensure.  
• 
Commissioner Fauver requested that the policy NCFD has in place be added to the employee handbook. 
 
SIGNATURE OF DOCUMENTS 
None. 
 
SIGNING OF CHECKS 
Motion of Commissioner Fauver to ratify checks to be signed out of session:  
1. 
Payroll checks dated 7/30/2026 
2. Accounts payable checks dated 7/30/2026 
Second by Commissioner Morrison. 
Motion carried by a 3-0-0 voice vote. 
 
NON-PUBLIC SESSIONS 

Commission Meeting 08/03/2026 
 
Adopted: 08/17/2026 
Page | 6  
 
Motion to enter non-public session made by Commissioner Fauver and seconded by Commissioner Morrison. 
 
Specific statutory reason cited as foundation for the non-public session: 
 
 _X_ RSA 91-A:3, ll(c) Matters which, if discussed in public, would likely affect adversely the reputation of any 
person, other than a member of the public body itself, unless such person requests an open meeting. This 
exemption shall extend to any application for assistance or tax abatement or waiver of a fee, fine, or other 
levy, if based on inability to pay or poverty of the applicant. 
 
_X_ RSA 91-A:3, ll(e) Consideration or negotiation of pending claims or litigation which has been threatened 
in writing or filed by or against this board or any subdivision thereof, or by or against any member thereof 
because of his or her membership therein, until the claim or litigation has been fully adjudicated or 
otherwise settled. 
 
 
Roll call vote to enter non-public session: 
 
 
 
 
Rodney Morrison 
 
Y 
N 
James Umberger 
 
Y 
N  
Deborah Fauver  
 
Y 
N 
 
Entered non-public session at 10:41 AM 
Public meeting reconvened at 11:45 AM 
 
Motion of Commissioner Fauver to seal the non-public session minutes as it was determined that divulgence could render the 
proposed actions ineffective. 
Second by Commissioner Morrison. 
Motion carried by a 3-0-0 voice vote. 
 
ADJOURN 
Having nothing further to come before this public meeting, motioned by Commissioner Fauver to adjourn at 11:45 AM.  
Second by Commissioner Morrison.  
Motion carried by a 3-0-0 voice vote. 
 
 
 
 
 
Respectfully, 
Molly Donley