Assistant Superintendent Hinds provided updates on hiring and the LHS Outreach Coordinator resignation. The 2026-27 budget line item review is scheduled for next week. The remaining fund balance will restore the Food Service Department deficit. The City approved $32,000.00 in Impact Fees for the ESS Bus Loop drainage project, scheduled for August completion with an additional $36,000.00 paving cost. The LHS sewer drain project is on hold to prioritize grease trap repairs costing $2,929.00. LHS water main repairs for leaking copper pipes are estimated at $20,122.00. Moving forward, the Superintendent will oversee facilities management. Committee Chair Dunn tasked the Budget and Personnel Committee with reviewing Policy Section D (Fiscal Management) to provide feedback to the Policy Committee. New scoreboard donations for LHS will go to the School Board for action. The next meeting is August 3, 2026, at 8:30 AM. Source: https://www.sau30.org/uploads/1/4/2/8/142821414/b_p_minutes_2025_jul_9.pdf

Document

​Meeting: Budget and Personnel Committee​
​Date: July 9, 2026 3:30 PM​
​Location: SAU 30 / Boardroom​
​Meeting Minutes​
​In Attendance:​ ​Committee Chair Dunn, Members Beck-Brown​​and Sullivan, Superintendent​
​Baeta, Assistant Superintendent Hinds, Business Administrator Cilley and Facility Director​
​Caruso​
​Start Time:​​3:31 PM​
​End Time:​​4:39 PM​
​Next Meeting:​​Monday, August 3, 2026 @ 8:30 AM​
​1.​ ​Personnel Update​
​●​ ​Assistant Superintendent Hinds offered a hiring update to the committee on​
​positions filled, recently posted, and those ongoing.​
​●​ ​Resignation for the LHS Outreach Coordinator (Non-Union Position) was​
​discussed with the committee.​
​●​ ​ESS School Nurse position will be on the School Board agenda for discussion and​
​approval.  There will also be a non-public session to discuss a request from a LEA​
​Teacher to be released from their contract for the 2026-27 school year.​
​2.​ ​Budget​
​a.​ ​2025-2026 Update​
​●​ ​Superintendent Baeta explained that the FY26 Close Out is Due September 1st to​
​DOE and this information will be shared with the committee once that is​
​complete.​
​●​ ​BA Cilley explained the remaining fund balance will be applied towards making​
​the Food Service Department whole.​
​b.​ ​BMO Charge Update​
​●​ ​BA Cilley reviewed the requested breakdown of the June BMO charge with the​
​committee.​
​●​ ​Building Codes were discussed: 10- District, 20- Elementary, 21- WHS, 22- PSS,​
​23- ESS, 34- LMS, 45- LHS, and 75- Huot.​
​●​ ​Fund Codes were discussed: 21- District, 22- Grant, and 25-Food Service.​
​●​ ​Any questions on the report from the committee will be emailed to the SAU​
​Administration for clarification.​
​●​ ​BA Cilley explained the current purchasing procedure and process.  This will be​
​reviewed by the SAU Administration and any changes/updates will be​
​communicated with the committee.​
​c.​ ​2026-2027 Update​
​●​ ​The approved budget will be reviewed by individual line items by the​
​Superintendent and BA next week.​

​3.​ ​Potential Use of  Impact Fees​
​a.​ ​ESS Bus Loop Drainage Cost​
​●​ ​The City approved $32,000.00 of Impact Fees to be used towards this project.​
​●​ ​FD Caruso discussed the scope of the project and drainage issues. This project is​
​scheduled to start in August and will be completed by the start of school.​
​●​ ​The cost for paving this area will be $36,000.00 to complete.​
​b.​ ​LHS Sewer Drain Cost​
​●​ ​Superintendent Baeta and FD Caruso explained that this project will not use​
​Impact Fees and is currently on hold of switching the pipes from 2 to 4 inch pipes​
​as work on the grease trap will be done first as that appears to be the problem and​
​is more cost effective to try first.​
​4.​ ​LHS Grease Trap Cost​
​●​ ​Superintendent Baeta discussed that the work on the grease trap is a safety​
​priority and needs to be done immediately.​
​●​ ​The cost of this work will be $2,929.00 to complete.​
​●​ ​Future work on the snack shack is needed to improve the cleanliness and will be​
​assessed for any updated equipment to help prevent clogs and backups.​
​5.​ ​Internal Process for Facility Projects based on LMS Access Road Project​
​●​ ​Superintendent Baeta discussed that he has already met with the BP Chair and​
​Facility Chair regarding this project.  The SAU Administration does not disagree​
​that the process was not followed for this work to be completed.​
​●​ ​Committee Member Sullivan read a statement sharing his concerns on the process​
​of this project.​
​●​ ​Going forward, Facilities will be overseen by the Superintendent.​
​●​ ​The idea of a CPI Plan being implemented was discussed and the difference​
​between facility emergencies, budgeted projects and those that will be long term​
​plans going forward was discussed.  Policies will be reviewed to help determine​
​dollar amounts that require committee or School Board action to determine a​
​process and procedure going forward.​
​6.​ ​Lakes Region Consortium Update - June 24, 2026 @ Huot, 5-6:30 PM​
​●​ ​Assistant Superintendent Hinds discussed the recent presentation.  The power​
​point from the presentation will be included in the July 14 School Board Packet.​
​There is also an analysis of the Consortium that is available to any School Board​
​Member that is interested in receiving that document.​
​7.​ ​Review of Policy Section D Fiscal Management for Feedback to Policy Committee​
​for August Meeting ( NHSBA Sample Policies and Laconia Current Policies)​
​●​ ​Committee Chair Dunn discussed that she feels the BP Committee should review​
​this section of policies and offer feedback to the Policy Committee for suggested​
​revisions and updates.​

​●​ ​Copies of the NHSBA sample policies and Laconia current policies will be​
​emailed to the committee members to begin this review.​
​8.​ ​LAYBL Score Board Donation​
​●​ ​The donation of new score boards were discussed by the committee for LHS.​
​This will be on the School Board agenda for discussion and action.​
​9.​ ​Open Items​
​●​ ​Superintendent Baeta and FD Caruso discussed the LHS Water main work by​
​Johnson & Jordan with the committee.​
​●​ ​There are leaking pinholes in the copper pipe on level 2A around the library that​
​are in need of repair.  The cost of this work is $20,122.00​
​●​ ​There is also needed work on level 1A in front of the weight room.​
​●​ ​Superintendent Baeta will work with FD Caruso to combine these projects and he​
​will communicate the additional cost to the committee.​
​10.​​Next Meeting Date:​​Monday,​​August 3, 2026 @ 8:30 AM​