NH Muni WatchStatewide meeting record

All towns · keene

City Council Agendas for September 17, 2026

The Keene City Council agenda for September 17, 2026, includes several key items. The Finance, Organization and Personnel Committee recommends adopting Resolution R-2026-40, appropriating $80,000 from the unallocated General Fund balance for the Marlboro Street & Cheshire Rail Trail Improvements Project. This represents the City's 20% funding match for the project, with the actual change order approximately $265,000 and the Department of Transportation providing 80% federal funding. The vote was 4 to 0 in committee. Other agenda items include public hearings on Thompson Road alterations and Community Development Block Grant mid-grant hearings, a proclamation for Dr. Dottie Morris, and consideration of an ordinance establishing a temporary moratorium on data centers and cryptocurrency mining facilities. No additional decisions, votes, or dollar amounts were specified in the provided text for the September 17 meeting date. Source: https://keenenh.gov/wp-content/uploads/2026/09/2026_09_17_City-Council-Agenda_optimized.pdf

Document

KEENE CITY COUNCIL 
Council Chambers, Keene City Hall 
September 17, 2026 
7:00 PM 
 
 
 
 
  
  
  
ROLL CALL 
  
  
  
PLEDGE OF ALLEGIANCE 
  
  
  
MINUTES FROM PRECEDING MEETING 
  
• 
August 6, 2026 Minutes 
  
  
A. 
HEARINGS / PRESENTATIONS / PROCLAMATIONS 
  
1. 
Proclamation - Acknowledging Dr. Dottie Morris for her Years of Service 
to Keene State College, the City of Keene Human Rights Committee, and 
the Community 
  
2. 
Proclamation - Adult Education and Family Literacy Week 
  
3. 
Public Hearing - Resolution R-2026-37: Relating to the Alteration of 
Thompson Road 
  
4. 
Public Hearing - Community Development Block Grant Mid-Grant 
Hearings: 
•    Keene Housing, Roosevelt West Housing Project 
•    Cedarcrest Center Planning Grant 
  
  
B. 
ELECTIONS / NOMINATIONS / APPOINTMENTS / CONFIRMATIONS 
  
1. 
Confirmation - Human Rights Committee 
  
  
C. 
COMMUNICATIONS 
  
1. 
Michael Guitard/Guitard Homes LLC - Petition for City Ownership of 
Water and Sewer Infrastructure - Cottage Court Community on Court 
Street 
  
2. 
Duncan Hilchey and Amy Christian - Request for a Traffic Study and 
Safety Assessment of School Street 
Page 1 of 210

 
 
  
3. 
John T. Newcombe - Resignation - Board of Assessors 
  
4. 
Councilor Jones - Central Square Pedestrian Access During the 2026 
Keene Pumpkin Festival 
  
5. 
Shawn Voisine/Elmside LLC - Request for Waiver of City Public Utilities 
Standards for Water Metering Infrastructure - Elmside Cottage Court 
  
  
D. 
REPORTS - COUNCIL COMMITTEES 
  
1. 
Councilor Filiault - Request for Consideration of an Ordinance 
Amendment Regulating Dogs at Downtown Events and 
Paul Allen-Webber - Request to Reconsider Ordinance O-2004-15-A 
Section (e) Regarding Dog Restrictions During the Pumpkin Festival 
  
2. 
Councilor Jones - Request for Consideration of an Ordinance Establishing 
a Temporary Moratorium on Data Centers and Cryptocurrency Mining 
Facilities 
  
3. 
FY25 Audited Financial Statements Presentation - CBIZ CPAs, P.C. 
  
4. 
Warren Steinberg - Request for Temporary Free Parking within Active 
Downtown Construction Zones 
  
5. 
Acceptance of NH Juvenile Court Diversion Network Funding - Youth 
Services Manager 
  
6. 
FY26 DOJ Byrne Justice Assistance Grant (JAG) Program Award - Police 
Captain 
  
7. 
Acceptance of FAA/NHDOT Grant Funding – Wildlife Perimeter Fence 
Phase II Construction - Airport Director 
  
8. 
Carry Forward Request - 2026 Unspent Wages - to Support Two One-
time Community Development Department Expenditures - Community 
Development Director 
  
9. 
2025 Hazmat Equipment Grant - Period of Performance Extension - Fire 
Chief 
  
10. 
FY28 Ambulance Replacement - Fire Chief 
  
11. 
LWCF Grant Round 33 Amendment - Skate Park - Deputy City Manager 
  
12. 
Relating to the Execution of an Agreement with KeyNetGPS - City 
Engineer 
  
13. 
Relating to the Execution of a Change Order with Structural Preservation 
Services - City Engineer 
  
14. 
Sale of Surplus Mechanical Ventilators - Fire Chief 
  
  
E. 
CITY MANAGER COMMENTS 
  
  
F. 
REPORTS - CITY OFFICERS AND DEPARTMENTS 
Page 2 of 210

 
 
  
1. 
Proposed Amendments to the Keene Community Power Plan - 
Community Development 
  
  
G. 
REPORTS - BOARDS AND COMMISSIONS 
  
1. 
Proposed Amendments to the Keene Community Power Program — 
Energy & Climate Committee 
  
  
H. 
REPORTS - MORE TIME 
  
1. 
Councilor Williams – Request to Consider Restricting the Sale of 7-
Hydroxymitragynine (7-OH) and Concentrated Kratom Products 
  
  
I. 
ORDINANCES FOR FIRST READING 
  
  
J. 
ORDINANCES FOR SECOND READING 
  
1. 
Relating to Amendments to Article VII. - Food Service Establishments 
Ordinance O-2026-14 
  
  
K. 
RESOLUTIONS 
  
1. 
Relating to the Appropriation of funds for the Marlboro Street & Cheshire 
Rail Trail Improvements Project  
Resolution R-2026-40 
  
  
  
NON PUBLIC SESSION 
  
  
  
ADJOURNMENT 
 
 
Page 3 of 210

08/06/2026 
183 
 
A regular meeting of the Keene City Council was held on Thursday, August 6, 2026. The 
Honorable Mayor Jay V. Kahn called the meeting to order at 7:02 PM. Roll called: Randy L. 
Filiault, Michele A. Chalice, Catherine I. Workman, Bryan J. Lake, Jacob R. Favolise, Laura E. 
Tobin, Robert C. Williams, Philip M. Jones, Kris E. Roberts, Bettina A. Chadbourne, Laura E. 
Ruttle-Miller, Molly V. Ellis, Thomas F. Powers, and Mitchell H. Greenwald were present. 
Edward J. Haas was absent. Councilor Ruttle-Miller led the Pledge of Allegiance. 
 
MINUTES OF THE PRECEDING MEETING 
 
A motion by Councilor Greenwald to adopt the July 16, 2026 minutes was duly seconded by 
Councilor Powers. The motion carried unanimously with 14 Councilors present and voting in 
favor. Councilor Haas was absent. 
 
ANNOUNCEMENTS 
 
Mayor Kahn recognized Councilors Roberts, Powers, and Lake, who all celebrated August 
birthdays. 
 
The Mayor announced upcoming dates of interest in August 2026 and early September 2026: 
• August 8, 2026 from 12:00 PM to 8:00 PM: JamFest at The Colonial 
Theatre/Commercial Street Parking Lot. They are coming back to the Keene area after 
some years in other communities. Mayor Kahn welcomed them back and thanked The 
Colonial for hosting. 
• August 9, 2026: The Sri Chinmoy Oneness-Home Peace Run, an international torch relay 
promoting peace and harmony, will pass through Keene in the mid-afternoon. The Mayor 
suggested meeting at 1:00 PM at Central Square as the time was not confirmed. The 
event celebrates goodwill and mutual respect, while giving participants an opportunity to 
share their hopes for a more peaceful world. If Councilors have that opportunity to greet 
folks on Sunday afternoon, Mayor Kahn asked them to please take advantage of that; 
they may be meeting some people from foreign countries and maybe some from outside 
of our region as well, so he called it a good opportunity. 
• August 15, 2026 from 11:00 AM to 12:30 PM, followed by a Walldogs Mural tour until 
2:00 PM: Dr. Albert Johnston Historic Marker Unveiling at 127 Washington Street. This 
is Keene's first dedication on the Black Heritage Trail 
o The Monadnock Diversity, Equity, Inclusion, and Belonging organization has was 
nominated and earned the designation of a Doctor Albert Johnson Historic Marker 
and that will be unveiled at 127 Washington St. Following this presentation, 
which includes a tour of some artifacts that the family has left in Keene, there will 
be a tour down to the Walldogs mural sometime between 12:30 and 2:00 PM. 
Mayor Kahn called this a real proud moment for the City of Keene, as its first 
stop on the Black Heritage Trail, which has designations throughout the State of 
New Hampshire. He called it a proud moment to recognize a good family and 
person; the family members will be present, and this is not their first time back in 
Keene, so they really have a connection to the City. 
• August 18, 2026 from 4:00 PM to 7:00 PM: Community Night at 350 Marlboro Street. 
Everyone was encouraged to join. Every department helps make this event more 
Page 4 of 210

08/06/2026 
184 
 
engaging and gives residents a chance to learn about the people and services that keep 
Keene running: 
o Festivities will include Touch-A-Truck, other family-friendly activities, and a 
BBQ at no cost to the public. It is always a good opportunity for residents to learn 
about our City departments and the people and the services that are provided by 
the City to the public. 
• August 29, 2026 at 9:00 AM: Community Kitchen’s Walk to Squash Hunger. Mayor 
Kahn encouraged making it a community wide activity 
• September 5, 2026: 
o 11:00 AM to 10:00 PM: Keene Music Festival 
o 10:00 AM: Art in the Park at Ashuelot River Park 
• September 15, 2026 from 5:30 PM to 7 PM: Robinhood Park design public input session 
on the park (not the pool) would be held at the Keene Recreation Center 
• September 8, 2026 from 8:00 AM to 7:00 PM: State Primary Election. Individuals were 
encouraged to make plan, to visit City Clerk’s webpage for any additional information 
that they might need relative to voter registration, and to remember to bring a valid ID 
 
The Mayor provided a reminder that Council break would be starting after tonight's Council 
meeting and extend through Labor Day on September 7, 2026. The Council would return from 
break with meetings of the Planning, Licenses and Development Committee on September 9, 
2026 and Finance, Organization and Personnel Committee on September 10, 2026. 
 
Mayor Kahn provided some thanks for the Monadnock 250 celebration. It brought out more 
people than he had ever seen for a parade and festival in the City of Keene, maybe barring a 
Pumpkin Festival. He extended his sincere appreciation to the many individuals and 
organizations whose hard work and dedication made the Monadnock 250 Celebration and Fourth 
of July Parade such a tremendous success. He gave a special shout out to the chairperson and 
City Councilor, Molly Ellis, for her leadership. The Mayor said it took someone at the lead to 
gather all the thoughts that many people contributed to the event, and ultimately vet those ideas, 
and put them together to make the event work. Mayor Kahn commented on all the other people 
who contributed, noting that Councilor Ellis held a thank you for members of the Committee. 
The Mayor wanted to shout out to those members: 
• Ben Hays: a student at Keene High School who was the tech and website developer, and 
always answered the call to put together a nice script for the public to easily get engaged 
• Councilor Ed Haas, who coordinated the bicycle ride with kids and their families 
• Janelle Sartorio, who coordinated the 4 on the 4th event with Pathways for Keene and 
made sure that we were not duplicating expenses across organizations 
• Jay House with Arts Alive, who did a lot of publicity work 
• Jenna Carol from the Historical Society of Cheshire County, which was the fiduciary 
agent and handled all the bill paying, as well as just participated in the day and the lead 
up to the day when the Historical Society of Wyman Tavern could be open to the public 
and organized programs through the Historical Society 
• Justin Somma, who was the voice of downtown Keene and merchants during the festival 
and the lead up 
• Keith Marks and The Colonial Theatre, who opened up the theatre for The Sandlot movie 
showing and a cooling spot for people who needed it that day 
Page 5 of 210

08/06/2026 
185 
 
• Kelsey Milden, who helped Kürt Blomquist. Mr. Blomquist was so important; his 
experience with parades and organizing closures of our streets for festivals was 
irreplaceable. Ms. Milden was an assistant for him with that. 
• Kristen Noonan, who represented a major donor to the overall planning but also brought 
additional Savings Bank of Walpole volunteers into the work. He called her a real 
contributor. 
• Kevin Watterson and the Keene Swamp Bats, who were present for the parade and did a 
great fireworks show in advance and helped with publicity coordination 
• Mark Rebillard for the Keene Downtown Group, which was the sponsoring organization 
for the license 
• Mike Prince and other Keene High School students who helped organize the vendors for 
the day 
• Nancy Howard, who brought the Daughters of American Revolution into the festival and 
provided a voice for entertainment 
• Keith Thibault, who joined and participated in organizing the Parade 
• Terry Clark was the connection to Cheshire County and other municipalities in the region 
who participated in this event, and he cleared the way for this date to not have too many 
conflicts with other towns 
• Sean Burke at The Keene Sentinel was valuable in helping with the design of the logo 
and placing ads in The Sentinel 
• The Mayor was glad he could help with publicity and fundraising for the event 
• Mayor Kahn recognized the outstanding efforts of the Public Works Department, whose 
staff worked behind the scenes to prepare for and support the event, with special thanks 
to Dan Mooney, Public Works Highway Foreman, for his leadership and coordination 
• Finally, thank you to the Keene High School Youth Council for their enthusiasm, 
volunteer spirit, and contributions to making this community celebration a success 
reading the Declaration of Independence 
 
Mayor Kahn noted that David Tubner, a videographer in the City of Keene, posted a 12-minute 
recap of the parade on YouTube. The Mayor called it great and had reached out to Mr. Tubner to 
try getting a copy of it for the City’s archives and to place it at the Historical Society of Cheshire 
County. The Mayor said we want to commemorate this event and this video is a fitting tribute to 
our shared history in our community, in our nation, and an event that no doubt people in Keene 
will remember for years and hopefully 50 years for those who are around to try to replicate and 
surpass the efforts of 2026. He thanked everyone for their participation and thanked Councilor 
Ellis again. 
 
PROCLAMATION – FIRST RESPONDERS 
 
Mayor Kahn welcomed Jim Coppa and Jimmy Tempesta, organizers of Keene First Responders 
Appreciation Day, which they organize with the various emergency response departments 
throughout the County (this year the event is on August 8, 2026, and is open to the public, and is 
being held at Keene Alumni Field). The Mayor read into the record and presented Mr. Coppa and 
Mr. Tempesta with copies of a Proclamation declaring August 16, 2026 as First Responder 
Appreciation Day in Keene and encouraged all residents to recognize and celebrate the 
Page 6 of 210

08/06/2026 
186 
 
dedication and service of the Monadnock Region’s first responders to our communities. He 
thanked Mr. Coppa and Mr. Tempesta. 
 
Mr. Tempesta called this a great honor. He said this was not about this Proclamation; it is about 
what they are doing for the community and the people. It just amazes him that these first 
responders get up every day, put on their uniforms, and go out to protect us and help to save us. 
He said they really need recognition and this is a way to give back to them. He mentioned the 
dinner at his restaurant that was held for the first responders and their families. He said it is nice 
to see them all come together because they are all family. Mr. Tempesta thought it was amazing 
that the City was recognizing him and Jim Coppo for this and he could not thank the Council 
enough, stating that it meant a lot and would make him try even harder now that everyone was 
recognizing this. 
 
Mr. Coppo thanked the Mayor for having them here for this Proclamation, stating that it meant 
an awful lot. He remembered the first day four years prior when they first tried to pull this off 
and said it had gotten bigger and bigger since. He said this is a blue carpet event for law 
enforcement and their families and is a special event to them. It includes the firefighters, police 
officers, EMTs, and the emergency service people. He said they come and have the time of their 
lives, and they get to see the public appreciate them. More importantly, the public gets to see 
them on a different level and a different note. Mr. Coppo said he and Mr. Tempesta have the 
time of their lives, are privileged to do this, and could not do it without the Council. He thanked 
the Council for having them here. 
 
PRESENTATION - CITY-WIDE REVALUATION - CITY ASSESSOR 
 
Mayor Kahn welcomed City Assessor Dan Langille for a presentation on the Citywide 
revaluation. Mr. Langille introduced Steve Whalen, who works with Vision Government 
Solutions, who was the contractor for this project. Mr. Langille was sure the Council had been 
anticipating that they had been hard at work doing revaluations over the past year and now they 
were taking the important step of getting the public involved and providing them with their 
updated values. Before doing that, he wanted to give the Council an update on what had been 
done. Mayor Kahn noted that Councilors had reference materials on their desks, which the public 
would have access to after this presentation. 
 
Mr. Langille began with an introduction and background on what revaluation is. It is the process 
of assessing all the property in Keene to reflect the current market value as of a certain date. In 
New Hampshire, that was April 1, 2026. He explained that they do this by a process called Mass 
Appraisal, where they value groups of property using common data, standardized methods, and 
statistical testing. He said most people are probably more familiar with a single property 
appraisal, when you buy a home or get a remortgage—your house is compared to three or four 
comparables. In this case, the City does that on a much larger scale for the entire community, 
looking at hundreds of sales and various data points and then apply that equally amongst all the 
properties in the City. Last time this was done was 2021, and so when people see their tax bill 
now, that value is much lower than what a house is selling for today because that reflects the 
market of 2021. So, he said it is not really an adjustment over one year, it is really an adjustment 
Page 7 of 210

08/06/2026 
187 
 
over five years. Mr. Langille said it would be a significant increase over that time and that was 
why there was such a large adjustment. 
 
Next, Mr. Langille explained that there are benefits of doing the revaluation. The City is required 
by the State of New Hampshire to do a revaluation every five years, and the City is required to 
assess property at full market value. He said there are good reasons to do this: because we are 
setting values as of a certain date, over time the market continues to fluctuate, there are different 
economic factors, there are market forces at play, and so over time, the value of your property or 
value of certain properties may rise higher or lower than others. So, he said the City’s 
responsibility is to make them all at the same level: to bring everybody at the same market level. 
When this exists, this is how the City provides an equal and fair tax burden according to the state 
law. The other real benefit of doing a revaluation that Mr. Langille thinks is important is this is a 
public process and there is transparency. He said if you are getting a large tax bill once or twice a 
year, it is important to know how the City came up with that value and what that money is going 
toward. 
 
Mr. Langille noted that one of the first steps in the revaluation is the data collection process. This 
is something that is ongoing for the Assessing Department; they are always looking at building 
permits, properties that have sold, and have an ongoing data verification process that they have 
started. They are looking at every property regardless of whether it is sold or has a building 
permit just to make sure the data is up to date. For the revaluation specifically, the Assessing 
Department had been inspecting sales over a two-year period, during which time there had been 
hundreds of them. For commercial properties, they send out questionnaires looking for income 
and expense information. They are not really interested in what a business makes but are 
interested in the value of real estate. So, they look at what they get for rent, what their operating 
costs are, and what capital is and capitalization rates are. He said they did get some responses for 
that. The Department also looks at other public sources that have multiple listing services, and 
research vacancy rates and capitalization rates. So, the Assessing Department was taking any 
source of data that it could from anywhere it could. 
 
Next, Mr. Langille summarized the market analysis and valuation, stating this is where most of 
the work happens. There are three approaches to value what they look at. They look at the sales 
approach, which is the one most people are familiar with; this is looking at what properties are 
selling and making comparisons to other properties that are like it. There is also the income 
approach, and this is used more for commercial properties; this is where they look at how much 
it takes to operate, upkeep, and get a return on investment on commercial property. The third is a 
cost approach, which is not used much, but Mr. Langille said they do look at replacement cost, 
depreciation, and land value. He said that is more useful for newer homes. 
 
As Mr. Langille mentioned, they do an in-depth study of the City sales over two years and break 
that out into many different strata, looking at different styles, conditions, quality, location, and 
neighborhoods. We start by breaking that down into various tables and adjustments and they do a 
similar kind of analysis for income and expenses. From the building and land values, they make 
different adjustments for location; location is a huge factor in a properties value. Then, they look 
at our building values, starting with building overall costs, and then adjust for things like 
bedrooms, bathrooms, quality, its condition, etc. When they are doing this, they create computer 
Page 8 of 210

08/06/2026 
188 
 
models so they can then apply all these adjustments equally and uniformly across the entire City. 
There is also statistical testing. Additionally, they review all the values in the field, making sure 
that our values are reasonable, and that the data is correct. 
 
Mr. Langille noted that there are often comments such as “how did we come up with this value,” 
but he said the City is not doing that, it is simply analyzing the market. The City is more of a 
historian, reflecting on what the market is doing and is using those adjustments to determine 
what a property is worth. Different types of properties are obviously changing in value at 
different rates: supply, demand, economic forces, and more cause a property to increase or 
decrease at a different rate than another type of property. Last, he said it was important to say 
that the City was going to have some significant increases but Keene was not alone; every 
community that was doing revaluation this year in the State of New Hampshire and probably 
even New England was in a very similar situation. 
 
Mr. Langille explained the preliminary changes for 2026. For the residential side, he cited a 
median increase of about 67% (some will be higher/lower), with multifamily averaging 68% 
increase in value. Condominiums averaging 64% increase in value. And, manufactured homes 
increasing in value up to 140%. He called this a continuation of the low supply of housing, low 
supply of affordable housing, and the resulting demand. He also displayed the median 
assessments to show where the City was in 2021 compared to now, which he thought was 
interesting. For example, the median assessment for manufactured housing in 2021 was $37,200 
and now in 2026 it is $97,800. He also cited significant increases on the commercial side, with 
increases to apartments at 49%, to commercial in general at 31%, and industrial at 29%. He did 
not include the medians because the ranges were so wide (e.g., apartment buildings worth 
$500,000 or up to $18 million), so he said the median did not really tell a story there. Mr. 
Langille said to keep in mind that there was some building permits included in some of these 
rates. So, for the manufactured home, they had been seeing a lot of older units pulled out of the 
park and newer units come in. In that case a home that was valued at $30,000 is replaced with a 
model from $100,000 to $450,000 and that skews the ratio a bit. 
 
Mr. Langille addressed how this would affect property taxes. He said the City does not want to 
take any more or less because of this. The City does not have some big windfall that it now 
determines what it can spend. He reminded us that the City collects money on the tax bills for the 
schools, the County, and the City. He recalled a couple of months prior, when the City Council 
determined the budget for the City; and at that time, the City was predicting an increase in the 
overall taxes. Mr. Langille said revaluation did not erase that. There would still be an increase 
when someone gets their property tax bill. Revaluation is going to maybe add or take away 
depending on the property on top of that. Mr. Langille said it is important not to multiply your 
new value by your current tax rate as it will result in a very large and incorrect number. 
Unfortunately, he said the City does not yet know what that new rate will be because that will be 
set by the Department of Revenue in the fall of 2026. There are still several variables remaining: 
final revenue sources for the year, finalized values, utility values, and more. He believed the tax 
rate was estimated to be around $37 (per $1,000 of value) at budget time. He cited well over $1.2 
billion in new taxable value. So, he said it would not be unreasonable for the tax rate to be in the 
mid to low $20s again, but he could not confirm what it would come out to be. He said this is 
Page 9 of 210

08/06/2026 
189 
 
why the City increased exemptions and credits this past year by about 65%. That was trying to 
keep them in line with what Mr. Langille was seeing for at least the residential side. 
 
Mr. Whalen discussed the next step: the informal hearing process. He said that once someone 
receives their letter in the mail with the new value, they would have multiple options to make an 
appointment. If they do not agree with the value, there will be a website included in the letter and 
you can log on to the website and either make a phone appointment or an in-person appointment 
through that website. That website is available 24 hours per day, seven days per week. If you do 
not have a computer or do not want to do it that way, there will be an 800-number, and you can 
call the call center and decide if it is more convenient to make a phone appointment or an in-
person appointment. Once you have an appointment, you can come in and review how the 
process worked and even review the information on your property record card, which is also 
available on the website; you can look at information on your property or any other property in 
the City. Once they have the hearings, they will send everybody that had a hearing a new 
valuation letter and that is the end of the hearings. If, for example, they find an issue with a 
condominium but someone in that building did not come in for a hearing, everyone in that 
condominium would be adjusted whether they came in or not. Once they send out the new 
revaluation letter, there will be an opportunity to appeal further through the City. 
 
Mr. Langille added that it is only necessary to attend an informal hearing if you feel it is 
necessary or if you are really interested more in what happened. He said to ask yourself, “let’s 
look at that value and put the taxes aside for a minute and say, ‘does this value reflect what I 
could sell it for, or what my neighbors sold their house for recently?’” He said if the value looks 
correct and your information is correct then you do not necessarily need an appointment. If you 
have concerns, then by all means, they want to hear from the public. Something members of the 
public can do is review sales again: look at what has been selling out there, look at what has been 
selling in your neighborhoods. You can use the City website. There are ways to look up sales 
that way. Contact the Assessing Office: Mr. Langille can help anybody through that. You can 
also review similar properties in your neighborhood with their new assessments. Are you making 
sure there is equity there? All that information is going to be available. Finally, he likes to tell 
everyone that it is always important to review your information. It is available online. If there are 
any discrepancies, please call the Assessing Department: they would be happy to come out, look 
at your house and property, and make any necessary changes. They want the assessments to be 
accurate. Mr. Langille expected the public informal hearings to go for several weeks until 
everyone has an ample opportunity to join one if they want to. He was expecting to be able to 
finalize the values by mid-September 2026 and to finalize the utility values by the end of 
September. The new tax rate would come out in November 2026, and these values would be used 
for the final tax bill of the year with a new tax rate. 
 
Councilor Favolise commented on the 67% increase for a single-family home and noted that 
those numbers across the board seemed fairly large to him. He asked the City Assessor to talk 
about how that compares to past five-year cycles. Mr. Langille stated that he would speak to the 
2021 revaluation because it was fresher in his mind. At that point in 2021, we were grappling 
with the COVID pandemic and there was a lot of panic, so there was a pretty good jump at that 
time. He believed the housing market at that time increased about 30% and there were a lot of 
unknowns with the commercial market and more. He thought the commercial properties 
Page 10 of 210

08/06/2026 
190 
 
probably went up 10% at that point. He said it had been a pretty steady pattern and ever since he 
had been doing this that the residential property value increases outpace the commercial property 
value increases and you are constantly seeing a tax shift from your commercial base over to the 
residential side just in the market that we are in. 
 
Councilor Chalice said these are complicated numbers for the public in general. She asked if the 
Assessing Department would be providing a Frequently Asked Questions (e.g., how to log into 
the website) that Councilors could have on hand when they get questions from their constituents 
to help them navigate these initial questions and maybe calm some fears in the process. Mr. 
Langille said the City did that in 2021 and the Department would be refreshing those on the 
Department website to prioritize some guidance, so he would take that into consideration. 
 
Councilor Jones thanked the presenters. He recalled that during the 2021 revaluation, there was a 
big decline in commercial/industrial, which Mr. Langille had explained earlier that more 
responsibility is placed on the residential. He was seeing in the current revaluation that 
commercial was going up 31% and industrial 29%, which he still called better than in 2021. Mr. 
Langille agreed that he recalled an approximate 10% decrease in 2021. He said those categories 
were reacting a little bit differently in this market: small-to-mid-size office spaces were doing 
fairly well, and apartments were doing very well. He said large office buildings were seeing a 
little more difficulty with this economy and business work today; they are not as valuable as they 
once were. He said it was similar with having a hard time attracting large industrial buildings. 
Councilor Jones called it a sign of the times. 
 
Mayor Kahn thanked the presenters. He wanted to ask the total valuation for the City, noting it 
had been at $2.2 billion since 2021. Obviously, he said it was going to go up, but Mr. Langille 
explained that the utility valuations were not yet included, so the Mayor saved his question for 
the upcoming fact sheet. 
 
REPORT - RESIGNATION - DOTTIE MORRIS - HUMAN RIGHTS COMMITTEE 
 
A memorandum was read from Youth Services Manager/JCC Coordinator Alyssa Bender, 
recommending that the Council accept the resignation of Dottie Morris from the Human Rights 
Committee with gratitude for her years of service. A motion by Councilor Greenwald to accept 
the resignation with gratitude for service was duly seconded by Councilor Powers. The motion 
carried unanimously with 14 Councilors present and voting in favor. 
 
NOMINATION – HUMAN RIGHTS COMMITTEE 
 
Mayor Kahn nominated Julie Odato to change from an Alternate to a Regular member of the 
Human Rights Committee, with a term to expire December 31, 2028. The Mayor tabled the 
nomination until the next regular meeting. 
 
COMMUNICATION - PAUL ALLEN-WEBBER - REQUEST TO REEVALUATE DOG 
RESTRICTIONS DURING THE PUMPKIN FESTIVAL 
 
Page 11 of 210

08/06/2026 
191 
 
A communication was received from Paul Allen-Webber, requesting the City Council consider 
removing dog restrictions during the Pumpkin Festival from the City Code of Ordinances. He 
asks that the City instead focuses on enforcing standard leashing and behavior rules, allowing 
responsible local pet owners and visitors to enjoy the City of Keene year-round. Mayor Kahn 
referred the communication to the September 9, 2026 Planning, Licenses and Development 
Committee meeting. 
 
COMMUNICATION - KENNETH KOST - REQUEST FOR A COMPREHENSIVE 
PLANNING STUDY OF THE GILBO AVENUE SITE PRIOR TO SOLAR PAVILION 
DEVELOPMENT 
 
A communication was received from Kenneth Kost requesting that the City conduct a 
comprehensive planning study of the 1.9-acre Gilbo Avenue site before finalizing the layout of 
the solar pavilion. Mayor Kahn referred the communication to the September 23, 2026 
Municipal Services, Facilities and Infrastructure Committee meeting. 
 
COMMUNICATION - WARREN STEINBERG - REQUEST FOR TEMPORARY FREE 
PARKING WITHIN ACTIVE DOWNTOWN CONSTRUCTION ZONES 
 
A communication was received from Warren Steinberg, requesting that the City Council 
consider adopting a temporary free parking policy for all public parking spaces located within an 
active downtown construction area during the current downtown infrastructure project. He 
further comments that he believes this request is consistent with Resolution R-2015-11, the City 
Council Policy Relating to Free Parking. Mayor Kahn referred the communication to the 
September 10, 2026 Finance, Organization and Personnel Committee meeting. 
 
COMMUNICATION - COUNCILOR JONES - REQUEST FOR CONSIDERATION OF AN 
ORDINANCE ESTABLISHING A TEMPORARY MORATORIUM ON DATA CENTERS 
AND CRYPTOCURRENCY MINING FACILITIES 
 
A communication was received from Councilor Philip Jones, formally requesting that the City 
Council direct the appropriate staff and committees to draft an ordinance establishing a 
temporary, two-year moratorium on the construction, development, and operation of Data 
Centers and Cryptocurrency Mining Centers within the City of Keene. He reasons that a two-
year moratorium will grant our City the necessary time to gain a comprehensive, transparent, and 
proactive understanding of these intensive industries before they establish a permanent footprint 
in our community. Mayor Kahn referred the communication to the September 9, 2026 Planning, 
Licenses and Development Committee meeting. 
 
COMMUNICATION - COUNCILOR TOBIN - REQUEST FOR ROADWAY SAFETY 
ACTION PLAN UPDATE 
 
A communication was received from Councilor Laura Tobin, requesting that City staff present 
the annual Roadway Safety Action Plan update to the Municipal Services, Facilities and 
Infrastructure Committee, consistent with the Plan's annual reporting provisions. Mayor Kahn 
noted that this communication was already referred to the September 23, 2026 Municipal 
Page 12 of 210

08/06/2026 
192 
 
Services, Facilities and Infrastructure Committee Meeting during the previous Council Meeting 
of July 16, 2026. 
 
MSFI REPORT - ROBIN HOOD PARK RENOVATION - CHA PHASE 1 PRESENTATION - 
PARKS & RECREATION DIRECTOR 
 
A Municipal Services, Facilities and Infrastructure Committee report was read, unanimously 
recommending the City Council approve the final design of the project and authorize the City 
Manager to do all things necessary to bid and construct that design, as recommended by City 
staff and the City’s consultant engineer, CHA. A motion by Councilor Greenwald to carry out 
the intent of the Committee report was duly seconded by Councilor Workman. 
 
Mayor Kahn recalled that further public input on the remaining designs would take place on 
September 15, 2026 at the Recreation Center. 
 
The motion carried unanimously with 14 Councilors present and voting in favor. Councilor Haas 
was absent. 
 
MSFI REPORT - EVERSOURCE ENERGY - REQUEST FOR TEMPORARY ACCESS AND 
USE OF OLD GILSUM ROAD FOR EVERSOURCE TRANSMISSION STRUCTURE 
REPLACEMENT PROJECT 
 
A Municipal Services, Facilities and Infrastructure Committee report was read, unanimously 
recommending that the City Manager be authorized to negotiate and execute agreements with 
Eversource Energy for the removal of a portion of the stone wall marking the boundary between 
Parcel #218-006 and #212-030; and for an access agreement to allow construction of a temporary 
gravel road on Old Gilsum Road. A motion by Councilor Greenwald to carry out the intent of the 
Committee report was duly seconded by Councilor Workman. 
 
Mayor Kahn recalled this being accessed by Timberlane Drive. Councilor Greenwald added Old 
Gilsum Road. 
 
The motion carried unanimously with 14 Councilors present and voting in favor. Councilor Haas 
was absent. 
 
MSFI REPORTS - PROPOSED RUMBLE STRIPS ON ROUTE 12 AND ROUTE 9 - PUBLIC 
WORKS DIRECTOR; ROADWAY SAFETY AUDIT - INTERSECTION OF ROUTE 9 AND 
WHITCOMB'S MILL ROAD - PUBLIC WORKS DIRECTOR; AND RESTRICTING 
VEHICULAR ACCESS TO WASTEWATER TREATMENT PLANT DRIVEWAY - PUBLIC 
WORKS DIRECTOR 
 
The first Municipal Services, Facilities and Infrastructure Committee report was read, 
unanimously recommending the report from the New Hampshire Department of Transportation 
relating to Proposed Rumble Strips on Route 12 and Route 9 be accepted as informational. A 
second Municipal Services, Facilities and Infrastructure Committee report was read, 
unanimously recommending the New Hampshire Department of Transportation’s Report relating 
Page 13 of 210

08/06/2026 
193 
 
to Roadway Safety Audit for the Intersection of Route 9 and Whitcomb's Mill Road be accepted 
as informational while recommending Concept 1 with the hope for lighting. A third Municipal 
Services, Facilities and Infrastructure Committee report was read, unanimously recommending 
the Public Works Director’s report on Restricting Vehicular Access to the Wastewater Treatment 
Plant Driveway be accepted as informational. 
 
Councilor Greenwald noted that there was an intense three-hour MSFI meeting that got into a lot 
of things. He pointed out item D5 with the Wastewater Treatment Plant (WWTP) driveway. He 
stated that there would still be access for people that want to walk it day or night and to drive it 
during open business hours. He thought those photographing birds would be there during the day 
when it is open anyway. This would prevent drag racing at night, which was concerning the 
Swanzey Police. Mayor Kahn said the photos provided to the Committee aptly described the 
story. 
 
Mayor Kahn accepted the three reports as informational. 
 
MSFI REPORT - AIRPORT TERMINAL RENOVATIONS - DEPUTY CITY MANAGER 
 
A Municipal Services, Facilities and Infrastructure Committee report was read, unanimously 
recommending the City Manager be authorized to execute an Authorization to Submit a Pre-
application for the fall funding cycle of the Northern Borders Regional Commission’s Timber for 
Transit grant program for the Dillant-Hopkins Airport terminal building. A motion by Councilor 
Greenwald to carry out the intent of the Committee report was duly seconded by Councilor 
Workman. 
 
Mayor Kahn called this a big plan and a great renovation. He pointed out the size of the grant at 
more than $4.5 million, and the City’s portion is just a fraction of that. He said it is quite an 
upgrade to the facility, which he thought everyone would agree could really help. 
 
The motion carried unanimously with 14 Councilors present and voting in favor. Councilor Haas 
was absent. 
 
MSFI REPORT - DOWNTOWN INFRASTRUCTURE PROJECT UPDATE - PUBLIC 
WORKS DIRECTOR 
 
A Municipal Services, Facilities and Infrastructure Committee report was read, unanimously 
recommending the Downtown Infrastructure Project Update be accepted as informational. Mayor 
Kahn filed the report as informational. 
 
The next Coffee and Construction update would be August 12, 2026 at 9:00 AM (location to be 
determined). 
 
FOP REPORT - 79-E 112 WASHINGTON ST: WAIVING CITY'S CLAIM AGAINST 
PROCEEDS FROM CASUALTY AND FLOOD INSURANCE 
 
Page 14 of 210

08/06/2026 
194 
 
A Finance, Organization and Personnel Committee report was read, unanimously recommending 
that the City Council forgo the right to include a lien against proceeds from casualty and flood 
insurance in the covenant to be recorded for the 79-E Community Revitalization Tax Relief 
previously granted to 112 Washington LLC. A motion by Councilor Powers to carry out the 
intent of the Committee report was duly seconded by Councilor Chadbourne. 
 
Councilor Powers disclosed that this property owner is a distant family member but that the 
Councilor has no part in this building and in prior discussions at Committee, nobody seemed to 
think it would be a conflict. He did not think he needed to be recused and there were no 
comments from the Council. 
 
The motion carried unanimously with 14 Councilors present and voting in favor. Councilor Haas 
was absent. 
 
FOP REPORT - 79-E 34 COURT LLC: WAIVING CITY'S CLAIM AGAINST PROCEEDS 
FROM CASUALTY AND FLOOD INSURANCE 
 
A Finance, Organization and Personnel Committee report was read, unanimously recommending 
that the City Council forgo the right to include a lien against proceeds from casualty and flood 
insurance in the covenant to be recorded for the 79-E Community Revitalization Tax Relief 
previously granted to 34 Court LLC. A motion by Councilor Powers to carry out the intent of the 
Committee report was duly seconded by Councilor Chadbourne. The motion carried 
unanimously with 14 Councilors present and voting in favor. Councilor Haas was absent. 
 
FOP REPORT - REQUEST TO CARRY FORWARD FISCAL YEAR 2026 PERSONNEL 
FUNDS FOR CITY CLERK'S OFFICE RENOVATIONS - DEPUTY CITY CLERK AND 
ASSISTANT CLERK 
 
A Finance, Organization and Personnel Committee report was read, unanimously recommending 
that the City Council authorize the City Clerk to carry forward $22,000 in unexpended Fiscal 
Year 2026 personnel appropriations and repurpose those funds to augment the City Hall 
Structural Repairs Capital Improvement Project for City Clerk's Office renovations that address 
accessibility, customer service, operational efficiency, and security concerns. A motion by 
Councilor Powers to carry out the intent of the Committee report was duly seconded by 
Councilor Chadbourne. 
 
Councilor Jones asked where the City Clerk’s Office would be temporarily located for those 
three to four months. The City Manager said that decision was not finalized yet; they were 
looking at a couple of different locations, one in very close proximity to City Hall. 
 
The motion carried unanimously with 14 Councilors present and voting in favor. Councilor Haas 
was absent. 
 
CITY MANAGER COMMENTS 
 
Page 15 of 210

08/06/2026 
195 
 
The City Manager, Elizabeth Ferland, reported that the City Council might have likely seen 
recent media reports concerning cybersecurity attacks targeting water and wastewater 
infrastructure in several states. The City has also received alerts from the New Hampshire 
Department of Environmental Services (DES) regarding these threats and recommended 
measures to strengthen system security. She said we are fortunate to have a highly capable IT 
Director and team. This evening, she asked the IT Director to provide a brief overview of the 
recent attacks and a general update on the measures the City takes to protect our systems and 
infrastructure. 
 
IT Director Andrew Mueller said he was present to talk about the situation for the City’s water 
and wastewater, what IT is doing to protect that from a cybersecurity standpoint, and how that 
relates to what is happening in the news related to Iranian cyber-attacks. He said it was important 
to know that this is not necessarily something new. Anybody that has been watching 
cybersecurity for the last bunch of years, he said the professionals had been screaming from the 
rooftops that these wastewater and water plants are the vector of attacks where the bad guys are 
aiming their stuff. Most of the time, he said it had been China that that has really been taking up 
all that bandwidth and Iran had been in the shadows, but they have been doing this as well. Now, 
with the war with Iran, Mr. Mueller felt they had doubled their efforts. They had some successful 
security breaches make the news, but again, this is something IT had been dealing with for a 
while, so the protections put forth did not begin yesterday; there had been years of buildup. Mr. 
Mueller talked briefly about what Iran was doing to other facilities and how, and from a broad 
standpoint, what the City was doing to mitigate. 
 
First, Mr. Mueller talked about programmable logic controls (PLCs), which are little devices 
spread throughout Wastewater and Water Treatment Plants to control things like valves, pumps, 
and motors. Iran finds PLCs that are accessible from the internet and starts manipulating them. 
As far as what he had researched, there had not been any contamination, but they are looking for 
disruption (e.g., running multiple motors until they die). There could even be disruptions to 
multiple plants simultaneously, creating supply and demand issues. These create real disruptions 
in water delivery when you need to find the implementers who put those motors in, for example. 
So, he said that seemed to be the Iranian goal, and they had certainly made the news doing it in a 
couple of locations. Unfortunately, he said these organizations need PLCs on the internet 
because plants the size of Keene’s cannot be staffed 24/7 and there needs to be a way for the 
plant alarm in the night to page out to the operator on call so they can get on their laptop and see 
if it is a serious issue. Unfortunately, everything he described there happens over the internet, so 
that is why there is the existing problem. He said IT’s goal is to make sure that they put a lot of 
different types of hurdles and security measures between the PLCs that control everything and 
the internet. Mr. Mueller said that includes the easy stuff like hard passwords to crack and dual 
authentication, so it is not a one-step process. He said that harkens to the fact that the Public 
Works crews at the Water Treatment Plants have done an amazing job learning all these new 
processes; as security goes up, convenience goes down. So, there can be pushbacks, but the staff 
had worked over the past three to four years to really help secure the infrastructure, with swiftly 
changing processes. Mr. Mueller was really proud of this partnership with them. They have 
something called penetration or PEN testing, which is done internally. The City hires external 
organizations like the Department of Homeland Security’s Cybersecurity and Infrastructure 
Security Agency (CISA). They provide free services for municipalities; they come to the 
Page 16 of 210

08/06/2026 
196 
 
Wastewater Treatment Plant and do audits both internal and external like penetration testing. It is 
a really great resource, and it usually gives the City a long To Do List; some things are usually 
within the City's Budget, and some things are often over the City's budget. Mr. Mueller said they 
are always trying to make things more secure; there is no finish line. There is not a time when 
they evolve out of there being bad guys; he wishes there was. He welcomed questions. 
 
Councilor Williams asked Mr. Mueller to explain the term “penetration testing” for people who 
did not know it. Mr. Mueller replied that the City hires a company to basically try and hack the 
organization. They use readily available tools, and they are not provided with any credentials or 
hints They are called ethical hackers; they come up with a whole list of ways that they are able to 
get into the City's system. Sometimes they cannot get in, they are allowed to get in and see how 
far they can go. There is a whole process to it and it results in a nice report at the end so the City 
knows who to watch out for. 
 
Councilor Jones asked to change the subject a little bit because he knew that a lot of 
municipalities around the country had been victims of ransomware and that cybersecurity was 
helping with preventative measures. He asked if the City and others were still working against 
that. Mr. Mueller said it is still out there again, but the workforce had been halved in some 
departments, so it had been tough. He said CISA would be a resource for incidents in the State of 
New Hampshire. 
 
Councilor Tobin  thought the public might be concerned about some of these things and may be 
concerned about potential risk and how the public might be notified. She also asked if the public 
could sign up for any alerts. The City Manager said she would treat this, depending upon the 
situation, as if it was just direct disruption. She said the City would handle that probably a little 
differently but still likely go back to the water incident when the City had the tools that it used to 
communicate with the public for social media and text messaging. The City is now on the State 
of New Hampshire's text messaging system so the City would use all of those same tools 
 
Mayor Kahn thanked the City Manager and Mr. Mueller for the timely update. 
 
The City Manager provided another update. She said there would be a community conversation 
on August 22, 2026 at 10:00 AM in Heberton Hall and that everyone was invited. It would be 
hosted by the Keene Family YMCA and the Keene Public Library. This would be an opportunity 
to share ideas, meet with your neighbors, and explore new ways to strengthen connections in the 
community. There would be no need to register for this event unless you are interested in 
childcare, in which case you must register before August 17, 2026 for free childcare (please 
contact Amy Kramer at the Library). 
 
The City Manager also announced that the City was about to start its compensation study. She 
briefly updated the City Council on it, and mentioned that the City Council received an e-mail 
about this topic. The City had selected Paypoint HR to review its job classifications, its internal 
equity, and its competitiveness with other comparable employers. The process begins with 
briefings for leadership and employees, which would be happening over the next few weeks 
followed by an employee questionnaire focused on their position responsibilities. That 
questionnaire would take a look at their current job descriptions and whether or not those 
Page 17 of 210

08/06/2026 
197 
 
descriptions are still accurate. The City Manager had provided a copy of the questionnaire to the 
City Council, in addition to the sample letter that would be going out to employees within the 
next week or two. At the conclusion of the study there would be recommendations and 
depending upon what recommendations come out there would be a timeline aligned with the 
City's budgeting process; if there is a need for any sort of adjustments to the pay scale that would 
be something presented to the City Council. 
 
The City Manager noted that a message went out this afternoon that on August 7, 2026 the City's 
Munis software would be going down at 3:00 PM, which would mean the public could not 
register or do any of the activities in its revenue office and the revenue office would need to 
close at 2:00 PM so it could reconcile its system by 3:00 PM. She thanked the Deputy City 
Manager for sending out a message to the public about this so that people could register their 
cars or pay their bills before 2:00 PM. 
 
The City Manager noted that the mayor mentioned the upcoming Peace Run and said that 
interested participants could meet at 1:00 PM on Central Square on August 9, 2026. She added 
that tonight's assessing presentation would be available on the City's website for anyone wishing 
to follow along. 
 
COLLECTIVE BARGAINING AGREEMENTS – CITY MANAGER 
 
A motion by Councilor Powers was duly seconded by Councilor Chadbourne to recommend that 
the City Manager be authorized to do all things necessary to execute the negotiated contract with 
Keene Police Department Supervisors, Teamsters Local 603 to be effective July 1, 2026, through 
June 30, 2030; and further that the City Manager be authorized to do all things necessary to 
execute the negotiated contract with the Professional Firefighters of Keene, NH to be effective 
July 1, 2026, through June 30, 2027. 
 
Mayor Kahn recognized the Human Resources Director, Darcy Newport, for comments. She said 
she had a tentative agreement with two bargaining units to go over with the Council. The first 
was with Keene Police Department supervisors, which is a four-year agreement covering July 1, 
2026 to June 30, 2030. The following revisions have been agreed upon between the City and its 
members: Independence Day has been added as a holiday that will receive compensation at two 
times the hourly rate, the minimum hours for court appearances and special duty pay will be 
increased from three to four hours, vacation accrual has been adjusted to 10 hours per month, the 
percentage of City contributions toward health insurance premiums for option 1 Anthem medical 
coverage will decrease by 1% the first three years and 2% the 4th year and will be eliminating a 
co-pay for HRA benefit, and the City will provide deferred compensation plan of 457 B 
contributions for special duty pay for those hired after July 1 2011. The wage scale has been 
adjusted from a nine-step schedule to a five-step schedule. Those increases vary by member, but 
roughly 5.15% average. 
 
The second tentative agreement is with the firefighters. It is a one-year contract beginning July 1, 
2026 through June 30, 2027. The following revisions have been agreed upon between the City 
and the members: Thanksgiving Day and Christmas Day have been added as holidays and will 
receive compensation at two times the hourly rate, the percentage of City contributions toward 
Page 18 of 210

08/06/2026 
198 
 
health insurance premiums for option 1 Anthem medical coverage will decrease by 2% and the 
City will be eliminating co-pay HRA benefit, the opt out payment for waving insurance coverage 
will increase from $5000 per year to $7000 per year, eyewear reimbursements will increase $100 
per year for qualified members, and clothing allowance will increase $50 per year for each 
member. The wage schedule will be adjusted by 3.5%. 
 
The City Manager wanted to recognize Ms. Newport. This was her first experience with 
negotiations, and she had done a great job. One of the things the City Manager appreciated about 
her approach was that she had done a great job explaining why the City could or could not do 
something, which the City Manager thought had helped in the conversation at the negotiating 
table. Mayor Kahn thanked miss Newport for bringing these points to the Council. 
 
The motion carried unanimously with 14 Councilors present and voting in favor. Councilor Haas 
was absent. 
 
REPORTS - CITY OFFICERS AND DEPARTMENTS - ACCEPTANCE OF DONATIONS - 
FINANCE DIRECTOR 
 
A memorandum was read from the Finance Director, Kari Chamberlain, recommending that the 
City Council accept donations totaling $27,196.70, as noted below, and the City Manager be 
authorized to use each donation in the manner specified by the donor. A motion by Councilor 
Powers to accept the donations with gratitude, and that the City Manager be authorized to use 
these funds in the manner specified by each donor was duly seconded by Councilor Chadbourne. 
 
Councilor Powers indicated the donations accepted this evening include the following: 
• $23,686.70 from Revo Casino as part of the Host Community partnership approved by 
City Council on 9/18/2025 
• $2,000 bench donation from Michelle Stitham for the purpose of purchasing and 
installing a bench in Robin Hood Park, honoring Jeremiah "Miah" Crump, a dear friend 
of the community who passed suddenly in May 2025 
• $500 from C&S Wholesale Grocers to offset food expenses for our annual Community 
Night on August 18, 2026 
• $1,000 from Savings Bank of Walpole for the 2026 Keene International Festival 
• $10 from Mike Governor for the "Branch Out for Parks" park forestry program 
 
Councilor Workman asked the City Manager to remind the public where the money from Revo 
Casino would go. The City Manager said that the last time, the City Council voted to apply the 
funds from Revo Casino to a capital project in the Police Department to offset a portion of that 
project. That was just a one-time motion. After the Council accepts these funds, staff would 
come back to the FOP committee with another recommendation as to how to expend these funds. 
 
The motion carried unanimously with 14 Councilors present and voting in favor. Councilor Haas 
was absent. 
 
REPORTS - CITY OFFICERS AND DEPARTMENTS - OPPORTUNITY ZONE 2.0 (OZ 2.0) 
EXPANSION NOMINATION ENDORSEMENT - DEPUTY CITY MANAGER 
Page 19 of 210

08/06/2026 
199 
 
 
A memorandum was read from Deputy City Manager, Rebecca Landry, recommending that the 
City Council direct the Mayor to send a letter of support for Keene's Opportunity Zone 2.0 
Expansion nomination. 
 
A motion by Councilor Greenwald to suspend Section 26 of the Rules of Order to act on this 
item on first reading was duly seconded by Councilor Powers. The motion carried unanimously 
on a roll call vote with 14 Councilors present and voting in favor. Councilor Haas was absent. 
 
A motion by Councilor Greenwald to direct Mayor Kahn to send a letter of support for Keene's 
Opportunity Zone 2.0 Expansion nomination was duly seconded by Councilor Workman. 
 
Mayor Kahn said he got an education on this earlier from the City Manager, noting there are 35 
slots about to be authorized from the Governor and put forward for her approval. There were 
about 50 organizations that were previously designated in the opportunity zone. The City 
Manager said the Mayor was close, but wanted to let the Deputy City Manager explain. The City 
Manager noted that the City of Keene currently has an opportunity zone and every 10 years they 
are reauthorized, which is what the City was attempting to do. She said there are about 50 zones 
and they are identified as census tracts across the State of New Hampshire but only 35 can move 
forward, so there is a competition to be selected and included as an Opportunity Zone for the 
next 10 years. So, right now, the City was preparing an application and working with the 
Monadnock Economic Development Corporation (MEDC) to help support the City in that strong 
application. 
 
Deputy City Manager Rebecca Landry said that the Opportunity Zone (OZ) 2.0 program is quite 
extensive and it takes some time to really learn about and understand what it is and how different 
it is from the OZ 1.0, so she had some notes to share with the Council and was sure there would 
be some questions. Then she said staff was going to ask the Council to suspend its Rules to act 
on the recommendation to direct the Mayor to send a letter of support with the nomination to 
designate two eligible census tracts as OZs in the OZ 2 Planning Program. So, she stressed that it 
is not a municipality or an organization that is eligible for nomination, it is a census tract. She 
said this was necessary tonight because the Council would not meet again before the August 28, 
2026 deadline to submit nominations. In 2018, the southernmost census tract in Keene was 
nominated and received the OZ designation. It runs across the southern border of Keene. The 
state is now accepting nominations for OZ 2.0 and the existing OZ census tract as well as the 
other and Keene are both eligible; that does not mean they will both receive the nomination, but 
the Deputy City Manager still thought it was important to try. She noted that Oz 2.0 had 
substantial changes from 1.0. It makes rural development more appealing to investors looking for 
federal tax breaks on capital gains whereas with 1.0 a lot of those capital gains went to Boston 
and not necessarily to rural communities like Keene. She pointed out that Cody Morrison of 
MEDC was present tonight, who was instrumental in providing essential support and information 
for the nomination regarding potential development projects in the pipeline as well as potentially 
interested investors, so they will be instrumental in helping with this nomination. 
 
The Deputy City Manager talked about what an Opportunity Zone is. She said it is not state and 
it is not local. It encourages private investors to put their capital gains into long-term community 
Page 20 of 210

08/06/2026 
200 
 
projects, which differs for five years and reduces by 30% their federal tax burden on those 
capital gains. So, it is not quite an incentive, and it eliminates the federal tax burden on profit and 
the increase in value of that property after 10 years. So, she said that if they are a patient investor 
and they stick around for 10 years, it is also a good motivator. This is important to meet federal 
low-income criteria specifically where the median family income is no more than 70% of the 
state average or poverty is 20% or higher. It draws private money into areas that might otherwise 
get passed over. Keene has two eligible census tracts. The current one that spans the southern 
border of Keene and the one that is directly above that, which staff can provide more information 
on if the Council needs it. Deputy City Manager Landry discussed why this would be good for 
Keene. First, she said it brings patient capital. So, the investors are required by law to keep their 
money in the property for at least five years in order to get that tax break. It attracts long-term 
investors. It also expands the City's tax base without local tax breaks so, unlike a program like 
79-E, which will delay or abate a portion of the City taxes. Opportunity zones use federal tax 
discounts and the developer pays their full property taxes to the City of Keene from day one, 
which will help grow the City's tax base and helps relieve pressure on the residential property 
taxpayers, which is incredibly important under the new OZ 2.0 rules for rural communities. She 
said that federal incentives give investors a 30% tax discount on invested capital gains and cut 
required building renovation costs from 100% of the initial value to 50%. So, on $1 million 
valued property the improvement needs to be valued at $500,000 or more. In the previous 
program they would have to double the value of the building. Deputy CITY MANAGER Landry 
said she could not support enough the need for the City to submit a nomination to make sure the 
City at least has at least one Opportunity Zone and it ideally two going forward. 
 
Councilor Favolise said the Deputy City Manager mentioned some possible examples that she 
could share with the Council and the public, and asked if she had any of those readily available. 
The Deputy City Manager said she had mathematical examples, but she did not have a building 
example. She said that the Kingsbury property is in the census tract, for example, but it is on the 
wrong side of Marlboro Street for the current opportunity zone. She said that MEDC was helping 
the City pull together a list of potential projects and investors within the new Opportunity Zone 
right now. 
 
Councilor Chalice said the Deputy City Manager mentioned the very important example for the 
community in terms of the Kingsbury property. Counselor Chalice asked if the City had any 
possibilities of petitioning that Opportunity Zone to its boundaries to be adjusted based on 
financial issues. Deputy City Manager Landry said no, the City had asked and asked, and would 
like the answer to be yes, but the answer is no. It is limited to census tracts. Mayor Kahn said 
each census tract needs to meet the qualifications that are set forth relative to income and 
valuations. Deputy City Manager Landry said that is correct and anyone can invest in those 
tracts, they do not have to come through the City or MEDC. The City may not even know if 
someone makes an investment in a property; that is all done separately from the City. 
 
Councilor Tobin asked if this is to support any type of development or specifically lower income 
development; she heard the Deputy City Manager mention median income. The Deputy City 
Manager thought the answer to the Councilor's question was no: that the poverty level or the 
income levels contribute to what makes the census tract eligible, but the development can be 
commercial, it can be market rate housing, or it could be low-income housing potentially.  
Page 21 of 210

08/06/2026 
201 
 
 
The motion carried unanimously with 14 Councilors present and voting in favor. Councilor Haas 
was absent. 
 
REPORT - RESIGNATION - ALEXANDER VON PLINKY - CONSERVATION 
COMMISSION 
 
A memorandum was read from Senior Planner Mari Brunner, recommending that the Council 
accept the resignation of Alexander "Sparky" Von Plinsky from the Conservation Commission 
with gratitude for his years of service. A motion by Councilor Greenwald to accept the 
resignation with gratitude for service was duly seconded by Councilor Powers. The motion 
carried unanimously with 14 Councilors present and voting in favor. Councilor Haas was absent. 
 
MORE TIME - MSFI REPORTS - ERIK MURPHY - PETITION - SAFETY 
IMPROVEMENTS AT THE SOUTH LINCOLN STREET AND ROXBURY STREET 
INTERSECTION; AND GILBO AVE SOLAR PAVILION CONCEPTUAL DESIGN - CITY 
ENGINEER 
 
The first Municipal Services, Facilities and Infrastructure Committee report was read, 
unanimously recommending placing “Petition – Safety Improvements at the South Lincoln Street 
and Roxbury Street Intersection” on More Time to allow for staff to develop options for 
consideration to be presented at the next MSFI Committee meeting on September 23, 2026, and 
direct the City Manager to introduce an ordinance for a four-way stop at this intersection. A 
second Municipal Services, Facilities and Infrastructure Committee report was read on a vote of 
4–1, recommending placing the Gilbo Ave Solar Pavilion Conceptual Design on More Time. 
Mayor Kahn granted More Time for both items. 
 
ORDINANCE FOR FIRST READING - RELATING TO AMENDMENTS TO ARTICLE VII. 
- FOOD SERVICE ESTABLISHMENTS - ORDINANCE O-2026-14 
 
A memorandum was read from Community Development Director Paul Andrus, recommending 
the City Council refer Ordinance O-2026-14 to the Planning, Licenses and Development 
Committee. Mayor Kahn referred Ordinance O-2026-14 to the September 9, 2026 Planning, 
Licenses and Development Committee meeting. 
 
ORDINANCE FOR FIRST READING - RELATING TO THE INSTALLATION OF TWO 
STOP SIGNS ON ROXBURY STREET - ORDINANCE O-2026-15 
 
A memorandum was read from Public Works Director Don Lussier, recommending that 
Ordinance O-2026-15 be referred to the Municipal Services, Facilities and Infrastructure 
Committee. Mayor Kahn referred Ordinance O-2026-15 to the September 23, 2026 Municipal 
Services, Facilities and Infrastructure Committee meeting. 
 
As a point of clarification, Councilor Greenwald said there was not an endorsement of a four-
way stop at Roxbury St. and Lincoln St. The Committee was saying to prepare the Ordinance, 
Page 22 of 210

08/06/2026 
202 
 
and they would talk about it first. Mayor Kahn said it is something staff had done in the past and 
it was a simple straightforward Ordinance anyway that the Council would take up in the future. 
 
RESOLUTION - RELATING TO FISCAL POLICIES - RESOLUTION R-2026-34-A 
 
A Finance, Organization and Personnel Committee report was read, unanimously recommending 
the adoption of Resolution R-2026-34-A. Mayor Kahn filed the report. A motion by Councilor 
Powers to adopt Resolution R-2026-34-A was duly seconded by Councilor Chadbourne. 
 
Councilor Jones referred to the fifth paragraph, where the City Manager is hereby granted the 
authority to appoint a designee temporarily to perform duties and responsibilities of the City 
Manager in his or her absence. He asked if that is a Fiscal Policy or if that should be a personnel 
policy. He said he had no problem with it, but he was wondering why it was in the Fiscal Policy 
and not in the personnel. The City Manager said that was added to the Fiscal Policy a few years 
ago because if she is not here sometimes and a document needs to be signed of financial nature 
like a purchase order or contract, the City Attorney suggested including this language to allow 
the Deputy City Managers to sign those documents in the City Manager's absence. So, the 
language has been in Fiscal Policy since then. 
 
The motion carried unanimously with 14 Councilors present and voting in favor. Councilor Haas 
was absent. 
 
RESOLUTION - RELATING TO THE APPROPRIATION OF WASTEWATER 
TREATMENT PLANT CAPITAL RESERVE FUNDS TO THE WASTEWATER 
TREATMENT PLANT HVAC REPLACEMENT PROJECT - RESOLUTION R-2026-36 
 
A Finance, Organization and Personnel Committee report was read, unanimously recommending 
the adoption of Resolution R-2026-36-A. Mayor Kahn filed the report. A motion by Councilor 
Powers to adopt Resolution R-2026-36-A was duly seconded by Councilor Chadbourne. The 
motion carried unanimously on a roll call vote with 14 Councilors present and voting in favor. 
Councilor Haas was absent. 
 
RESOLUTION - RELATING TO THE ALTERATION OF THOMPSON ROAD - 
RESOLUTION R-2026-37 
 
A memorandum was read from Public Works Director Don Lussier, recommending that the 
Mayor schedule a Site Visit and a Public Hearing on September 17, 2026, and that following the 
Public Hearing Resolution R-2026-37 be referred to the Municipal Services, Facilities & 
Infrastructure Committee and the Planning Board for their review and consideration. Mayor 
Kahn referred Resolution R-2026-37 to the Municipal Services, Facilities and  
Infrastructure Committee and the Planning Board. He scheduled a Site Visit for September 17, 
2026 at 5:30 PM and a Public Hearing to be for September 17, 2026 at 7:00 PM; transportation 
and a light meal would be provided. 
  
Page 23 of 210

08/06/2026 
203 
 
RESOLUTION - ACKNOWLEDGING DR. DOTTIE MORRIS FOR HER YEARS OF 
SERVICE TO KEENE STATE COLLEGE, THE CITY OF KEENE HUMAN RIGHTS 
COMMITTEE, AND THE COMMUNITY - RESOLUTION R-2026-39 
 
A communication was read from Councilor Jones, recommending drafting a Resolution to 
express the City Council's support and acknowledgment of Dr. Dottie Morris for her years of 
service as she strived to make Keene and the Monadnock Region a welcoming and accepting 
community. A motion by Councilor Jones to direct the Mayor to prepare a Proclamation to 
recognize Dr. Dottie Morris for years of service to Keene State College, the City of Keene 
Human Rights Committee, and the community was duly seconded by Councilor Workman. 
 
The Mayor said he was pleased to be able to write this Proclamation after all his years working 
with Dr. Morris at Keene State College. He said she is an amazing person and a great part of this 
community. He said that during the Proclamation, he hoped she would share all her future plans. 
Dr. Morris had agreed to be present for the presentation of the Proclamation on September 17, 
2026. 
 
The motion carried unanimously with 14 Councilors present and voting in favor. Councilor Haas 
was absent. 
 
RESOLUTION - RELATING TO THE APPROPRIATION OF FUNDS FOR THE 
MARLBORO STREET & CHESHIRE RAIL TRAIL IMPROVEMENTS PROJECT -
RESOLUTION R-2026-40 
 
A memorandum was read from the City Engineer Bryan Ruoff, recommending that Resolution 
R-2026-40 be referred to the Finance, Organization and Personnel Committee. Mayor Kahn 
referred Resolution R-2026-40 to the September 10, 2026 Finance, Organization and Personnel 
Committee of September 10, 2026. 
 
NON-PUBLIC SESSION 
 
A motion by Councilor Greenwald was duly seconded by Councilor Powers to go into non-
public session to discuss legal matters pursuant to RSA 91-A:3,II(L), land matters pursuant to 
RSA 91-A:3,II(d), and litigation matters pursuant to RSA 91-A:3,II(e). The motion carried 
unanimously on a roll call vote with 14 Councilors present and voting in favor. Councilor Haas 
was absent. 
 
Mayor Kahn called a five-minute recess at 8:50 PM before the session began at 8:55 PM. The 
public session reconvened at 9:35 PM. 
 
A motion by Councilor Greenwald to seal the minutes of the non-public session held this 
evening as divulgence of the information would render the proposed actions ineffective was duly 
seconded by Councilor Powers. The motion carried unanimously on a roll call vote with 14 
Councilors present and voting in favor. Councilor Haas was absent. 
 
ADJOURNMENT 
Page 24 of 210

08/06/2026 
204 
 
 
Councilor Chadbourne acknowledged how wonderfully Ms. Fitz-Simon had led the meeting in 
the City Clerk’s absence. 
 
There being no further business, Mayor Kahn adjourned the meeting at 9:35 PM. 
 
  
 
 
 
A true record, attest:      
 
 
 
 
 
 
 
 
     Heather Fitz-Simon 
 
 
 
 
 
 
 
     City Clerk, Pro Tem 
Page 25 of 210

 
 
PUBLIC HEARING NOTICE 
 
Notice is hereby given that a Public Hearing will be held before the Keene City Council 
pursuant to a petition from Donald Lussier, Public Works Director of the City of Keene, 
relating to Resolution R-2026-37 for the alteration of the layout of Thompson Road. The 
petition seeks to correct the layout of Thompson Road as a result of the recently 
completed Thompson Road Stabilization project, during which it was determined that the 
traveled path of Thompson Road did not fully align with the Right-of-Way as it was 
originally laid out by the City Council. In two locations, the paved portion of the road 
actually encroached onto the abutting properties. In addition, the construction of retaining 
walls as part of the stabilization project required additional right-of-way width. The 
proposed alteration will add a total of 5,098 square feet (+/-) to the public right-of-way 
and will incorporate all public infrastructure into the layout. 
 
SITE VISIT:  September 17, 2026 at 5:30 PM 
PUBLIC HEARING:  September 17, 2026 at 7:00 PM 
PUBLIC HEARING LOCATION:  Council Chambers, Keene City Hall 
 
Per order of the Mayor and Councilors of the City of Keene, this 6th day of August 2026. 
 
 
 
 
 
 
Attest: 
 
 
 
 
 
 
 
City Clerk 
Page 26 of 210

 
 
C I T Y O F K E E N E 
P U B L I C W O R K S D E P A R T M E N T 
350 Marlboro Street 
Keene, NH 03431 
 
(603) 352-6550 
KeeneNH.gov 
 
PETITION TO ALTER THE LAYOUT OF THOMPSON ROAD 
 
 
To: 
Mayor Jay Kahn and the Keene City Council 
 
 
Your Petitioner, Donald R. Lussier, P.E., Public Works Director, respectfully petitions the Keene 
City Council to alter the layout Thompson Road, a Class V highway located in the City of Keene, 
Cheshire County, New Hampshire, and represents as follows: 
 
1. For the accommodation and convenience of the traveling public, there is occasion for 
the alteration of the historic layout of Thompson Road.   
 
2. Thompson Road is a public highway in the southeast corner of Keene, running from 
State Route 101 to the home formerly occupied by Aaron Thompson.  The original date 
for the layout of the road is unclear from City records, however, the road was re-surveyed 
in 1836 and recorded in the City Clerk’s Highway Records in Volume 1, Page. 43. 
 
3. Thompson Road, as originally laid out, is 2 Rods (33 feet) in width and 100 Rods (1650 
feet) in length. 
 
4. In the spring of 2024, as the City was preparing to construct the Thompson Road 
Stabilization Project, it was determined that the historically traveled roadway did not 
align with the highway laid out by the City.  In two locations, the paved portion of the 
roadway encroached on the abutting parcels.  In addition, since the reconstruction 
entailed building retaining walls, additional right-of-way width was required. 
 
5. It is therefore requested to alter the layout by adding two strips of land to the City’s 
Right-of-Way, affecting a total of three parcels: 
 
a. Tract No. 1: a strip of land encompassing 1,795 square feet (+/-) of Tax Map 
Parcel No. 241-094 
b. Tract No. 2: a strip of land encompassing 699 square feet (+/-) of Tax Map 
Parcel No. 241-095 
c. Tract No. 3: a strip of land, contiguous with Tract No. 2, encompassing 2,604 
square feet (+/-) of Tax Map Parcel No. 241-096 
 
6. The Petitioner is also requesting a waiver of Article 23.2.1 of the City of Keene Land 
Development Code to allow for the conveyance of a highway easement rather than fee-
simple title to the land to be added to the Right-of-Way.  The City does not possess fee 
for land underlying Thompson Road as currently laid out and there is little benefit for the 
City to own two small, noncontiguous strips of land. 
Page 27 of 210

 
 
 
WHEREFORE,  your Petitioner respectfully requests that: 
 
I. 
The City Council, in accordance with the provisions of New Hampshire RSA 231:9-12, 
conduct a public hearing on the proposed alteration of Thompson Road; and, 
II. 
The City Council vote to alter the layout of Thompson Road by adding the following 
tracts of land to the historic layout: 
Tract No. 1 
A certain tract of land situated in Keene, Cheshire County, New Hampshire, bounded and 
described as follows: 
Beginning at a point on the westerly line of Thompson Road, said point being the 
southernmost point on Tax Map Parcel No. 241-094 and the easternmost point 
on Tax Map Parcel No. 241-093; 
Thence N 26°12’26” E along the westerly line of said Thompson Road for a 
distance of 252.16 feet to a point, said point being a 5/8” diameter iron rod, set 
flush with the surrounding pavement;  
Thence S 28°38’17” W for a distance of 34.87 feet to a point said point being a 
5/8” diameter iron rod, set flush with the surrounding earth; 
Thence along a curve to the left whose chord bearing is S 26°21’35”W and whose 
radius is 694.63 feet for a distance of 135.86 feet to a point; 
Thence S 20°45’24” W for a distance of 82.83 feet to the place of beginning. 
Containing one thousand seven hundred ninety five (1,795) square feet, more or less. 
Said tract is depicted as “Proposed ROW Taking #1” on a plan entitled “Thompson Road, 
Keene N.H., Right of Way Boundary Plan, Land Located along the Branch River”, prepared 
for the City of Keene by Bailey Associates, dated 3/21/2025, to be recorded  at the 
Cheshire County Registry of Deeds. 
Tract No. 2 
A certain tract of land situated in Keene, Cheshire County, New Hampshire, bounded and 
described as follows: 
Beginning at a point on the westerly line of Thompson Road, said point being a 1” 
diameter iron pipe set 0.6 feet above the surrounding earth, marking the 
southernmost point on Tax Map Parcel No. 241-095 and the easternmost point 
on Tax Map Parcel No. 241-094; 
Page 28 of 210

Thence N 44°12’34”E along the westerly line of said Thompson Road for a 
distance of 115.38 feet to a point;  
Thence N 47°28’44” W for a distance of 11.01 feet to a point; 
Thence S 39°17’58” W for a distance of 115.48 feet to the place of beginning. 
Containing six hundred ninety-nine (699) square feet, more or less. 
Said tract is depicted as “Proposed ROW Taking #2” on the aforementioned plan. 
Tract No. 3 
A certain tract of land situated in Keene, Cheshire County, New Hampshire, bounded and 
described as follows: 
Beginning at a point on the westerly line of Thompson Road, said point being the 
northeastern most point on Tax Map Parcel No. 241-096; 
Thence S 44°12’34” W along the westerly line of said Thompson Road for a 
distance of 226.92 feet to a point;  
Thence N 47°28’44” W for a distance of 11.01 feet to a point; 
Thence N 39°17’58” E for a distance of 29.87 feet to a point; 
Thence along a curve to the right whose chord bearing is N 46°18’27” E and 
whose radius is 600 feet for a distance of 146.78 feet to a point; 
Thence N 53°18’56” E for a distance of 51.82 feet to the place of beginning. 
Containing two thousand six hundred four (2,604) square feet, more or less. 
Said tract is depicted as “Proposed ROW Taking #3” on the aforementioned plan. 
III. 
The City Council vote to grant a waiver to the requirements of Article 23.2.1 of the Land 
Development Code, requiring a warranty deed conveying fee title; and, 
IV. 
The City Council authorize the City Manager to accept and record deeds for highway 
easements across the above-described tracts of land from the current property owners, 
with the final form and content of said easements to be subject to the review and 
approval of the City Attorney. 
V. 
That the City Council authorize the City Manager to pay damages to the owners of the 
aforementioned tracts as follows; 
a. Tract #1 – Seven Thousand Eight Hundred Forty-One Dollars and Thirty Cents 
($7,841.30) 
b. Tract #2 – One Thousand Ninety Dollars and Forty-Four Cents ($1,090.44) 
Page 29 of 210

c. Tract #3 – Four Thousand Sixty-Two Dollars and Twenty-Four Cents ($4,062.24) 
 
Respectfully Submitted this 4TH  day of August, 2026 
 
 
 
 
Donald R. Lussier, P.E. 
Public Works Director 
 
Page 30 of 210

 
R-2026-37 
CITY  OF  KEENE 
 
 
 
In the Year of Our Lord Two Thousand and              Twenty Six 
 
A RESOLUTION     Relating to the Alteration of Thompson Road 
 
Resolved by the City Council of the City of Keene, as follows: 
WHEREAS: Thompson Road is a public highway in the City of Keene; and 
WHEREAS: There is now occasion to alter the location of Thompson Road by widening the 
existing Right-of-Way to accommodate the historically traveled roadway plus 
improvements constructed as part of the City’s Thompson Road Stabilization 
Project;  
NOW THEREFORE BE IT RESOLVED: 
That the Keene City Council hereby accepts the following tracts of land, identified as 
“Proposed ROW Taking #1, #2 & #3” on a plan entitled “Thompson Road, Keene N.H., 
Right of Way Boundary Plan, Land Located along the Branch River”, prepared for the 
City of Keene by Bailey Associates, dated 3/21/2025, to be recorded at the Cheshire 
County Registry of Deeds. 
Tract No. 1 
A certain tract of land situated in Keene, Cheshire County, New Hampshire, bounded and 
described as follows: 
Beginning at a point on the westerly line of Thompson Road, said point being the 
southernmost point on Tax Map Parcel No. 241-094 and the easternmost point on 
Tax Map Parcel No. 241-093; 
Thence N 26°12’26” E along the westerly line of said Thompson Road for a 
distance of 252.16 feet to a point, said point being a 5/8” diameter iron rod, set 
flush with the surrounding pavement;  
Thence S 28°38’17” W for a distance of 34.87 feet to a point said point being a 
5/8” diameter iron rod, set flush with the surrounding earth; 
Thence along a curve to the left whose chord bearing is S 26°21’35”W and whose 
radius is 694.63 feet for a distance of 135.86 feet to a point; 
Thence S 20°45’24” W for a distance of 82.83 feet to the place of beginning. 
Containing one thousand seven hundred ninety-five (1,795) square feet, more or less. 
Page 31 of 210

Said tract is depicted as “Proposed ROW Taking #1” on the aforementioned plan. 
Tract No. 2 
A certain tract of land situated in Keene, Cheshire County, New Hampshire, bounded and 
described as follows: 
Beginning at a point on the westerly line of Thompson Road, said point being a 1” 
diameter iron pipe set 0.6 feet above the surrounding earth, marking the 
southernmost point on Tax Map Parcel No. 241-095 and the easternmost point on 
Tax Map Parcel No. 241-094; 
Thence N 44°12’34”E along the westerly line of said Thompson Road for a 
distance of 115.38 feet to a point;  
Thence N 47°28’44” W for a distance of 11.01 feet to a point; 
Thence S 39°17’58” W for a distance of 115.48 feet to the place of beginning. 
Containing six hundred ninety-nine (699) square feet, more or less. 
Said tract is depicted as “Proposed ROW Taking #2” on the aforementioned plan. 
Tract No. 3 
A certain tract of land situated in Keene, Cheshire County, New Hampshire, bounded and 
described as follows: 
Beginning at a point on the westerly line of Thompson Road, said point being the 
northeastern most point on Tax Map Parcel No. 241-096; 
Thence S 44°12’34” W along the westerly line of said Thompson Road for a 
distance of 226.92 feet to a point;  
Thence N 47°28’44” W for a distance of 11.01 feet to a point; 
Thence N 39°17’58” E for a distance of 29.87 feet to a point; 
Thence along a curve to the right whose chord bearing is N 46°18’27” E and 
whose radius is 600 feet for a distance of 146.78 feet to a point; 
Thence N 53°18’56” E for a distance of 51.82 feet to the place of beginning. 
Containing two thousand six hundred four (2,604) square feet, more or less. 
Said tract is depicted as “Proposed ROW Taking #3” on the aforementioned plan. 
BE IT FURTHER RESOLVED: 
That the Petitioner’s request for a waiver to the requirements of Article 23.2.1 of the 
Land Development Code to allow conveyance of an easement for highway purposes 
rather than fee title is hereby granted. 
BE IT FURTHER RESOLVED: 
Page 32 of 210

That the City Manager be, and hereby is, authorized to accept and record deeds for 
highway easements across the above-described tracts of land from the current property 
owners, with the final form and content of said easements to be subject to the review and 
approval of the City Attorney. 
BE IT FURTHER RESOLVED: 
That the City Manager be, and hereby is, authorized to pay damages to the owners of the 
aforementioned tracts as follows; 
a. Tract #1 – Seven Thousand Eight Hundred Forty-One Dollars and Thirty Cents 
($7,841.30) 
b. Tract #2 – One Thousand Ninety Dollars and Forty-Four Cents ($1,090.44) 
c. Tract #3 – Four Thousand Sixty-Two Dollars and Twenty-Four Cents ($4,062.24) 
 
 
_________________________________ 
Jay V. Kahn, Mayor 
In City Council August 6, 2026. 
Referred to the Municipal Services, 
Facilities and Infrastructure Committee and  
the Planning Board.   Site visit set 
September 17, 2026, at 5:30 PM.    
Public Hearing set September 17, 2026, at 7:00 PM. 
 
Assistant Clerk 
 
Page 33 of 210

 
 
 
RETURN OF ALTERATION OF THE THOMPSON ROAD LAYOUT 
 
 
A petition requesting the alteration of the Thompson Road Layou having come before the Keene 
City Council, and their having considered the same, all parties having been heard and the 
owners of land over which such highway shall pass having agreed to accept compensation and 
waive their right to any additional damages, it is hearby ordered and adjudged that: 
 
I. 
Public exigency and convenience require that a highway be and the same hereby is laid 
out, taken and appropriated over three tracts of land situated in the City of Keene, 
Cheshire County, New Hampshire.  Said tracts are more particularly bounded and 
described as follows: 
Tract No. 1 
A certain tract of land situated in Keene, Cheshire County, New Hampshire, bounded and 
described as follows: 
Beginning at a point on the westerly line of Thompson Road, said point being the 
southernmost point on Tax Map Parcel No. 241-094 and the easternmost point 
on Tax Map Parcel No. 241-093; 
Thence N 26°12’26” E along the westerly line of said Thompson Road for a 
distance of 252.16 feet to a point, said point being a 5/8” diameter iron rod, set 
flush with the surrounding pavement;  
Thence S 28°38’17” W for a distance of 34.87 feet to a point said point being a 
5/8” diameter iron rod, set flush with the surrounding earth; 
Thence along a curve to the left whose chord bearing is S 26°21’35”W and whose 
radius is 694.63 feet for a distance of 135.86 feet to a point; 
Thence S 20°45’24” W for a distance of 82.83 feet to the place of beginning. 
Containing one thousand seven hundred ninety five (1,795) square feet, more or less. 
Said tract is depicted as “Proposed ROW Taking #1” on a plan entitled “Thompson Road, 
Keene N.H., Right of Way Boundary Plan, Land Located along the Branch River”, prepared 
for the City of Keene by Bailey Associates, dated 3/21/2025, to be recorded  at the 
Cheshire County Registry of Deeds. 
 
 
Page 34 of 210

Tract No. 2 
A certain tract of land situated in Keene, Cheshire County, New Hampshire, bounded and 
described as follows: 
Beginning at a point on the westerly line of Thompson Road, said point being a 1” 
diameter iron pipe set 0.6 feet above the surrounding earth, marking the 
southernmost point on Tax Map Parcel No. 241-095 and the easternmost point 
on Tax Map Parcel No. 241-094; 
Thence N 44°12’34”E along the westerly line of said Thompson Road for a 
distance of 115.38 feet to a point;  
Thence N 47°28’44” W for a distance of 11.01 feet to a point; 
Thence S 39°17’58” W for a distance of 115.48 feet to the place of beginning. 
Containing six hundred ninety-nine (699) square feet, more or less. 
Said tract is depicted as “Proposed ROW Taking #2” on the aforementioned plan. 
 
Tract No. 3 
A certain tract of land situated in Keene, Cheshire County, New Hampshire, bounded and 
described as follows: 
Beginning at a point on the westerly line of Thompson Road, said point being the 
northeastern most point on Tax Map Parcel No. 241-096; 
Thence S 44°12’34” W along the westerly line of said Thompson Road for a 
distance of 226.92 feet to a point;  
Thence N 47°28’44” W for a distance of 11.01 feet to a point; 
Thence N 39°17’58” E for a distance of 29.87 feet to a point; 
Thence along a curve to the right whose chord bearing is N 46°18’27” E and 
whose radius is 600 feet for a distance of 146.78 feet to a point; 
Thence N 53°18’56” E for a distance of 51.82 feet to the place of beginning. 
Containing two thousand six hundred four (2,604) square feet, more or less. 
Said tract is depicted as “Proposed ROW Taking #3” on the aforementioned plan. 
 
 
Page 35 of 210

II. 
The City Council finds that there is occasion and necessity for such layout. 
III. 
The tracts of land hereby laid out shall be added to and become part of the Thompson 
Road Right-of-Way. 
IV. 
These findings and orders shall be recorded in the office of the Keene City Clerk. 
 
 
 
 
___________________________________  
 
_______________________________ 
Jay V. Kahn,  Mayor 
 
 
 
 
Date 
 
 
 
 
Approved as to Description:  
 
 
Approved as to Form: 
 
 
 
 
_________________________________ 
 
 
_________________________________ 
Bryan Ruoff, P.E. 
 
 
 
 
Amanda Palmiera 
City Engineer  
 
 
 
 
City Attorney 
Page 36 of 210

UP 31/4
1" IPF .6' HIGH
TBM #1
ELEV=613.23
TRI-NAIL SET IN UP 1' AGL
TBM #3
ELEV=608.93
ARROW BOLT
ELEV=526.72
TBM #2
TRI-NAIL SET IN 14" OAK
UP 31/3
5/8" RBF 1.1' HIGH
UP 31/8
BM NGS
ELEV=631.51
BRASS DISK
5/8" RBF .7' HIGH DREW
UP 31/7
5/8" RBF .8' HIGH DREW
UP 31/6
5/8" IRF -.1' HIGH
UP 31/10
Δ=4° 12' 28"
R=1004.87'
L=73.80'
W
S59°57'16"W
66.25'
0 Rd
4 Rd
8 Rd
12 Rd
16 Rd
20 Rd
24 Rd
28 Rd
32 Rd
36 Rd
40 Rd
44 Rd
48 Rd
52 Rd
56 Rd
60 Rd
64 Rd
68 Rd
72 Rd
76 Rd
80 Rd
84 Rd
88 Rd
92 Rd
N26°10'E 16 Rd
N44°10'E 22 Rd
N63°40'E 20 Rd
N75°10'E 8 Rd
N37°50'E 14 Rd
N65°10'E 10 Rd
N36°40'E 10 Rd
33'
33'
PC: 80+63.20
PT: 85+33.80
81
82
83
84
85
5/8" RBS FLUSH 1001
5/8" RBS FLUSH 1001
5/8" RBS 1' HIGH 1001
5/8" RBS -0.4' HIGH 1001
3/4" IPF 0.2' HIGH
5/8" RBS FLUSH 1001
5/8" RBS FLUSH 1001
5/8" RBS FLUSH 1001
W
S
O
UP 31/1
S
PROPOSED
ROW Taking #2
699 S.F.
ROW PARCEL
SEGMENTS
TABLE
ID
L4
L5
L6
Length
115.48
115.38
11.01
Bearing
S39° 17' 58"W
N44° 12' 34"E
N47° 28' 44"W
THOMPSON ROAD RIGHT OF WAY TAKINGS
PROPOSED RIGHT-OF-WAY
TAKING #2
FOR TAX MAP 241 LOT 95
(27 THOMPSON ROAD)
PROPOSED
ROW Taking #3
2,604 S.F.
PROPOSED RIGHT-OF-WAY
TAKING #3
FOR TAX MAP 241 LOT 96
(27 THOMPSON ROAD)
ROW TAKING #2: 699 S.F.
ROW TAKING #3: 2,604 S.F.
5/8" RBF .5' HIGH DREW
UP 31/2
PROPOSED RIGHT-OF-WAY
TAKING #1
FOR TAX MAP 241 LOT 94
(17 THOMPSON ROAD)
PROPOSED
ROW Taking #1
1,795 S.F.
ROW PARCEL
SEGMENTS TABLE
ID
C1
L1
L2
L3
Length
135.86
82.83
252.16
34.87
Bearing
Chrd Brg:S26°21'35"W
S20° 45' 24"W
N26° 12' 26"E
S38° 38' 17"W
Curve Radius
694.63
ROW PARCEL
SEGMENTS TABLE
ID
C10
L6
L7
L8
L9
Length
146.78
11.01
29.87
51.82
226.92
Bearing
Chrd Brg:N46°18'27"E
N47° 28' 44"W
N39° 17' 58"E
N53° 18' 56"E
S44° 12' 34"W
Curve Radius
600.00
ROW TAKING #1: 1,795 S.F.
RL17
ROW-L7
5/8" IRF -.1' HIGH
UP 31/10
100 Rd
92 Rd
96 Rd
N37°50'E 14 Rd
1"=50'
50
25
0
50
100
1.
THE PURPOSE OF THIS PLAN IS TO SHOW THE RIGHT OF WAY OF
THOMPSON ROAD, ACCORDING TO CITY OF KEENE HIGHWAY BOOK
#1, RETURN OF LAYOUT AS DESCRIBED AS BEING 2 RODS IN WIDTH,
100 RODS IN LENGTH, AND DESCRIBED BY NON-CURVILINEAR
POINTS OF INTERSECTION AND DISTANCES ONLY.  THE ORIGINAL
RIGHT OF WAY IS SHOWN AS A CENTERLINE USING RODS AS THE
UNIT LENGTH.
2.
IN ADDITION TO THE EXISTING RIGHT OF WAY, A NUMBER OF NEW
RIGHT-OF-WAY TAKINGS ARE NEEDED TO FACILITATE ON GOING
ROAD MAINTENANCE.  THIS PLAN SHOWS THE PROPOSED PARCELS
TO BE ANNEXED TO THE EXISTING RIGHT OF WAY.
3.
THERE ARE TWO APPARENT LOCATIONS WHERE THE HIGHWAY AS
TRAVELED IS LOCATED OUTSIDE OF THE ORIGINAL RIGHT OF WAY,
AND PRESCRIPTIVE EASEMENTS MAY HAVE RIPENED OVER TIME.
4.
AN ASBUILT SURVEY AND RIGHT-OF-WAY BOUNDARY SURVEY WAS
PERFORMED BY THIS OFFICE ON 12/12/2024.  THE AS-BUILT
LOCATIONS OF THE RECENTLY CONSTRUCTED RETAINING WALLS
AND ASSOCIATED SLOPES WITH DRAINAGE WAS LOCATED, AND THE
PROPOSED TAKINGS SHOWN ON THIS PLAT WERE MONUMENTED.
TAX MAP 241 LOT 93
642 MARLBORO RD.
KAREN B. CURRAN
BK.969 PG.152
TAX MAP 241 LOT 94
17 THOMPSON RD.
GREGORY C. WALKER
BK.840 PG.522
TAX MAP 241 LOT 95
27 THOMPSON RD.
ROBERT W. BALL
BK.1155 PG.126
TAX MAP 241 LOT 97
THOMPSON-CHAPMAN
CONSERVATION ASSOC. INC.
BK.2646 PG.16
TAX MAP 241 LOT 98
NORMAN C. KRISTOFF
BK.2646 PG.20
TAX MAP 241 LOT 99
NORMAN C. KRISTOFF
BK.2646 PG.20
1.
BOUNDARY ADJUSTMENT PREPARED FOR KAREN B. CURRAN, KEENE NH AS PREPARED BY
DAVID A. MANN ASSOCIATES, DATED 01/03/1987 AND RECORDED AS CCRD PLAN 521.
2.
BOUNDARY LINE ADJUSTMENT LOTS 241-102-000, 101, 103 & 104, THOMPSON ROAD
KEENE, NH 03431 AS PREPARED BY CARDINAL SURVEYING & LAND PLANNING, DATED
05/22/2023 AND RECORDED AS CCRD PLAN #23049.
3.
EXISTING CONDITIONS PLAN, BULK STORAGE FACILITY, TAX MAP PARCEL 68-1-1, 639
MARLBORO ROAD, KEENE, NH. AS PREPARED BY FIELDSTONE LAND CONSULTANTS,
DATED MARCH 16, 2017 AND ON FILE AT THE CITY OF KEENE.
4.
BOUNDARY ADJUSTMENT PLAN PREPARED FOR JEANNETTE L. GARDNER & GREGORY H.
GARDNER 67 THOMPSON ROAD, AS PREPARED BY DAVID A. MANN, LAND SURVEYOR
DATED MARCH 27, 2007 AND RECORDED AS CCRD PLAN #C13-D06-0085
5.
SUBDIVISION PLAT, MAP 199 LOT 01-1, MAP 901 LOTS 21-6 & 21-28, CHAPMAN AND
THOMPSON ROADS KEENE, N.H. AS PREPARED BY RICHARD P. DREW LLC DATED
08/13/2003 AND ON FILE AT THE CITY OF KEENE.
6.
STATE OF NEW HAMPSHIRE, STATE HIGHWAY DEPARTMENT - PLAN AND PROFILE OF
PROPOSED T.L.R. PROJECT NO. 14117, SOUTH SIDE ROAD, DATED 05/31/1933. ON FILE
AT THE NH DOT ARCHIVES.
TAX MAP 241 LOT 105
ANTIOCH UNIVERSITY
BK.2190 PG.411
TAX MAP 241 LOT 96
OTHER LAND OF BALL
BK.1810 PG.805
SCALE: 1"=50'
TAX MAP 241 LOT 102
67 THOMPSON ROAD
JESSICA & FRANCIS PIERANNUNZI
BK.2624 PG.361
TAX MAP 241 LOT 101
59 THOMPSON ROAD
MICHAEL R. LAROCHE ET AL
BK.1775 PG.159
TAX MAP 241 LOT 100
HEIRS OF GEORGE A. LAROCHE
BK.1775 PG.159
TAX MAP 241 LOT 103
60 THOMPSON ROAD
JEFFREY & ALLISON GARDNER
BK.1962 PG.474
TAX MAP 241 LOT 104
THOMPSON ROAD
JEFFREY H. GARDNER
BK.3265 PG.1040
CRAIG T. BAILEY L.L.S. #1001
DATE:
I HEREBY CERTIFY THAT THIS SURVEY AND SURVEY PLAT WAS PREPARED BY ME OR THOSE UNDER
MY DIRECT SUPERVISION.
I CERTIFY THAT THIS SURVEY PLAT IS NOT A SUBDIVISION PURSUANT TO THIS TITLE AND THAT THE
LINES OF STREETS AND  WAYS SHOWN  ARE THOSE OF PUBLIC OR PRIVATE STREETS OR WAYS
ALREADY ESTABLISHED AND THAT NO NEW WAYS ARE SHOWN.
I HEREBY CERTIFY THAT I HAVE FILED A COPY OF THIS PLAN WITH THE PLANNING BOARD OF KEENE,
IN ACCORDANCE WITH RSA 676:18 (IV)
I HEREBY CERTIFY THAT THIS PLAN IS A TRUE AND ACCURATE REPRESENTATION OF A THEODOLITE /
EDM SURVEY PERFORMED ON THE GROUND AND UNDER MY DIRECT SUPERVISION DURING 2022 &
2024, AND THAT THE ADJUSTED ERROR OF CLOSURE IS NOT GREATER THAN 1 PART IN 10,000.
EVERY REASONABLE EFFORT HAS BEEN MADE TO PROPERLY ESTABLISH THE BOUNDARIES OF THE
SUBJECT TRACT. THIS CERTIFICATION DOES NOT INCLUDE ANY GUARANTEE OF TITLE.
PLAN CERTIFICATIONS
PROJECT OWNER:
    DATE OF PLAN:
CITY OF KEENE, N.H.
DEPARTMENT OF PUBLIC WORKS
3 WASHINGTON ST.
KEENE, NH 03431
March 2025
DATE
REVISION
INITIALS
DATE
JOB No.
DRAWN BY ;
SCALE ;
BRYAN L. BAILEY ASSOCIATES, INC.
BA
Bailey Associates
land surveying & land planning
engineering & natural resource sciences
www.bailey-associates.com
(603) 528-3734
217 Cotton Hill Rd. Gilford, NH 03249
L
A
N
D
 
S
U
R
V
E
Y
E
N
G
I
N
E
E
R
I
N
G
S
E
P
T
I
C
 
D
E
S
I
G
N
N
A
T
U
R
A
L
 
S
C
I
E
N
C
E
S
SERVING NEW HAMPSHIRE SINCE 1978
SHEET 4 OF 4
RIGHT OF WAY BOUNDARY PLAN
3673
3/21/2025
CTB
03/21/2025
SPIKE FND/SET
UTILITY POLE
WETLAND FLAG
CONCRETE BND.FND/SET
REBAR FND/SET
DRILL HOLE FND/SET
TEMPORARY BENCHMARK
HYDRANT
WETLAND
TP
TEST PIT
CATCH BASIN
D
DRAIN MAN HOLE
TREE STUMP FOUND
PERCOLATION TEST
EXISTING STORM DRAIN
EXISTING SEWER LINE
D
D
S
S
EXISTING WATER
W
W
WELL
W
S
O
WATER SHUTOFF
GV
GATE VALVE
DECIDUOUS TREE
CONIFEROUS TREE
S
SEWER MAN HOLE
LIGHT POLE
GUY ANCHOR
BUILDING SETBACK LINE
SOIL TYPE
TREELINE
STONEWALL
WETLAND
REBAR TO BE SET
CONC. BND. TO BE SET
EDGE OF GRAVEL DRIVE
GRANITE BND. FND/SET
MAGNAIL (PK) FND/SET
STONE ERECT FOUND
STAKE & STONES FND.
IRON ROD FOUND
IRON PIPE FOUND
PERMANENT BENCHMARK
HUB & TACK FND/SET
MAIL BOX
12/30/2024
ASBUILT & PROPOSED EASEMENT ADDED
CTB
03/07/2025
ROW TAKINGS PARCELS REVISED
CTB
THIS PLANSET CONTAINS A TOTAL OF 8 SHEETS.  SHEET NUMBER
8 IS RECORDED AT THE CHESHIRE COUNTY REGISTRY OF DEEDS.
THE REMAINING SHEETS ARE ON FILE AT THE CITY OF KEENE
DEPARTMENT OF PUBLIC WORKS, WHICH IN ITS ENTIRETY,
CONSTITUTE THE SITE PLAN AS APPROVED BY THE PLANNING
BOARD.
MULTIPLE SHEET RECORDABLE ROW PLAN
03/21/2025
SURVEY DATUM
THIS SURVEY IS ORIENTED TO N.H. STATE PLANE GRID NORTH AS DETERMINED BY UTILIZING BAD
ELF "FLEX 5600" DUAL FREQUENCY GNSS (GPS, GLONASS, GALELIO & BEIDOU) RECEIVERS, RTK,
VIRTUAL NETWORK METHODS. OBSERVATIONS WERE TAKEN ON
VERTICAL DATUM: NAVD 88 UTILIZING (GEOID 18).
HORIZONTAL DATUM: NAD83(2011) MULTI-YEAR CORS SOLUTION 2 (MYCS2) EPOCH = 2010.000
BEGIN DATE = 01/01/2020.
REFERENCE FRAME: ITRF2014
11/21/2022
CONCRETE
MASONRY
UNIT
RETAINING
WALLS (TYP.)
03/21/2025
PARCEL TABLES RE-ALIGNED
CTB
G:\3673_JTC-KEENE\dwg\3673_EXISTING_CONDITIONS.dwg, 3/21/2025 8:02:38 AM
Page 37 of 210

 
 
NOTICE OF PUBLIC HEARINGS 
CITY OF KEENE 
 
Notice is hereby given that two Public Hearings will be held on September 17, 2026 at 7:10 
p.m. at Keene City Hall, Second Floor, 3 Washington Street, Keene, NH 03431 to discuss and 
hear public comment on current projects sponsored by the City of Keene under the federal 
Community Development Block Grant (CDBG) program. The projects to be featured include 
1) Keene Housing’s second phase of the redevelopment of the former Roosevelt School site 
at 438 Washington Street known as Roosevelt West, and 2) a planning and feasibility 
assessment of the Cedarcrest Center for Children with Disabilities facility at 91 Maple 
Avenue. 
Interested persons are invited to attend and comment on the projects. If you need assistance 
to attend or participate in the hearing, please contact Elizabeth Ferland, Keene City 
Manager, five days in advance. Anyone wishing to submit written comments should address 
them in writing to the City Manager, City of Keene, 3 Washington Street, Keene, NH 03431 
and submit them by the close of business on the day preceding the hearing. 
Page 38 of 210

 
2026-382 
 
 
CITY OF KEENE 
NEW HAMPSHIRE 
 
ITEM #B.1. 
 
  
   
Meeting Date: 
September 17, 2026 
  
  
To: 
Mayor and Keene City Council 
  
  
From: 
Mayor Jay V. Kahn 
  
  
Through: 
Terri Hood, City Clerk 
  
  
  
 
Subject: 
Confirmation - Human Rights Committee 
  
  
 
  
Council Action: 
In City Council August 6, 2026. 
Nomination tabled until the next regular meeting. 
  
                                                    A true record; 
                                                             Attest: 
 
                                                                            Assistant Clerk 
  
Recommendation: 
 
  
Attachments: 
None 
  
Background: 
I hereby nominate the following individuals to serve on the designated Board or Commission: 
 
HUMAN RIGHTS COMMITTEE 
 
Julie Odato 
December 31, 2028 
Moving from Alternate to Regular Member 
 
Slot 5 
 
 
Page 39 of 210

 
2026-396 
 
 
CITY OF KEENE 
NEW HAMPSHIRE 
 
ITEM #C.1. 
 
  
   
Meeting Date: 
September 17, 2026 
  
  
To: 
Mayor and Keene City Council 
  
  
From: 
Michael Guitard 
  
  
Through: 
Terri Hood, City Clerk 
  
  
  
 
Subject: 
Michael Guitard/Guitard Homes LLC - Petition for City Ownership of Water 
and Sewer Infrastructure - Cottage Court Community on Court Street 
  
  
 
  
Recommendation: 
 
  
Attachments: 
1. 
Guitard Communications_redacted 
  
  
Background: 
Michael Guitard of Guitard Homes LLC is requesting that the City assume ownership of the water 
and sewer infrastructure serving the approved Cottage Court Community on Court Street. The 
development is proposed in three phases totaling 29 homes, and the applicant requests the City’s 
consideration of municipal ownership of the infrastructure as the project moves forward. 
 
 
Page 40 of 210

Page 41 of 210

 
2026-398 
 
 
CITY OF KEENE 
NEW HAMPSHIRE 
 
ITEM #C.2. 
 
  
   
Meeting Date: 
September 17, 2026 
  
  
To: 
Mayor and Keene City Council 
  
  
From: 
Duncan Hilchey and Amy Christian 
  
  
Through: 
Terri Hood, City Clerk 
  
  
  
 
Subject: 
Duncan Hilchey and Amy Christian - Request for a Traffic Study and Safety 
Assessment of School Street 
  
  
 
  
Recommendation: 
 
  
Attachments: 
1. 
Hilchey and Christian Communications_redacted 
  
  
Background: 
Duncan Hilchey and Amy Christian are requesting a Traffic Study and Safety Assessment of School 
Street. They would like particular attention to be spent on studying and assessing vehicle speeds, 
traffic volumes, traffic patterns, and excessive vehicle noise. They mention that residents have 
become increasingly concerned and mention that although they are part of the central business 
district, they do not want to lose the safety, livability, and residential character of their neighborhood. 
 
Page 42 of 210

Page 43 of 210

Page 44 of 210

 
2026-427 
 
 
CITY OF KEENE 
NEW HAMPSHIRE 
 
ITEM #C.3. 
 
  
   
Meeting Date: 
September 17, 2026 
  
  
To: 
Mayor and Keene City Council 
  
  
From: 
John T. Newcombe 
  
  
Through: 
Terri Hood, City Clerk 
  
  
  
 
Subject: 
John T. Newcombe - Resignation - Board of Assessors 
  
  
 
  
Recommendation: 
 
  
Attachments: 
1. 
J. Newcombe Assessors Board Resignation 
  
  
Background: 
John Newcombe has submitted his resignation from the Board of Assessors. He has served on the 
Board since 2016. 
 
Page 45 of 210

Page 46 of 210

 
2026-434 
 
 
CITY OF KEENE 
NEW HAMPSHIRE 
 
ITEM #C.4. 
 
  
   
Meeting Date: 
September 17, 2026 
  
  
To: 
Mayor and Keene City Council 
  
  
From: 
Councilor Philip M. Jones 
  
  
Through: 
Terri Hood, City Clerk 
  
  
  
 
Subject: 
Councilor Jones - Central Square Pedestrian Access During the 2026 
Keene Pumpkin Festival 
  
  
 
  
Recommendation: 
 
  
Attachments: 
1. 
Councilor Jones Communication about Pumpkin Festival 2026 
  
  
Background: 
A communication from Councilor Philip Jones requesting that barriers and obstructions associated 
with the downtown infrastructure project be removed, where it can be done safely, to allow pedestrian 
access to Central Square during the 2026 Keene Pumpkin Festival. The request is limited to 
pedestrian access and does not seek changes to vehicular traffic patterns, the festival’s licensed 
footprint or liability, or the display of pumpkins in Central Square. 
 
Page 47 of 210

To: Mayor and City Council 
From: Councilor Philip Jones 
Subject: Central Square Pedestrian Access at Pumpkin Festival 
Date: September 15, 2026 
 
I am requesting that during the 2026 Keene Pumpkin Festival that all barriers and 
obstructions caused by the downtown infrastructure project blocking pedestrian access to 
Central Square be removed to safely allow pedestrian access to that section of downtown. 
The Pumpkin Festival is very important to the downtown merchants including those 
located around the Central Square area. 
I am not asking for any changes in vehicular traffic patterns. I am not asking Let it Shine to 
expand their licensed footprint. I am not asking for Let it Shine to take on any additional 
liability. I am not asking for pumpkins to be displayed in the Central Square area. I am 
simply requesting that all barricades and obstructions preventing pedestrian access that 
can safely be removed be removed for that day. 
 
Thank you for your attention to this matter.  
Respectfully,  
 
Page 48 of 210

 
2026-440 
 
 
CITY OF KEENE 
NEW HAMPSHIRE 
 
ITEM #C.5. 
 
  
   
Meeting Date: 
September 17, 2026 
  
  
To: 
Mayor and Keene City Council 
  
  
From: 
Shawn Voisine 
  
  
Through: 
Terri Hood, City Clerk 
  
  
  
 
Subject: 
Shawn Voisine/Elmside LLC - Request for Waiver of City Public Utilities 
Standards for Water Metering Infrastructure - Elmside Cottage Court 
  
  
 
  
Recommendation: 
 
  
Attachments: 
1. 
Voisine Communication Redacted 
  
  
Background: 
Shawn Voisine of Elmside LLC is requesting a waiver of City of Keene Public Works public utilities 
standards requiring a main water meter serving the privately owned water and sewer infrastructure at 
Elmside Cottage Court to be located within a stand-alone heated building. The applicant requests 
instead that each of the development’s 18 homes be individually metered, citing concerns regarding 
reliability, equitable billing, and long-term costs to homeowners. 
 
Page 49 of 210

Page 50 of 210

 
2026-311 
 
 
CITY OF KEENE 
NEW HAMPSHIRE 
 
ITEM #D.1. 
 
  
   
Meeting Date: 
September 17, 2026 
  
  
To: 
Mayor and Keene City Council 
  
  
From: 
Planning, Licenses and Development Committee, Standing Committee 
  
  
Through: 
  
  
  
 
Subject: 
Councilor Filiault - Request for Consideration of an Ordinance Amendment 
Regulating Dogs at Downtown Events and 
Paul Allen-Webber - Request to Reconsider Ordinance O-2004-15-A 
Section (e) Regarding Dog Restrictions During the Pumpkin Festival 
  
  
 
  
Recommendation: 
On a vote of 5 to 0, the Planning, Licenses and Development Committee recommends that the City 
Attorney draft an ordinance restricting dogs at all licensed downtown community events and return it 
as a draft at the next PLD meeting. 
  
Attachments: 
None  
  
Background: 
Chair Filiault took these two items on the agenda together. He noted that Paul Allen-Webber (not a 
Keene resident) was not present to speak to his letter but had spoken with the Chair by phone. He 
added that he would take up consideration of this ordinance and the potential amendments, and 
accept and file Mr. Allen-Webber’s letter into the record as part of the overall discussion related to 
dogs at downtown events. 
 
Chair Filiault explained that his letter to the Mayor and City Council is to request the consideration of 
an ordinance regulating dogs at downtown events. He noted that there is already an Ordinance to 
regulate dogs at the Pumpkin Festival. The unfortunate part is that it relies on the organizers to 
regulate the dogs being at the event, which creates a problem within itself. This was brought to Chair 
Filiault’s attention at the last Taste of Keene Food Fest downtown, where multiple times, various 
groups of dogs got together; there were some situations that could have gotten out of hand rapidly. 
Chair Filiault witnessed it and had several citizens approach him saying the City must do something 
about this before something happens. During that time, he said his wife was unfortunately recently 
bitten by a dog. Thanks to Councilor Williams’ efforts to enact enforcement, a fine was put forward; 
he appreciated Councilor Williams working on that Ordinance. Chair Filiault noted all that comes with 
being bit by a dog, like many hospital visits and shots. Fortunately, the dog that bit his wife had its 
shots and could prove it. However, he said there could be situations downtown with people from out 
of town who cannot. Chair Filiault suggested that this would be a case of being preemptive. He does 
Page 51 of 210

 
2026-311 
 
not think that when there are a few thousand people downtown that it is the best place to be dragging 
your dog. With that said, he spoke with the City Attorney about the hope of putting together an 
ordinance so that people cannot bring their dogs within the footprint of downtown events. Chair 
Filiault welcomed input. 
 
Vice Chair Jones noted that Ordinance O-2004-15-A was included in the meeting packet and asked if 
this would be an amendment to that Ordinance, or if a new Ordinance would be created based on 
festivals. City Manager Ferland thought they would need to look at where it makes sense to include 
that in the 2004 Ordinance, which has the language specifically for the Pumpkin Festival. She said it 
might make sense to get rid of that and write some new language in a new Ordinance and repeal O-
2004-15-A. 
 
To clarify the types of events, City Manager Ferland asked Chair Filiault whether he was looking at 
community events, which are specifically licensed and go through the City process; those are the 
larger events. Chair Filiault agreed that the larger events when there is a certain square footage in 
the footprint are the most concerning and having dogs be prohibited within the footprint of those 
major downtown events is what he is looking to achieve. Regarding defining major events, Councilor 
Haas could see it defined as anytime street closures are involved because that is when people are 
transiting and walking in different ways than they usually do, and they might be unaccustomed to 
where the flow goes. City Attorney Palmeira said it was brought to her attention that some events 
possibly have closures of very small roads that do not actually disrupt much and may not have a 
significant footprint; she said it might not be the same targeted event the Chair was thinking of if 
talking about an Ordinance. She said they might need to be aware of whether some events will fit into 
this concept. 
 
The City Manager said that was why she talked about community events, which are specifically 
defined. Those are events that come before the Council each year for some funding; they are they 
larger events that get licenses through the City. Chair Filiault agreed, stating that he thought it is 
there that there is potential for a problem because you are within a footprint, which the dogs get 
crowded into. He called it a good place to start and said it could be expanded down the road. Chair 
Filiault said this would be a new Ordinance, which would be enforced by the City and not by the 
event organizers. He cited the case of the Pumpkin Festival, which at this time has no Police; he said 
there is not an Ordinance that the Police enforce. It is set up so the event organizers must enforce 
the Ordinance, which puts an unnecessary burden on them and can put the average person in some 
uncomfortable situations. He said it would be different if it were a Police Officer enforcing it. He said 
public information would help also. The City Manager said that she thought if the Council were to do 
this, she talked with the City Attorney about including it within event licenses, to state that dogs are 
not allowed in the footprint of the event. Councilor Williams brought up the example of No King’s Day 
as an instance when this would not apply, and Chair Filiault agreed because there is not a footprint, 
although Councilor Williams said it uses the Gazebo. In general, Councilor Williams said political 
events (small to large) happen there, and he thought it should generally be kept out of this category. 
 
Councilor Haas asked if it could be possible to create this ordinance the Committee was tending 
toward for all community events, but then empower the protocol committees to make exceptions, if 
possible, as needed where appropriate. The City Attorney understood the protocol was that these 
details would usually come up during the process with licensed events and there is a distinction 
between having something in the license and having an Ordinance separate from license conditions, 
so that it is enforced by police, which Chair Filiault was seeking. If the stipulation were through the 
license/protocol process, it would be something the license holders would be responsible for 
Page 52 of 210

 
2026-311 
 
enforcing. Chair Filiault said that would be like what exists now for Pumpkin Festival. The City 
Attorney clarified that the Pumpkin Festival Ordinance in the City Code is a prohibition enforced by 
the Police, but it is currently the only event identified as such in the Code. 
 
Chair Filiault said he did not disagree with Councilor Williams, but like all things where politicians get 
together, he did not want to overcomplicate it. He wanted to start with the footprints of City events 
and if there is a need to expand, they could. Chair Filiault wanted to get something they could 
enforce sooner than later. He reiterated that it could be expanded later. Chair Filiault said the City 
had been lucky so far and stated that if somebody gets bit on City property, no matter who is 
organizing the event, they are coming after the City. 
 
Vice Chair Jones asked for this to come back as a draft Ordinance, so it would not have to be 
amended through many versions. Chair Filiault said he talked to the City Attorney about having a 
draft to get most of the decisions out of the Committee. 
 
Chair Filiault opened the floor to public comments. 
 
At Large City Councilor Michele Chalice wondered about the criteria of when surrounding streets are 
blocked off and whether the isolated area created by the City’s large trucks and concrete barriers 
could be the trigger for the associated size that would make this necessary. Chair Filiault said he 
heard what the Councilor was saying but that usually within a bigger footprint, it means a bigger 
crowd and vice versa; a smaller footprint does not necessarily make it any easier, it is just going to be 
more concentrated. 
  
He personally wanted to try to keep it simple and make it start off with downtown events. Chair 
Filiault agreed about bringing back a draft ordinance, so the Committee could get it right and it would 
not be kicked back by the full Council. 
 
Councilor Ruttle-Miller noted that she likes dogs (they all do), but that there are specific instances 
when she could see that this could be problematic. On the other side, she said most of the time, dogs 
she has seen at these events do not want to be there; they are there because of somebody who 
does not understand that their dog does not want to be there. It is way too much pressure for that 
animal to behave in that scenario. Then, she said there could be a lovely person with a dog at Pride 
Festival wearing a “hug me” shirt, which is nice and well behaved. Councilor Ruttle-Miller noted that 
unless it were an actual service animal, this would not preclude that. She stated this would also cut 
out any sort of emotional support animals, which do not fall under the same regulation. Chair Filiault 
said he was not disagreeing with Councilor Ruttle-Miller: Chair Filiault and his wife love dogs, until 
they get bit by one. Councilor Ruttle-Miller stated that this is a hard topic for her and it has nothing to 
do with the dogs and everything to do with the people putting dogs in bad situations. Chair Filiault 
said they are all dog lovers. 
 
Councilor Haas said they would hear from the dog lovers when this comes to full Council. He said 
one thing to have in mind for the future is how the City defines service dogs or emotional comfort 
dogs. Chair Filiault said service dogs are totally separate, and every dog is an emotional comfort dog. 
 
The following motion by Councilor Haas was duly seconded by Vice Chair Jones. 
 
On a vote of 5 to 0, the Planning, Licenses and Development Committee recommends that the City 
Page 53 of 210

 
2026-311 
 
Attorney draft an ordinance restricting dogs at all licensed downtown community events and return it 
as a draft at the next PLD meeting. 
 
Page 54 of 210

 
2026-378 
 
 
CITY OF KEENE 
NEW HAMPSHIRE 
 
ITEM #D.2. 
 
  
   
Meeting Date: 
September 17, 2026 
  
  
To: 
Mayor and Keene City Council 
  
  
From: 
Planning, Licenses and Development Committee, Standing Committee 
  
  
Through: 
  
  
  
 
Subject: 
Councilor Jones - Request for Consideration of an Ordinance Establishing 
a Temporary Moratorium on Data Centers and Cryptocurrency Mining 
Facilities 
  
  
 
  
Recommendation: 
On a vote of 5 to 0, the Planning, Licenses and Development Committee recommends that the 
Request for Consideration of an Ordinance Establishing a Temporary Moratorium on Data Centers 
and Cryptocurrency Mining Facilities be referred to the Planning Board. 
  
Attachments: 
None  
  
Background: 
Chair Filiault welcomed comments from the petitioner, Councilor Philip Jones. Vice Chair Jones said 
he first got thinking about this when he was up in the Statehouse and there was a bill before the 
house. It was Senate Bill 439, which would have allowed these entities to happen in any industrial or 
commercial zones of a municipality. Fortunately, it was tabled at the House and never brought back, 
so it died on the table, he said thankfully. He said that got his mind going about this. He noted it had 
been in the news a lot lately. He cited that Arizona had 180 of these data centers suddenly; they 
decided they wanted to be reactive, and they are suddenly finding out there are a lot of things they do 
not like about them, so they are putting a moratorium on them. Vice Chair Jones explained that 
Texas was inviting them to come to their state. Now, just this week, Governor Scott decided that they 
need to have regulations. The Governor of New York just introduced a two-year moratorium so they 
can create more regulations The City of Lowell, Massachusetts, has the largest data center in New 
England and Councilor Jones said they were going through lots of problems with the neighbors, for 
example. They have 28 generators running all day long with long diesel spewing fumes, with the 
diesel motors going all the time (air conditioners on the roof are humming all the time because they 
must keep it cool). So, he said it is bad quality of life for the people in Lowell, and they are finding out 
the hard way. 
 
Vice Chair Jones said the reason for suggesting a two-year moratorium is an indefinite sunset. He 
was asking for the two weeks so the Committee could be educated; there is a lot on social media, 
and they do not know what to believe. He called the keyword impact. He thought one way they could 
Page 55 of 210

 
2026-378 
 
educate people on this would be to have a presentation or report from the Energy and Climate 
Committee on how this would impact Keene’s Sustainable Energy Plan, the 2015 Greenhouse Gas 
Emissions report, and how it would affect Keene adapting to climate change. He wondered how it 
would affect Keene’s 2004 Climate Action Plan. He also thought about the Community Development 
perspective and how the data centers would affect Keene’s Master Plan; the Building, Health, and 
Fire Codes; the Water Department; and the Assessing Department and certain neighborhoods. He 
thought it would be great to hear from the Monadnock Economic Development Corporation because 
they might have another side to it: they might have the features and benefits to the City, especially 
ratables and employ-ables. He also thought the Council should hear from Southwest Region 
Planning Commission because this should be a regional issue. Vice Chair Jones added input from 
the New Hampshire Department of Environmental Services would be beneficial because they may 
already have some restrictions and they could help the City to write some restrictions or regulations. 
He also believes that the New Hampshire Public Utilities Commission already has some regulations 
that would be great for the Council to hear. He suggested hearing from Eversource and Liberty 
Utilities as well about what is available for power (e.g., some of these places run off propane gas). He 
said there is a lot to be learned about all of this. Finally, he said the Council should hear from the 
public about this because it could affect their neighborhoods. He was not saying the City should not 
have data centers, he was just saying the Council should be proactive and not reactive. 
 
Vice Chair Jones said he asked City staff whether a resolution or an ordinance would be more 
appropriate, because an ordinance creates a law and a resolution creates a policy. Chair Filiault said 
he spoke with City Attorney Palmeira about that today and her recommendation was that the next 
step should be to send this to the Planning Board. Chair Filiault asked if that would be the correct 
procedure. City Attorney Palmeira said there is a specific channel to go through for the process they 
would recommend for the moratorium. There is a state statute on moratoria, and it is specifically for 
all the reasons Vice Chair Jones just described; these are all the various areas of information we 
want to adhere to while regulating it. 
 
The City Attorney said it would take a lot of research and a lot of understanding. She stated that a 
moratorium is the tool to freeze the status quo and to prevent any development while the City is 
doing that research. She said the moratorium does get referred to the Planning Board and first, the 
Planning Board by statute makes a recommendation of the need for a moratorium on the specific 
categories of use. Then, that recommendation would come to the legislative body, our City Council, 
to pass an ordinance. So, the City Attorney noted that the statute says that it would go through an 
ordinance. She also wanted to flag that the statute states a time frame for a moratorium of no more 
than one year, so the City would try to get all its work done in that time period. 
 
Chair Filiault recalled that the City would not set a precedent here because as mentioned, the Town 
of Nottingham, New Hampshire, and others have already made moratoria. That reminded Vice Chair 
Jones that there was a recent announcement that the Governor of New Hampshire was going to 
request a moratorium because of Nottingham and now Bow, New Hampshire, dealing with issues. He 
said unfortunately, the Governor is putting it through the budget process, which means it would go to 
House Bill 2, which is the “Christmas Tree Bill” where everybody puts their “ornaments” on it. It would 
not even be heard until April 2027, and it would not be finished until June 2027. Vice Chair Jones 
thought that was too much time. He thought Keene should get something on the books before that 
happens because there is no guarantee she would even be the Governor; there is no guarantee what 
the House and Senate would do. 
 
Councilor Haas thought there was a process laid out where it goes through the Planning Board and 
Page 56 of 210

 
2026-378 
 
he imagined this Committee would make that recommendation. Reviewing the Land Development 
Code as the Committee had, Councilor Haas said there were virtually no limitations as such right 
now. The LDC does define data centers, but they are widely permitted with no special restrictions. He 
appreciated the City Attorney’s guidance. 
 
Councilor Williams said he had a few thoughts. First was that he was not terribly concerned about 
data centers opening in Keene soon because our price of electricity is so expensive. He said they are 
opening in Texas and Arizona, which are places with ample solar renewable energy, and that is really 
what these things are moving into to take advantage of. Councilor Williams added that data centers 
have some very negative environmental effects. He cited particular concern about the effect on 
water: not just that it uses water, but that it heats water up, which is terrible for an ecosystem if it is 
then released into the environment. Nevertheless, he said he was not super concerned about them 
opening in Keene. He said we could see that here. Which was not to say he was against a 
moratorium. Yet he wanted to make sure it is not “bigfooting a lot of the, I wouldn't call them a data 
center.” He compared these giga scale centers with their own power plants to the office where he 
works, which has a server room and several racks of servers. He would like to continue being able to 
have a server room and several racks of servers. He would like to be able to build that without too 
much hassle anywhere in Keene. Councilor Williams said he recognized there is a certain scale at 
which the City would probably want to say, “let's not do that,” but he wanted to understand what that 
scale is before agreeing to a moratorium. 
 
Vice Chair Jones added that at the Joint Planning Board-Planning, Licenses and Development (PB-
PLD) Committee meeting he would have a request for definitions to use for zoning purposes. He said 
it would be a little bit different than how they are identified as uses within certain zones. He thought 
they would probably be conditional uses or overlays, where they can be regulated and not put up 
against neighborhoods (e.g., like the City did with casinos). Vice Chair Jones asked whether the 
Planning Board (PB) would make a recommendation that would come back to the Council, because 
the Planning Board cannot create an ordinance, the Council can. The City Attorney said that is right. 
 
The City Attorney said, to Councilor Williams’ question, part of the City Council’s requirement for 
creating a moratorium is identifying categories of development to which the ordinance applies. She 
said staff spoke internally about how data centers are already defined and the City’s own IT 
Department was a little concerned about prohibiting its own servers. So, there would be an intent to 
narrow it down to not prohibit what the City wants and have it really serve as a temporary definition 
while staff do the work for the Zoning Ordinance. To Vice Chair Jones, the City Attorney said he was 
correct and that his letter would be coming up at the Joint PB-PLD Committee, starting the 
conversation of how the City is going to define data centers for more of a permanent Zoning 
Ordinance, not the temporary one that would be in the moratorium. The City Attorney's office will be 
at the Joint Committee to talk about that, and their recommendation is going to be if this Council does 
suggest going forward with a moratorium, then the Joint Committee should put that on more time 
while the moratorium gets in place. Then, that would be the trigger to start the long-term work for the 
regulation. Vice Chair Jones said that was exactly the way he would like to see it and thanked the 
City Attorney. 
 
Mayor Jay Kahn (of Mountain View Drive) said it was good to hear the one-year guard rail. He 
thought it was helpful that there would be some standard established across the state. He thought 
there would be a lot of evidence that comes from legislation, regardless of whether it is finalized in 
April, but he thought Keene was clearly in an investigative point in our country. He did not think that 
anybody wanted to act out of fear in prohibition because this is progress and we ought to be trying to 
Page 57 of 210

 
2026-378 
 
set up what are the appropriate guardrails to that progress. The Mayor shared a story about being on 
Dan Mitchell’s radio show and discussing data centers in Keene. He agreed with Councilor Williams 
about questioning the definition of a data center. Mayor Kahn said there are lots of potential data 
centers: there is a website on WMUR listing about one dozen in New Hampshire; four of those are 
under the name of First Light and one of those First Light locations is in Keene. There is also one in 
Lebanon, Portsmouth, and Manchester. The Mayor said the City does not want to put a prohibition or 
a moratorium on existing data centers; they are not causing much harm currently and he has not 
heard complaints. So, Mayor Kahn said the City’s definitions really need to be forthcoming. He 
suspected if this went to the PB, there would be a Public Hearing. There is not necessarily action to 
be taken following a Public Hearing but at least the Council would get more perspective on what the 
definitions ought to be. Mayor Kahn called it a good question that Vice Chair Jones raised. The 
Mayor said the City does not want to make guidelines that inhibit current uses because its definitions 
were not accurate enough. 
 
Al Smith (of Keene) has lived in Keene for one year and has 30 years’ experience in the data center 
industry working for a private company, which wrapped up with the design and build of data centers 
globally (a private company; they were all very small). The question Mr. Smith kept coming back to is 
“what is a data center?” He worked with ASHRAE and some other significant industry experts and 
said no one can answer the question because they range from a small telecom closet to in the case 
of Lowell, 350,000 square foot buildings, which is a reuse of an old factory. Mr. Smith called the latter 
a great opportunity, but it does come with the negatives: the noise, the diesel exhaust. In the 
company he worked for, they ran generator tests every single week on a Tuesday morning and they 
knew not to park their cars near the exhaust, or they would be covered in diesel soot. He provided 
other examples of how neighbors might have been disrupted on the weekends. He explained the 
noise that comes from the commercial locations, which could be next to residential locations, and it is 
very concerning because the noise carries. He shared experience of being at “data center row” in 
Ashburn, VA, stating that they never get a break. Mr. Smith commented on how the background 
humming noise is still there even when the cicadas go away. He said to imagine that in this nice 
valley, stating that it would be all anyone hears in the background: there would never be another 
quiet night. 
 
Mr. Smith continued that most companies who are building a data center are going to get a deal with 
an electric company because they are buying a lot of power, so they get a better price, and that is 
something else to be concerned with as well, because that raises the demand. If they are getting a 
better price, then the people who are just living in a house that are not making a big payment are not 
going to get the same deal. Those are the concerns Mr. Smith has as a resident. He continued about 
when you start talking about the thousands of gallons of water. It is not always cooling; sometimes it 
adds humidity to keep the equipment running. He pointed out that Keene is not heavily connected. 
Unlike Lowell, Keene does not have a main heavy duty fiber connection into Boston. That is why 
Lowell was a potential connection. So, Mr. Smith said there are a lot of negatives. He knew one of 
the big pluses was that states like Texas and Arizona were convincing companies to move there. He 
said that does not make sense when you look at the water requirement, and they promise jobs. Mr. 
Smith wanted to warn people, having worked in a couple of data centers that were 50,000 plus 
square feet, he said they minimize the number of people on the floor: there are not a lot of jobs 
actually on site, they are remote workers doing things, possibly in another country sending the 
instructions to those servers. He said for every positive that is sold there is a negative. He added that 
they are great for construction jobs in the short term, but he did not think there were any companies 
in Keene that were experts at building data centers; they would come in from outside as well. 
 
Page 58 of 210

 
2026-378 
 
Vice Chair Jones asked, when Mr. Smith said Keene does not have the connection, was he talking 
about the data connection? Mr. Smith said yes, the heavy-duty fiber connectivity to bring in gigabits 
of data transfer, which would be more in the metropolitan areas. He discussed the subsea cables that 
come across the Atlantic Ocean, terminating in Virgina, making Ashburn, Virginia, the perfect spot for 
data centers. Boston has some of that connectivity as well, in addition to New York. Without access 
to subsea cables, Mr. Smith said it would be less likely that companies would move heavy duty 
colocation facilities like the one in Lowell, Massachusetts, to Keene, New Hampshire. It would involve 
a lot of heavy-duty trenching and underground work. Mr. Smith shared an experience building a 
remote site in Western Maryland and leasing cables that were run already along Route 70 all the way 
up to Colorado. The big telecommunication companies have already put these in; they generally stick 
to the major highways. He said Brattleboro is closer to Hwy-91, so those commercial facilities would 
be more readily available to connect than Keene’s. Mr. Smith called it something to think about, 
stating it was nothing to do with the moratorium and more to do with education. He closed by stating 
the four things needed for data centers: (1) water, (2) power, (3) cooling, and (4) connectivity. Vice 
Chair Jones appreciated Mr. Smith as an excellent resource. 
 
Councilor Williams reiterated what Mr. Smith said about connectivity. Councilor Williams investigated 
hosting servers in Keene. It is far more expensive because of the lack of connectivity. 
 
Chuck Redfern (of 9 Colby Street) thanked Mr. Smith for providing great information. In Mr. Redfern’s 
opinion, stating he is no expert at this, but he thought Mr. Smith did throw a bit of a cautionary tale 
not to jump into it with blinders. Mr. Redfern said that feeds into the need for a moratorium, not to 
stop it, but to give us a chance to figure it out. Technology is moving at a rapid rate, just like so many 
things in the technology field, but this is one that we need to grasp where in Keene a data center 
would likely go. He said a lot of things in the “unknown” column end up in the East Keene 
neighborhood, where he resides. So, Mr. Redfern had some concerns that he wanted addressed 
during the moratorium. He would like to look at the other towns that were mentioned and do an AI of 
the pros/cons on the subject. He mentioned considerations like noise generated from the AC units on 
roof fixtures. He asked why to be the first in the area to implement it. He asked what would be wrong 
with a relatively short moratorium of one year, which he hoped would be two years; he felt one year 
was short. Mr. Redfern said the output value to the community has got to be the bottom-line question. 
He said we must somehow limit the output from these facilities (i.e., water use, which is precious). 
Mr. Redfern cited a Mayoral study from a few years ago about trends occurring with the water supply 
and change in the environment with global warming. Mr. Redfern said this is something that must be 
careful and well thought out. He said none in the room were experts; the closest was probably 
Councilor Jones. Mr. Redfern asked whether this would be going to the Joint PB-PLD Committee, 
and Vice Chair Jones said no, the Planning Board. The City Attorney clarified that Vice Chair Jones 
submitted two letters so there were two tracks: (1) if this Committee recommended to the City 
Council to refer this to the PB, (2) if that gets carried out the second letter from Vice Chair Jones, 
would be at the Joint PB-PLD Committee, concerning definitions for a data center. Mr. Redfern 
concluded by stating that he does question the value of cryptocurrency and whether it is a value to 
our society or not. He suggested a moratorium to do some more serious research on this. 
 
Robin Walden (157 Pako Avenue) said she has a lot of concerns around data centers in our 
community. First, electricity. Also, a lot of times when data centers install new plants, substations, 
and lines, often those costs get downshifted to residential customers. Ms. Walden cited water usage; 
any research she had done, or news reports, showed that communities near these data centers do 
not have water pressure. She asked what would happen if that occurred in Keene? Next, she cited 
the constant noise of the data centers. Ms. Walden stated that she has lived a blessed and quiet life 
Page 59 of 210

 
2026-378 
 
at her home for the last 29 years and she is not looking to change that. She said the diesel 
generators emit fumes and fine particle pollutants that harm local air quality and human health: the 
decibels emitted from these generators can reach 90 decibels and levels over 85 are harmful to 
hearing. Ms. Walden mentioned lower property values and the taxes: “if I ever go to sell my house 
and there's a data center near me, that's not going to happen. 
 
I'm not going to recoup what I've put in.” Her research agreed that there are far fewer jobs after data 
centers are built. For the case in Lowell, Massachusetts, she believed they had 12 people on site for 
that massive facility. So, she thought that advertising more jobs to Keene would be a false narrative. 
She also read that public health researchers have started evaluating how the broader environmental 
and structural footprints of data centers, specifically emissions from generators, cooling chemicals, 
and resource strain, could indirectly act as risk factors for reproductive health. Finally, Ms. Walden 
mentioned wildlife: we are disrupting their ecosystems, pulling water from rivers, and disrupting all of 
that. Ms. Walden stated that she would love the whole thing kiboshed but would be happy if the 
Council at least did a moratorium to look into this further. She does not think the City should put 
progress ahead of human health and quality of life. 
 
Councilor Laura Tobin (of Center Street) said she, like a lot of people, has concerns. She thought 
there were a lot of unanswered questions. She cited a couple of things she hoped the Council would 
consider if it chose to do a moratorium. She cited the City’s renewable energy goals and how that 
would fit in with this. She noted that a lot of people are using AI now, and she wondered what the 
City’s fair share is of carrying that infrastructure. She wondered how that fit in with the PB’s Process. 
She does not want to be the City that says we have to just build somewhere else; she felt that the 
City had been there with a lot of other things too. 
 
Eli [last name not given] (of Keene) said his concern is about the ecosystem and the environment. He 
has some knowledge in that as a fisherman. He said the biggest thing is studying and knowing your 
environment and how the ecosystem works. He noted there are a lot of great ecosystems locally in 
and around Keene, and if you are pulling water from the watersheds to cool that down, possible 
pollutants could easily cripple some of the great ecosystems we have. Let alone he said it is probably 
not the best for animals or human consumption on top of that if it produces a noise. He noted that 
high humming and everything else is not the best for anyone’s health, from animals to people, and 
could lead to some different syndromes. Still, Eli said the biggest thing is the not the water being 
cooled but the pollutants that cripple the ecosystem and make it a lot rougher for outdoorsmen 
especially to make money from guiding and everything else that is very fragile. It could very well 
impact the environments locally too. Eli said that is the biggest thing to keep in mind when doing 
research into it: it is something that a lot of the outdoorsman would want the Council to keep in mind. 
He said on top of whether this is something that we should allow in our communities or not. 
 
Councilor Michele Chalice said she received two calls about this, so she thanked Councilor/State 
Representative Jones for bringing this to the Council’s attention. The two calls Councilor Chalice 
received were requests to add U.S. Department of Human Services Immigration and Customs 
Enforcement (ICE) detention centers to the list of data centers and cryptocurrency mining facilities 
due to the fact that a large facility would be potentially having similar impacts to our natural 
resources: water quality, water quantity, air quality, and potential sound disturbances. They were 
specifically requesting that if the Council were going to go through all this research that they would 
make sure they cover all their bases of potential large impacts to our community by these larger 
developments. Vice Chair Jones stated that detention centers were in his request to the PB-PLD 
Committee for definitions. 
Page 60 of 210

 
2026-378 
 
 
Jeannie Kingsbury (of Spruce Street) was glad to be having this meeting on data centers and about 
these broader impacts that can be called progress, but she questioned whether progress is so great 
when we live in a bowl. So, she said all that noise and pollution is trapped here with all of us; it is 
foggy, you can smell things, and you can see the pollution. She said they already get poor air quality 
alerts on their phones, and this would have an impact. She said these other places like Texas and 
Arizona are large, big, flat areas with a lot less populace, where the noise is less of a problem. 
Whereas in Keene, with the populace the noise and pollution would be a problem. She said it would 
not bring in jobs, citing the example from Lowell. She said these data centers are meant to replace 
people and jobs nationwide, which is why the people with the money are pushing for them. So, Ms. 
Kingsbury said the Council has to look at what kind of community we want here in Keene: do you 
want a welcoming community to manufacturers or companies that are actually going to employ 
people or places that are actually going to work to get rid of people. She was glad that the City was 
saying that it needs to slow down on this and look at what is going on. She agreed that there are 
businesses with server rooms, yes, but said those businesses employ a lot of people, using the 
hospital as a prime example. In the big scheme of things she said they were talking about impacts to 
people, to public lands and animals, and the environment. Ms. Kingsbury was glad Keene was saying 
to investigate this a little bit more. She said we cannot just let these companies steamroll themselves 
in saying progress, because progress is not always a good thing. Chair Filiault agreed. 
 
Terry Clark (of 14 Barrett Avenue) did not come to necessarily speak for or against data centers, AI, 
or any of that, because as been noted, data centers and AI have been around here for a long time. 
The data centers especially. He thought the reason that we had been hearing so much about it is the 
dramatic increase in the interest in AI and in the number of companies that have that have formed to 
get into it in a big way. Mr. Clark is a member of the Nonpartisan National Association of Counties, 
Energy, and Land Use Steering Committee, which has been helping to craft a resolution urging 
protection of local authority over data centers, data privacy processing facilities, and which include 
cryptocurrency mining operations. He said the reason they got involved is because President Trump, 
in March of 2026, issued an executive order 14-318 titled Accelerating Federal Permitting of Data 
Center Infrastructure that was directing federal agencies to ease regulatory burdens and rapidly build 
out large data center projects. He said the translation of that is to cut local governments out of the 
regulatory loop and forego the usual impact studies that could identify problems and implement 
solutions. State and federal lawmakers have already proposed or enacted legislation that limits or 
prohibits local governments from regulating the development of these energy and water hungry 
facilities, and it had been noted about the price of electricity around these data centers. Mr. Clark 
said utility customers in Maryland and Washington, DC, are some of the first in the country to see the 
effects of the data center boom show up on their residential electricity bills. Much of that price 
increase is due to the anticipation of future demand. That is the way the pricing works and is a part of 
the reason we have very high energy costs in New England data centers; they can be built faster 
than new supply resources like power plants, so the market is not competitive because projected 
demand exceeds supply and new supply cannot be timely built to restrain the prices. 
 
Mr. Clark said the Nonpartisan National Association of Counties, Energy, and Land Use Steering 
Committee’s proposal urges Congress to pass legislation to protect the authority of local 
governments to regulate, restrict, or ban data centers within their jurisdictions. The National 
Association of Counties, Energy, and Land Use Steering Committee is a 3,600-county strong 
organization that has been very effective in influencing the actions of Congress. So, Mr. Clark said 
the technology is here to stay, and he does not really oppose it; in fact, it can be beneficial if applied 
with proper safeguards. He said that if we do not let technology get ahead of the society curve. We 
Page 61 of 210

 
2026-378 
 
will have a medical breakthrough and implement something just to find out that this miracle drug 
causes mass addiction, for example. So, he said we must be careful to slow things down, so that we 
can understand them before we start acting with them. Mr. Clark thanked the Councilman for bringing 
it all up because we really need time to sort all these things out. He said there are a lot of really 
serious questions: who owns and benefits from the technology and the centers, and where are they 
best located? How do we safeguard our electrical grid and water supplies? Most importantly, who 
makes those decisions? Mr. Clark was glad the Council was getting involved because this was really 
taking off at the County level and he hoped the City would be successful. 
 
Vice Chair Jones agreed with motion but first wanted to ask the City Manager if the various entities, 
boards, departments, and so on that he mentioned in the beginning could be notified and asked if 
they would like to present some data that the Council or Planning Board could use in their research. 
The City Manager thought we would want to invite them to the Planning Board for their process when 
they are considered. Vice Chair Jones said that was what he was asking: for the Planning Board 
Public Hearing. 
 
The following motion by Vice Chair Jones was duly seconded by Chair Filiault. 
 
On a vote of 5 to 0, the Planning, Licenses and Development Committee recommends that the 
Request for Consideration of an Ordinance Establishing a Temporary Moratorium on Data Centers 
and Cryptocurrency Mining Facilities be referred to the Planning Board. 
 
Page 62 of 210

 
2026-416 
 
 
CITY OF KEENE 
NEW HAMPSHIRE 
 
ITEM #D.3. 
 
  
   
Meeting Date: 
September 17, 2026 
  
  
To: 
Mayor and Keene City Council 
  
  
From: 
Finance, Organization and Personnel Committee, Standing Committee 
  
  
Through: 
  
  
  
 
Subject: 
FY25 Audited Financial Statements Presentation - CBIZ CPAs, P.C. 
  
  
 
  
Recommendation: 
On a vote of 4 to 0, the Finance, Organization and Personnel Committee recommends accepting the 
presentation on FY25 Audited Financial Statements by CBIZ CPAs, P.C. as informational. 
  
Attachments: 
None  
  
Background: 
Finance Director, Kari Chamberlain addressed the Committee and welcomed the auditors joining the 
Committee remotely. 
 
Auditors Scott Warnetsky and Amar Jalilovich addressed the Committee. Mr. Warnetsky explained 
that the audit process involves performing procedures on obtaining evidence about the amounts and 
disclosures in the financial statements. He stated they use different audit techniques in order to 
obtain reasonable assurance regarding the City’s financial statements. They sample items but don’t 
look at every single transaction and balance of the City. He indicated they verify that the financial 
statements are materially accurate and fairly presented. 
 
As far as responsibilities, they are hired to express an opinion on the financial statements based on 
their audit procedures. Mr. Warnetsky noted the ultimate responsibility for the financial statements is 
City management. 
 
He went on to say, auditors are not expressing an opinion on internal controls. Because the City is a 
government, they perform their audit in accordance with two sets of auditing standards; Government 
auditing standards as well as generally accepted auditing standards. For all intents and purposes, 
they are largely the same, with a few enhancements on the government auditing standards. One of 
those is the requirement for auditors to report to the Finance Committee any deficiencies. 
 
Mr. Jalilovich addressed the Committee next and stated he wanted to provide a brief context over the 
financial statements that they audited for fiscal year 2025. He stated the City received an unmodified 
or clean audit opinion, which means the financial statements are fairly presented in accordance with 
Page 63 of 210

 
2026-416 
 
applicable accounting standards. He explained the financial statements are designed to provide two 
different perspectives on City finances. 
 
The government-wide statements provide a longer-term perspective, looking at the City as a whole, 
including long-term assets and liabilities. While the fund financial statements provide a more short-
term perspective, particularly for the City’s governmental funds, the management discussion and 
analysis are intended to help put those numbers into context. 
 
The notes and required supplementary information provide additional details behind the numbers and 
explain some of the City’s more significant accounting principles, balances and activities. 
 
Lastly, it is worth noting that the City has continued to receive the GFOA Certificate of Achievement 
for Excellence in financial reporting, which speaks to the quality and the transparency of the City’s 
overall financial reporting. 
 
Mr. Warnetsky next referred to actual budgeted amounts and variances. He spoke about the General 
Fund unassigned fund balance and explained that the numbers indicated might not always be a one-
for-one comparison. He felt the unassigned fund balance was healthy overall. 
 
Mr. Warnetsky next addressed Pension Liability. He stated these numbers fluctuate year after year. 
He indicated the liabilities allocated to the City from NHRS are related to net liability and those assets 
fluctuate over time; depending on how those investments perform in a particular fiscal year can send 
that net liability up and down over time. As of today, it is a $35 million liability, which is going to be 
funded over time. This concluded the auditors’ comments. 
 
Councilor Chalice referred to the last slide, GISB 104 Disclosure of Certain Capital Assets Standard 
is expected to require certain information regarding capital assets to be presented by major class. 
The Councilor asked whether major class meant the City would have more information regarding 
what the capital assets the City is invested in. Mr. Warnetsky explained the accounting term class 
would be equipment, infrastructure, buildings, and land (fairly broad). GISB 104 would add a little 
more detail such as leased assets. 
 
The following motion by Councilor Chalice was duly seconded by Councilor Lake. 
 
On a vote of 4 to 0, the Finance, Organization and Personnel Committee recommends accepting the 
presentation on FY25 Audited Financial Statements by CBIZ CPAs, P.C. as informational. 
 
Page 64 of 210

 
2026-370 
 
 
CITY OF KEENE 
NEW HAMPSHIRE 
 
ITEM #D.4. 
 
  
   
Meeting Date: 
September 17, 2026 
  
  
To: 
Mayor and Keene City Council 
  
  
From: 
Finance, Organization and Personnel Committee, Standing Committee 
  
  
Through: 
  
  
  
 
Subject: 
Warren Steinberg - Request for Temporary Free Parking within Active 
Downtown Construction Zones 
  
  
 
  
Recommendation: 
On a vote of 4 to 0, the Finance, Organization and Personnel Committee recommends that the 
Council grant free parking under the provisions of the Free Parking Policy (Resolution R-2015-11) for 
on-street public parking spaces within downtown for the remainder of the 2026 construction season, 
This to be coordinated with the Parking Division. Staff shall report back to the Finance Organization 
and Personnel Committee before the next construction phase for re-evaluation. 
  
Attachments: 
None  
  
Background: 
Mr. Warren Steinberg of 36 Concord Hill Drive addressed the Committee and stated he was before 
the Committee to request the City consider temporary parking relief for the public parking spaces 
located downtown in the construction area. He stated he submitted this request before construction 
reached his own business for many reasons. He stated the effects are not limited to the block behind 
the construction fencing. He is already seeing people on social media indicate they are avoiding 
downtown because of lane closures, detours, traffic, and uncertainty about access. Mr. Steinberg 
stated that when someone decides not to come downtown, it affects businesses well beyond the 
immediate construction zones. He stated the idea is to have a policy that can follow the project rather 
than repeatedly reacting after businesses have already absorbed the impact. 
 
Mr. Steinberg stated he is not asking for any relief to enforcement. He would like enforcement to 
continue as it does today with two-hour limits in certain spots, which should remain. However, how 
this is enforced is something that would need to be discussed. He stated he would like parking relief 
to be addressed now and consider enforcement at another meeting. He stated he agrees that free 
parking alone may not be enough to convince someone to navigate construction, it might not fix all 
issues and it can’t eliminate construction lane closures, detours, but, he felt the City can remove one 
inconvenience. 
 
Mr. Steinberg stated communication is also an important aspect with temporary signs or some sort of 
Page 65 of 210

 
2026-370 
 
online notification. This concluded Mr. Steinberg’s presentation. 
 
Councilor Chalice stated the Committee has been provided spreadsheets with the different options 
and agreed there are serious budget considerations. 
 
Chair Powers asked Mr. Steinberg regarding enforcement whether he referred to just that area that is 
under construction or the entire downtown zone. Mr. Steinberg stated when he originally submitted 
his request, it was just for areas where active construction was happening but since that time, he has 
seen the impact construction is having on the entire downtown area. 
 
Parking Manager Chelsea North addressed the Committee next. Ms. North with respect to 
enforcement stated staff has the capability of enforcing time limits by people registering through the 
ParkMobile app or at the pay stations which makes it easier for parking officers to perform their time 
limit monitoring compared to chalking tires which is time consuming and not efficient. 
 
Councilor Lake questioned how free parking in certain sections could be accomplished. Ms. North 
stated her department works directly with the Communications Director to update social media, 
online website, and parking maps, which are more interactive. The other option would be to post 
signs and make sure they are consistent. 
 
Mr. Roger Weinreich of 51 Railroad Street was the next speaker. He stated offering free parking is a 
mechanism to attract people downtown especially people visiting Keene from out of town. Mr. 
Weinreich went on to say some cities extend parking beyond 5 PM, especially to address people 
visiting restaurants. He suggested perhaps free parking from 11 am to 1 PM to attract people to 
come downtown during their lunch breaks, while also giving people an opportunity to look at the 
machinery and see what is actually happening downtown. 
 
He went on to say metered parking would start again at 1 PM and extend parking until 7 PM. He felt 
this could be just an experiment. 
 
Councilor Chalice felt extending parking until 7 PM was a good idea and added people who are 
coming downtown for meals are ones who could perhaps afford to pay for parking. 
 
Ms. Dorrie Masten Downtown Property Owner and Owner of the Pour House addressed the 
Committee next. She began by stating that parking is not income-based. 
 
Ms. Masten read the following statement: 
 
I am asking the City Council to provide free parking throughout the entire downtown for the duration 
of this almost $30 million infrastructure project. Although construction is divided into three phases on 
paper, the disruption is not. Construction vehicles and equipment travel throughout the entire 
downtown. Traffic is congested and redirected. Roads are closed and changed, and customers often 
cannot tell which businesses remain accessible. The City and its contractor treat this as one project. 
Casella bid on one project they received one contract and carries insurance covering one 
project. The three phases are simply a schedule in completing different portions of this work. They do 
not turn this into three separate projects. If it is one project for bidding, contracting, and insurance, 
and contractor parking, then it should also be treated as one project when determining which 
merchants and customers get affected. To the public, the entire downtown feels like a construction 
zone. This is why the entire downtown, not merely one phase being actively excavated, should 
Page 66 of 210

 
2026-370 
 
qualify for free parking throughout all of the downtown and all phases. I also want the public to 
understand what the City’s contract with Casella allows. 
 
Casella can use up to 50 downtown parking spaces every day at no charge (at a charge), but it's 
included in their contract. From what I have regularly observed and as we know, it started in front of 
Pour House. Casella generally uses about 10, maybe 15 spots a day. I'm not asking the City to take 
away their parking. Casella genuinely needs that parking to complete their work. I'm pointing out that 
the City has already recognized that the parking is a legitimate expense and a burden created by this 
project. The contractor receives that consideration while the merchants and customers suffering from 
the same construction receive no comparable relief. 
 
Downtown businesses are losing customers and sales because of the congestion, the detours, the 
equipment traffic, and the perception that downtown is difficult to access. Charging people to park 
gives them one more reason to just go somewhere else. We did not create these conditions, but we 
are expected to absorb their financial consequences. 
 
Our mortgages, property taxes, payroll, utilities, and other expenses do not decrease because 
construction causes our sales to decline. Resolution R-2015-11 gives this Council the framework for 
suspending parking fees during special circumstances, including construction impacts. Three phases, 
$30 million construction of downtown clearly qualifies as a special circumstance. Therefore, I am 
asking the Council to suspend parking fees throughout the entire downtown for the duration of all 
phases. The City can continue enforcing reasonable time limits, so space is turned over, and remain 
available to the customers. Free parking will not eliminate the disruption, but it will send a powerful 
message; Downtown is open. Customers are welcome and the City stands behind the merchants 
being asked to endure this project. The City is investing almost $30 million in downtown’s 
future. Please protect the businesses that are trying to survive to be a part of that future. 
 
Ms. Brandie Wells owner of Shadow and Soul Emporium addressed the Committee next. Ms. Wells 
stated she has owned her business for nine years. She stated business has declined which forces 
her to think if she can retain the staff she currently has, or purchase inventory she needs for the 
holidays. She stated she is hearing from her customers that they are avoiding downtown. Ms. Wells 
stated she does not want her customers to have to be burdened with having to pay for parking in 
addition to the inconvenience they are experiencing. She added the notification about construction is 
not always accurate. She feels it is ironic that the City is worried about their budget impacts of losing 
parking revenues but she is worried that she might not be in business anymore due to the downtown 
construction. 
 
Ms. Roberta Mastrogiovanni who is a business owner and downtown merchant agreed the project 
ahead of us is a needed project but the merchants in downtown need to also survive. She noted her 
water and sewer bill has gone up 5% and expects taxes to increase as well. Ms. Mastrogiovanni 
added the economy in general is difficult currently. She felt the free parking for customers is 
essential, which would help save businesses and in turn the downtown. 
 
Mayor Kahn was the next speaker. He stated the proposal before the Committee needs to be 
addressed. He felt the City could experiment with some option but did not feel a three-year decision 
needed to be made right now, perhaps a two-month decision to address the rest of the construction 
season. 
 
Councilor Haas asked to see the costs with and without construction discussed today and asked that 
Page 67 of 210

 
2026-370 
 
this information be included in the minutes. 
 
Chair Powers suggested staff meeting with the merchants and come up with an option. The Manager 
stated this could delay the decision because once a recommendation comes out of the Committee, it 
has to go to the full City Council which recommendation could be brought to the next Finance 
meeting versus the normal process of coming back to FOP first. The Chairman stated he wasn’t 
expecting the item to be brought back to FOP. 
 
Councilor Chalice stated the City has the winter to come up with a more creative idea but given there 
are only two months in the construction season, noted there is a motion in front of the Committee to 
remove parking for the 2026 construction season. Because time was of the essence. She would 
support removing parking for this construction season and come up with a plan in the winter for the 
next construction season. The Manager noted the motion refers to waiving the parking for each 
construction phase not for the entire downtown but should the Committee wish to change that, it is 
prerogative of the Committee. 
 
Councilor Greenwald stated he agrees with Councilor Chalice, the City needs to act now and felt the 
entire downtown needs to be addressed. He commended Casella Construction and City staff but felt 
finer points are being missed. For example, there could be signs put up that say free parking but 
people are still likely to plug the meters. The other issue that has been raised is that merchants and 
the residents would use the spaces and felt this is something that needs to be self- enforced by the 
merchants and the property owners as well as the two-hour limit needs to be enforced. He felt the 
request is pennies compared to the entire construction project. 
 
Councilor Lake stated the rough math gives a cost of $45,000 in addition to what is estimated for the 
rest of the season. He stated this proposal makes sense and is a marketing tool to attract customers. 
 
Ms. Pamela Slack addressed the Committee and asked how much the City has lost in parking to 
date. The Manager stated most of the parking used so far has been by Casella and this has been 
part of the contract but stated she did not have that number today. 
 
The Manager stated instead of using the term date specific suggested remainder of the construction 
season, should the construction season extend longer. 
 
The following motion by Councilor Lake was duly seconded by Councilor Roberts. 
 
The Finance, Organization and Personnel Committee recommends that the Council grant free 
parking under the provisions of the Free Parking Policy (Resolution R-2015-11) for on-street public 
parking spaces within downtown for the remainder of the 2026 construction season, This to be 
coordinated with the Parking Division. Staff shall report back to the Finance Organization and 
Personnel Committee before the next construction phase for re-evaluation. 
 
Councilor Roberts stated he will support this request but noted parking is not free; it is a delay. From 
next year to the end of the construction, there is a $900,000 shift. To keep the parking account 
functional and to have the maintenance funds for downtown, the parking charges will need to 
increase to replace the losses during the free parking. 
 
The Manager stated when this proposal came forward in addition to calculating loss of revenue for 
construction and free parking, staff also looked at other revenue sources related to the Wells Garage. 
Page 68 of 210

 
2026-370 
 
She indicated since Council changed parking overnight for downtown, the City has seen a dramatic 
decrease in revenue. She stated there is an opportunity to open up those spaces that were used for 
permit parking for public parking. The Parking Manager will be bringing a proposal for Council review. 
 
Councilor Greenwald clarified free parking was only for on-street parking. The Manager agreed. 
 
The motion carried on a 4-0 vote. 
 
Mr. Weinreich suggesting convening a Committee in the winter to review this issue. 
 
Page 69 of 210

 
2026-394 
 
 
CITY OF KEENE 
NEW HAMPSHIRE 
 
ITEM #D.5. 
 
  
   
Meeting Date: 
September 17, 2026 
  
  
To: 
Mayor and Keene City Council 
  
  
From: 
Finance, Organization and Personnel Committee, Standing Committee 
  
  
Through: 
  
  
  
 
Subject: 
Acceptance of NH Juvenile Court Diversion Network Funding - Youth 
Services Manager 
  
  
 
  
Recommendation: 
On a vote of 4 to 0, the Finance, Organization and Personnel Committee recommends that the City 
Manager be authorized to do all things necessary to accept and expend funds provided by New 
Hampshire Juvenile Court Diversion Network for Youth Services programs. 
  
Attachments: 
None  
  
Background: 
Youth Services Manager Alyssa Bender addressed the Committee and stated each year a certain 
amount of money is awarded to her department based on prior three years of case numbers. This 
year, the State decided to transition from the administratively determined subcontract to a needs-
based RFA process. The City was fortunate that the full RFA was awarded in the amount of $46,988. 
This funding will allow the department to retain a 34-hour Intervention Specialist position. This 
individual has been with the department and has been expanding their hours throughout each year 
for the past nearly three years. 
 
The rest of the funding the department was able to receive from this grant allows the department to 
provide more positive youth activities, trainings, substance use prevention and intervention, and 
wellness programs. Ms. Bender went on to say that they were able to use the funding that they 
received last year to expand certifications for the Youth Services Manager and the Intervention 
Specialist for motivational interviewing, restorative justice training, and to train others on how to hold 
restorative practice conferences. 
 
She went on to say the statewide diversion network recently underwent an entire evaluation process 
through Georgetown University. In the past few years, the City has been attaining around a 92% 
successful completion rate statewide. In 2025, the department specifically for juvenile court diversion 
for Keene were also at 92% successful completion rate. In 2026, the department has had only four 
youth that either chose to drop out of the program or needed to be referred for further services. In 
previous years, the department ranges at around a 90% success rate, but this year for the first time 
Page 70 of 210

 
2026-394 
 
in the five years the department has seen that number over 90%. 
 
Ms. Bender stated some of the things this funding would assist with; Ms. Bender is one of an eight 
person New Hampshire team that is currently attending Georgetown University, the McCourt School 
of Public Policy where they attended an intensive week-long diversion certificate program. This 
program allows participants to create a capstone project to put together a standardized referral form. 
This referral form would be used by law enforcement throughout the State. This helps limit the 
burden law enforcement agencies being forced to train other officers that are moving from a diversion 
program to another diversion program. For example, the City covers all of Cheshire County, if a law 
enforcement officer in any of the 23 towns transitions to a different City within the County they would 
be entering a different diversion program and would have to learn an entirely new process. The hope 
is to standardize this process and make it easier for everyone. 
 
Ms. Bender stated the City is also in the process of increasing juvenile justice training for all law 
enforcement agencies in the state. Staff was recently invited to the Police Academy to start 
increasing their juvenile justice-training category. 
 
Councilor Chalice commended staff for their effort. She stated there is a new drug referred to as 
Kratom. She asked whether the substance abuse screening completed by the department now 
include Kratom. Ms. Bender stated they are looking into this and have already connected with the 
Monadnock Youth Coalition Director to discuss this drug. She went on to say that she has been 
hearing from youth who know about it. She stated she is also looking to add this drug to the screener 
they use. 
 
The following motion by Councilor Lake was duly seconded by Councilor Chalice. 
 
On a vote of 4 to 0, the Finance, Organization and Personnel Committee recommends that the City 
Manager be authorized to do all things necessary to accept and expend funds provided by New 
Hampshire Juvenile Court Diversion Network for Youth Services programs. 
 
Page 71 of 210

 
2026-402 
 
 
CITY OF KEENE 
NEW HAMPSHIRE 
 
ITEM #D.6. 
 
  
   
Meeting Date: 
September 17, 2026 
  
  
To: 
Mayor and Keene City Council 
  
  
From: 
Finance, Organization and Personnel Committee, Standing Committee 
  
  
Through: 
  
  
  
 
Subject: 
FY26 DOJ Byrne Justice Assistance Grant (JAG) Program Award - Police 
Captain 
  
  
 
  
Recommendation: 
On a vote of 4 to 0, the Finance, Organization and Personnel Committee recommends that the City 
Manager be authorized to do all things necessary to co-apply with Cheshire County, NH and to 
accept and expend the U.S. Department of Justice FY26 Byrne JAG in the amount allocated to the 
city in the amount of $6,519.00. 
  
Attachments: 
None  
  
Background: 
Police Captain Steve Tenney addressed the Committee and stated he was before the Committee 
regarding the JAG Grant, which he has been before the Committee in the past. This year the City has 
been awarded $6,519 dollars, which is about $1,000 more than last year’s award. The funds will be 
used for cell phones in cruisers as well as data packages for cruisers to keep up with changing times. 
This is the 16th year for this award. 
 
The following motion by Councilor Chalice was duly seconded by Councilor Roberts. 
 
On a vote of 4 to 0, the Finance, Organization and Personnel Committee recommends that the City 
Manager be authorized to do all things necessary to co-apply with Cheshire County, NH and to 
accept and expend the U.S. Department of Justice FY26 Byrne JAG in the amount allocated to the 
city in the amount of $6,519.00. 
 
Page 72 of 210

 
2026-404 
 
 
CITY OF KEENE 
NEW HAMPSHIRE 
 
ITEM #D.7. 
 
  
   
Meeting Date: 
September 17, 2026 
  
  
To: 
Mayor and Keene City Council 
  
  
From: 
Finance, Organization and Personnel Committee, Standing Committee 
  
  
Through: 
  
  
  
 
Subject: 
Acceptance of FAA/NHDOT Grant Funding – Wildlife Perimeter Fence 
Phase II Construction - Airport Director 
  
  
 
  
Recommendation: 
On a vote of 4 to 0, the Finance, Organization and Personnel Committee recommends that the City 
Manager be authorized to do all things necessary to accept, execute, and expend grant funding from 
the Federal Aviation Administration and New Hampshire Department of Transportation for the Wildlife 
Perimeter Fence Phase II Construction Project, SBG 08-32-2026 and SBG 08-33-2026. 
  
Attachments: 
None  
  
Background: 
Airport Director Ryan Cooley stated this item is requesting acceptance of two companion state block 
grants through NHDOT for phase two construction of the airport’s wildlife perimeter fence, which has 
been a project that has been going on for quite some time. He stated the department has an Airport 
Improvement Grant totaling $295,657 and an Airport Improvement Program Grant of $1,847,367, for 
a combined total of $2,143,024. 
 
He noted their requested action is to authorize the City Manager to do all things necessary to accept, 
execute, and expand the grant funding, which together funds 100% of the phase two construction 
scope. I would like to point out. 
 
He stated the estimate came in under budget. 
 
The following motion by Councilor Lake was duly seconded by Councilor Roberts. 
 
On a vote of 4 to 0, the Finance, Organization and Personnel Committee recommends that the City 
Manager be authorized to do all things necessary to accept, execute, and expend grant funding from 
the Federal Aviation Administration and New Hampshire Department of Transportation for the Wildlife 
Perimeter Fence Phase II Construction Project, SBG 08-32-2026 and SBG 08-33-2026. 
 
Page 73 of 210

 
2026-395 
 
 
CITY OF KEENE 
NEW HAMPSHIRE 
 
ITEM #D.8. 
 
  
   
Meeting Date: 
September 17, 2026 
  
  
To: 
Mayor and Keene City Council 
  
  
From: 
Finance, Organization and Personnel Committee, Standing Committee 
  
  
Through: 
  
  
  
 
Subject: 
Carry Forward Request - 2026 Unspent Wages - to Support Two One-time 
Community Development Department Expenditures - Community 
Development Director 
  
  
 
  
Recommendation: 
On a vote of 4 to 0, the Finance, Organization and Personnel Committee recommends that the City 
Council authorize the Community Development Department to carry forward $32,500 in unexpended 
Fiscal Year 2026 personnel appropriations and repurpose those funds to pay for the conversion of 
the Land Development Code to the online Municode system and to provide a local match for a 
Building Resilient Infrastructure and Communities (BRIC) match. 
  
Attachments: 
None  
  
Background: 
Community Development Director Paul Andrus addressed the Committee next. Mr. Andrus stated 
tonight’s request is for authorization to carry over $32,500 in FY26 unspent wages to fund two one-
time Community Development line items. 
 
The first item is the conversion of the Land Development Code in its current state to transfer over to 
Municode with the rest of City Code. This will bring it in line with the rest of the City Code, but also 
bring it in line with the upcoming ADA accessibility requirements with the changes in the City website. 
$17,000 for initial conversion plus $3,000 to accommodate amendments during the first year. 
 
The second item is for a match for the Building Resilient Infrastructure and Communities Grant 
funding. The Department applied for a $37,500 grant for software and equipment for electronic plan 
review capabilities as part of the City’s Hazard Mitigation program. This will enhance the 
department’s abilities to continue with the new permitting system (Open Gov System). 
 
The department should hear about receipt by end of this year but this would at least match what is 
accounted for. 
 
Councilor Lake asked by bringing the entire LDC over to Municode whether there will be any 
Page 74 of 210

 
2026-395 
 
additional fees accrued because of the extra capacity. Mr. Andrus stated his understanding is that 
there will be recurring cost on top of what the Clerk’s Office is currently paying for those Municode 
updates. Hence, the reason for at least the first year, requesting funds to be able to cover that. In 
subsequent years, it would need to be accounted in the normal budget process. The Councilor asked 
whether Mr. Andrus knows what those costs might. Mr. Andrus stated he did not at this time and it 
will depend on how much the LDC is updated. 
 
The following motion by Councilor Roberts was duly seconded by Councilor Chalice. 
 
On a vote of 4 to 0, the Finance, Organization and Personnel Committee recommends that the City 
Council authorize the Community Development Department to carry forward $32,500 in unexpended 
Fiscal Year 2026 personnel appropriations and repurpose those funds to pay for the conversion of 
the Land Development Code to the online Municode system and to provide a local match for a 
Building Resilient Infrastructure and Communities (BRIC) match. 
 
Page 75 of 210

 
2026-397 
 
 
CITY OF KEENE 
NEW HAMPSHIRE 
 
ITEM #D.9. 
 
  
   
Meeting Date: 
September 17, 2026 
  
  
To: 
Mayor and Keene City Council 
  
  
From: 
Finance, Organization and Personnel Committee, Standing Committee 
  
  
Through: 
  
  
  
 
Subject: 
2025 Hazmat Equipment Grant - Period of Performance Extension - Fire 
Chief 
  
  
 
  
Recommendation: 
On a vote of 4 to 0, the Finance, Organization and Personnel Committee recommends that the City 
Manager be authorized to do all things necessary to execute the 2025 Homeland Security Grant 
agreement amendment. 
  
Attachments: 
None  
  
Background: 
Fire Chief Seymour stated he was before the Committee requesting authorization for the City 
Manager to be authorized to do all things necessary to execute a 2025 Homeland Security Grant 
amendment extending the period of performance for that grant from September 30, 2026 to August 
31, 2028. He stated there were no other material changes to the grant. This is recommended after 
some changes to purchasing requirements giving staff time to complete those changes. 
 
The following motion by Councilor Chalice was duly seconded by Councilor Lake. 
 
On a vote of 4 to 0, the Finance, Organization and Personnel Committee recommends that the City 
Manager be authorized to do all things necessary to execute the 2025 Homeland Security Grant 
agreement amendment. 
 
Page 76 of 210

 
2026-415 
 
 
CITY OF KEENE 
NEW HAMPSHIRE 
 
ITEM #D.10. 
 
  
   
Meeting Date: 
September 17, 2026 
  
  
To: 
Mayor and Keene City Council 
  
  
From: 
Finance, Organization and Personnel Committee, Standing Committee 
  
  
Through: 
  
  
  
 
Subject: 
FY28 Ambulance Replacement - Fire Chief 
  
  
 
  
Recommendation: 
On a vote of 4 to 0, the Finance, Organization and Personnel Committee recommends that the City 
Manager be authorized to do all things necessary to execute a contract with Autotronics of Maine for 
the purchase and construction of the Fire Department ambulance. 
  
Attachments: 
None  
  
Background: 
Chief Seymour stated the next item is to recommend the City Manager be authorized to do all things 
necessary to execute a contract with Autotronics for the purchase and construction of the new Fire 
Ambulance. He stated this is coming as a request to order the ambulance early. He stated the item is 
currently in the CIP for 2028 to order a new ambulance. The Chief stated the department has been 
having fleet issues as it relates to diesel motors. 
 
In order to get ahead of these issues, the department would like to process the order now so it 
arrives in July/August of 2028 versus ordering in July/August 2028, which will place receipt of the 
truck out 24 to 36 months. Ordering it now will enable receipt of the ambulance in the next fiscal year. 
 
Councilor Lake asked whether the City would be expending funds this year instead of in 2028. Chief 
Seymour stated it is payment on delivery. The City would not have to spend anything until next year. 
 
Councilor Chalice stated she likes the idea of not paying 5% – 10% extra by purchasing the item 
sooner. 
 
The following motion by Councilor Lake was duly seconded by Councilor Roberts. 
 
On a vote of 4 to 0, the Finance, Organization and Personnel Committee recommends that the City 
Manager be authorized to do all things necessary to execute a contract with Autotronics of Maine for 
the purchase and construction of the Fire Department ambulance. 
 
Page 77 of 210

 
2026-417 
 
 
CITY OF KEENE 
NEW HAMPSHIRE 
 
ITEM #D.11. 
 
  
   
Meeting Date: 
September 17, 2026 
  
  
To: 
Mayor and Keene City Council 
  
  
From: 
Finance, Organization and Personnel Committee, Standing Committee 
  
  
Through: 
  
  
  
 
Subject: 
LWCF Grant Round 33 Amendment - Skate Park - Deputy City Manager 
  
  
 
  
Recommendation: 
On a vote of 4 to 0, the Finance, Organization and Personnel Committee recommends that the City 
Manager be authorized to accept and execute an amendment to Land and Water Conservation Fund 
sub-grant #33-00761_Patricia T Russell Park-II, with the State of New Hampshire to increase the 
award limit by $75,000 (from $225,000 to $300,000), and to extend the completion date by one-year 
(from 9/30/2026 to 9/30/2027), and to increase the agreed-to project scope further including a 
parking lot and pathway extensions at Patricia T Russell Park in addition to the development of the 
skate park. 
  
Attachments: 
None  
  
Background: 
City Engineer Bryan Ruoff addressed the item on behalf of the Deputy City Manager. He stated this 
item is a request for the City Manager to be authorized to accept and execute an amendment to the 
existing Land and Water Conservation Fund sub-grant for the Patricia T Russell Park and Skate Park 
site. 
 
He noted that about 18 months ago, the City successfully completed the demolition of the Findings 
building property as part of that demolition the monitoring wells that were on that site were 
accidentally removed. The City’s consultant reached out to DES to relocate these wells, DES has 
advised the City to wait on the relocation of the wells due to soil issues. The Deputy City Manager as 
a result look at incorporating a parking area that covers that area of contaminated soils that DES is 
concerned about. He also concurrently asked the Land and Water Conservation Fund Grant 
Committee if the City could receive an amendment for additional funds for that construction. The City 
has applied for those funds which have been conditionally approved. Staff is now looking for approval 
to accept and execute these grant funds. 
 
Mr. Ruoff stated staff has gone before the MSFI Committee regarding this project and discussed 
some features that could be added as part of the project based on community and Council input. 
 
Page 78 of 210

 
2026-417 
 
Councilor Chalice stated the community has had a hard time with this part of the Pat Russell Park. 
These decisions were made very quickly and felt there could have been other options rather than 
adding another parking lot. She stated the community and the Conservation Commission have been 
encouraged by the negotiations, discussions and creative problem solving that has gone on to date 
and are looking forward to that continuing to move forward. She stated she looks forward to 
continuing discussions with the community as they finish these decisions. 
 
The following motion by Councilor Roberts was duly seconded by Councilor Chadbourne. 
 
On a vote of 4 to 0, the Finance, Organization and Personnel Committee recommends that the City 
Manager be authorized to accept and execute an amendment to Land and Water Conservation Fund 
sub-grant #33-00761_Patricia T Russell Park-II, with the State of New Hampshire to increase the 
award limit by $75,000 (from $225,000 to $300,000), and to extend the completion date by one-year 
(from 9/30/2026 to 9/30/2027), and to increase the agreed-to project scope further including a 
parking lot and pathway extensions at Patricia T Russell Park in addition to the development of the 
skate park. 
 
Page 79 of 210

 
2026-399 
 
 
CITY OF KEENE 
NEW HAMPSHIRE 
 
ITEM #D.12. 
 
  
   
Meeting Date: 
September 17, 2026 
  
  
To: 
Mayor and Keene City Council 
  
  
From: 
Finance, Organization and Personnel Committee, Standing Committee 
  
  
Through: 
  
  
  
 
Subject: 
Relating to the Execution of an Agreement with KeyNetGPS - City Engineer 
  
  
 
  
Recommendation: 
On a vote of 4 to 0, the Finance, Organization and Personnel Committee recommends that the City 
Manager be authorized to do all things necessary to negotiate and execute a Participant Agreement 
with KeyNetGPS. 
  
Attachments: 
None  
  
Background: 
City Engineer Bryan Ruoff addressed the next time. This item relates to an agreement with KeyNet 
GPS. He stated the City has worked with this entity for the past 15 years. With this agreement, the 
City agrees to let them use our GPS base station to expand their network. It is essential infrastructure 
for the engineering division in order to design and construct projects. As part of that agreement, 
KeyNet GPS pays the City $2,000 a year for the added coverage that they get from being able to 
utilize the City’s base station. 
 
The last agreement the City had with this entity has expired but are continuing to pay the City under 
the terms of the previous agreement. 
 
Councilor Lake asked who would be a typical user of this product. Mr. Ruoff stated the simplistic way 
to explain this item is that it is a signal booster. Other individuals doing surveys get a better signal 
and better coverage by being able to use the City’s signal and boost KeyNet’s signal, which extends 
from Virginia to Maine. He stated it is mutually beneficial for the City and the community at large. 
 
Councilor Chalice stated she is nervous about our data being out in the digital. She asked whether 
third parties will now be involved with this data and would this data become more vulnerable to 
commercial applications being able to access it. Mr. Ruoff stated this is not data as much as it is a 
signal. 
The City has a base station that provides a signal for its GPS units. The City needs that to perform 
engineering tasks. The Councilor clarified our data is not being shared, we are just permitting their 
signal to become stronger. Mr. Ruoff agreed. 
Page 80 of 210

 
2026-399 
 
 
Councilor Haas asked whether the City requests an increase in the cost of $2,000 because KeyNet 
GPS is getting much more use out the City’s base station as they grow their business. 
 
Mr. Ruoff stated it is written into the agreement; it is percentage-based on the revenue they generate. 
The $2,000 is just a rough estimate. Recently, the City has seen it closer to $3,000. 
 
The following motion by Councilor Chalice was duly seconded by Councilor Lake. 
 
On a vote of 4 to 0, the Finance, Organization and Personnel Committee recommends that the City 
Manager be authorized to do all things necessary to negotiate and execute a Participant Agreement 
with KeyNetGPS. 
 
Page 81 of 210

 
2026-400 
 
 
CITY OF KEENE 
NEW HAMPSHIRE 
 
ITEM #D.13. 
 
  
   
Meeting Date: 
September 17, 2026 
  
  
To: 
Mayor and Keene City Council 
  
  
From: 
Finance, Organization and Personnel Committee, Standing Committee 
  
  
Through: 
  
  
  
 
Subject: 
Relating to the Execution of a Change Order with Structural Preservation 
Services - City Engineer 
  
  
 
  
Recommendation: 
On a vote of 4 to 0, the Finance, Organization and Personnel Committee recommends that the City 
Manager be authorized to do all things necessary to negotiate and execute a change order with 
Structural Preservation Services, Inc in an amount not to exceed $65,325 for the City Hall Parking 
Garage Rehab Project (22M006AA). 
  
Attachments: 
None  
  
Background: 
Mr. Ruoff stated this item relates to the execution of a change order or structural preservation 
services for the City Hall parking garage project. The City awarded the project with just the base bid. 
Additional needs have now been added to extend the life of that structure and maximize the benefit 
of those repairs, for example, items such having the upper deck as a lighted area, seal coat which 
lasts ten years versus just two years, additional steel repairs. Because of these changes additional 
repairs were identified during construction. 
 
Mr. Ruoff stated even with these changes, the project still came under the overall budget by about 
$33,500. 
 
The following motion by Councilor Lake was duly seconded by Councilor Roberts. 
 
On a vote of 4 to 0, the Finance, Organization and Personnel Committee recommends that the City 
Manager be authorized to do all things necessary to negotiate and execute a change order with 
Structural Preservation Services, Inc in an amount not to exceed $65,325 for the City Hall Parking 
Garage Rehab Project (22M006AA). 
 
Page 82 of 210

 
2026-421 
 
 
CITY OF KEENE 
NEW HAMPSHIRE 
 
ITEM #D.14. 
 
  
   
Meeting Date: 
September 17, 2026 
  
  
To: 
Mayor and Keene City Council 
  
  
From: 
Finance, Organization and Personnel Committee, Standing Committee 
  
  
Through: 
  
  
  
 
Subject: 
Sale of Surplus Mechanical Ventilators - Fire Chief 
  
  
 
  
Recommendation: 
On a vote of 4 to 0, the Finance, Organization and Personnel Committee recommends that the City 
Council suspend the public auction or competitive quotation requirements of City Ordinance O-2023-
15, Section 2-1341; authorize the City Manager to do all things necessary to sell three surplus Zoll Z-
Vent mechanical ventilators to the Town of Fitzwilliam for $6,000, with sale proceeds to be deposited 
to the General Fund; and direct staff to bring forward a separate resolution to the City Council 
requesting an appropriation for the purchase of swift water rescue dry suits for the Keene Fire 
Department. 
  
Attachments: 
None  
  
Background: 
Fire Chief Seymour addressed the Committee again. The Chief stated this is a request to suspend 
public auction or competitive quotation requirements, permitting the department to sell three surplus 
ventilators to the Town of Fitzwilliam Fire Department. The ventilators being replaced by Keene is as 
part of this fiscal year’s CIP project. The $6,006 will be placed in the General Fund and staff will be 
coming back with a Resolution to use those funds to purchase dry suits for swift water rescue. 
 
Councilor Chalice thanked staff for being able to keep this in our system and being able to receive 
more from their sale. 
 
Councilor Lake asked whether these suits are a replacement. The Chief stated they are a 
replacement for suits that are worn out. 
 
The following motion by Councilor Chalice was duly seconded by Councilor Lake. 
 
On a vote of 4 to 0, the Finance, Organization and Personnel Committee recommends that the City 
Council suspend the public auction or competitive quotation requirements of City Ordinance O-2023-
15, Section 2-1341; authorize the City Manager to do all things necessary to sell three surplus Zoll Z-
Vent mechanical ventilators to the Town of Fitzwilliam for $6,000, with sale proceeds to be deposited 
Page 83 of 210

 
2026-421 
 
to the General Fund; and direct staff to bring forward a separate resolution to the City Council 
requesting an appropriation for the purchase of swift water rescue dry suits for the Keene Fire 
Department. 
 
Page 84 of 210

 
2026-390 
 
 
CITY OF KEENE 
NEW HAMPSHIRE 
 
ITEM #F.1. 
 
  
   
Meeting Date: 
September 17, 2026 
  
  
To: 
Mayor and Keene City Council 
  
  
From: 
Mari Brunner, Senior Planner 
  
  
Through: 
Elizabeth Ferland, City Manager 
Paul Andrus, Community Development Director 
  
  
  
 
Subject: 
Proposed Amendments to the Keene Community Power Plan - Community 
Development 
  
  
 
  
Recommendation: 
That the proposed amendments to the Keene Community Power Plan be referred to the Finance, 
Organization and Personnel Committee. 
  
Attachments: 
1. 
8-7-26 clean draft 
2. 
8-7-26 redline draft 
  
  
Background: 
Keene Community Power is a program that provides electricity supply options to Keene residents 
and businesses on a default ("opt-out") basis. The program was launched in June 2023 and is 
currently in its second Electric Service Agreement (ESA) contract, effective December 2025 through 
December 2027. Electric customers in Keene can join or leave the program or switch options at any 
time. The default product, which is about 2 ¢/kWh cheaper than the current Eversource Default 
Service, costs 12.100 ¢/kWh and includes 50% renewable energy. The other products offered 
through the program range in price and renewable energy content from 11.220 ¢/kWh / 25% 
renewables (Keene Basic), 11.580 ¢/kWh / 35% renewables (Keene 10), to 13.890 ¢/kWh / 100% 
renewables (Keene 100).  
 
City staff propose amending the existing Community Power Plan and ESA to change the default 
option for low-income customers. Low-income customers can be identified in utility data as those 
customers participating in the New Hampshire Electric Assistance Program (EAP), which provides a 
discount on the entire electricity bill for income-eligible customers. The City proposes to change the 
default product for customers participating in the EAP to Keene Basic, the least-cost option, rather 
than the current default product, Keene Standard. Keene Standard will continue to be the default 
product for all other customers. EAP customers will retain the option to switch to any other Keene 
Community Power product, if they wish. There are currently just over 300 EAP customers 
Page 85 of 210

 
2026-390 
 
participating in Keene Community Power.  
 
The following table provides a summary of the proposed change: 
 
 
Keene Basic 
Keene 10 
Keene Standard 
Keene 100 
Renewable Energy 
Meets State Minimum 
(25% in 2026) 
Adds 10% NH Class I 
(35% in 2026) 
Adds 25% NH Class I 
(50% in 2026) 
Adds 75% NH Class I 
(100% in 2026) 
Price  
(Dec. 2025 - Dec. 2027) 
11.220 ¢/kWh 
11.580 ¢/kWh 
12.100 ¢/kWh 
13.890 ¢/kWh 
EAP Participants 
 
Default 
Option 
Option 
Option 
All Other Customers 
Option 
Option 
Default 
Option 
 
The proposed amendments to the Plan are limited to the following: 
• On pages 5-6, the “Equitable treatment” section references that the Program will distinguish 
between customers that participate in the New Hampshire Electric Assistance Program (EAP) 
and other customers by assigning a default product to EAP customers and a default product to 
all other customers. On page 31, the “Exhibit 1, Historical overview” includes a new entry 
documenting this amendment. 
• Throughout the Plan, references to specific consulting firms have been replaced with the term 
"Community Power Consultant" to make the language more flexible and reduce the need for 
future plan amendments when consulting relationships change. The Plan also directs readers 
to the professional services agreement for additional information regarding the consultant and 
their responsibilities. 
• The timeline of revisions to the plan was moved from the top of the “Historical 
overview” section in Exhibit 1. 
 
If this proposal is approved, existing EAP customers who are enrolled in Keene Standard will be 
moved to Keene Basic at the next available meter read date, following public announcements from 
the City. For EAP customers that have affirmatively opted in to Keene 10 or Keene 100, the Program 
will honor that choice and not make any change to their product. All new eligible EAP customers will 
be automatically enrolled in Keene Basic unless they choose a different product or opt out of the 
program. 
 
Page 86 of 210

 
 
 
 
 
 
 
CITY OF KEENE 
COMMUNITY POWER PLAN 
 
Adopted May 6, 2021Amendment Adopted 
March 20, 2026 
Page 87 of 210

City of Keene 
 
Community Power Plan 
 
 
 
 
TABLE OF CONTENTS 
 
I. Community Power Goals and Vision 
2II. Process to Develop and Approve Plan
 
4III. Customer Participation
 
5III.a. Applicable classes of customers
 
5III.b. Universal access
 
5III.c. Equitable treatment
 
5III.d. Reliability
 
7IV. Organizational Structure
 
7IV.a Roles
 
7IV.b. Data Security
 
8V. Electricity Supply Product Options
 
9V.a. Default and Optional Electricity Supply Products
 
9V.b. Green & Local Definitions
 
11V.c. NH Class I Renewable Energy
 
11VI. Operation
 
12VI.a.  Issue an RFP for power supply, select a competitive supplier and provide notice
 
12VI.b.  Implement public information program including Customer Notification Letters
 
14VI.c.  Enroll customers and provide service
 
16VI.d.  Plan for Program evolution
 
17VII. Funding
 
17VIII. Rate Setting and Other Costs to Participants
 
18IX. Net Metering Compensation
 
19X. Electric Assistance Program and other discounts
 
20XI. Aggregating Municipalities & Buying Group
 
20XII. Promoting Energy Efficiency
 
20XIII. Method of Entering and Terminating Agreements with Other Entities
 
21XIV. Rights and Responsibilities of Program Participants
 
22XV. Extensions or Termination of Program
 
22XVI. Planned Schedule
 
23XVII. Conclusion
 
24Exhibit I - Historical Overview
 
25Exhibit II - Education & Outreach Plan
 
32Exhibit III - Data Protection Plan
 
41 
 
I. Community Power Goals and Vision 
 
The City of Keene will develop and implement its Community Power Program 
(“Program”) as described in this Community Power Plan (“Plan”).  
 
Community Power creates new electricity supply choices for Keene residents and 
businesses with the potential for cost and environmental benefits beyond that of the 
Default Service supply from the electric distribution utility, Eversource. Instead of simply 
utilizing Eversource’s electricity supply, Keene will bundle together the electricity needs 
of its residents and small businesses and put out a bid for an electricity supplier to 
provide the necessary electricity at competitive prices. With Community Power, the City 
is able to make strategic decisions about when to solicit bids, lock in fixed pricing for 
multiple years, and increase the amount of renewable energy above the existing statewide 
minimum. Eversource will continue to manage billing and maintain wires and poles. 
Page 88 of 210

City of Keene 
 
Community Power Plan 
 
 
 
 
August 5, 2026 
 
 
 
 
                    3 
 
Community Power is part of the City’s comprehensive climate and energy planning 
process. One of the primary goals of Keene’s process, embodied in the City Council’s 
2018 Resolution R 2018-36, is to achieve 100% renewable electricity use: 
“It is the goal of the City of Keene that all electricity consumed in the City will 
come from renewable energy sources by the year 2030 and that 100% of all 
thermal energy and energy used for transportation come from renewable energy 
sources by the year 2050. This goal will apply to the entire Keene community, not 
just municipal government operations. 
Keene’s climate and energy planning process also seeks to support equity, energy 
efficiency, job creation, and climate resilience and preparedness. 
To establish specific goals and a vision for the Program, the City held information 
sessions and surveyed community members to ask about their priorities and preferences. 
While individual opinions differed, there was strong support from the majority of survey 
respondents from all income classes and age groups for five community priorities related 
to electricity supply:  
● Choice for electricity options 
● Control of electricity costs 
● Competitive rates and lower bills 
● Increased local renewable energy 
● Local jobs 
 
 
Particularly strong among 
respondents was support for 
renewable energy. As shown at 
right, over 90% of all respondents 
indicated a desire for extra 
renewables, and almost half 
indicated a willingness to pay more 
for extra renewables.  
The desire for extra renewable 
energy generally held across age and 
household income brackets, with the 
strongest support overall in the 
middle income bracket, as shown below. 
Page 89 of 210

City of Keene 
 
Community Power Plan 
 
 
 
 
August 5, 2026 
 
 
 
 
                    4 
 
Do you want extra renewable energy, by household income? 
 
 
 
 
 
Detailed survey results can be found in Exhibit I.  
The Keene community goals translate into the following goals for Keene’s Community 
Power Program: 
1. Establish a standard (or default) electricity supply product that delivers economic 
value via competitive rates, uses more renewable energy, and supports the growth of 
local renewable energy as defined in Section V.b.  
2. Increase the contribution of renewables toward 100% renewable electricity for the 
entire Program by 2030, using optional products, tools and incentives that include: 
● Provide optional electricity supply products with alternative renewable electricity 
amounts (for example, 100%). Options afford individual participants the 
opportunity to meet higher renewable goals immediately and increase the overall 
renewable energy impact of the Program; 
● Catalyze the development of distributed energy resources within Keene, such as 
rooftop solar, by providing enhanced net metering and other incentives;  
● Explore opportunities to support the development of and utilize new renewable 
energy supply at utility scale within our region;  
● Support electrification, particularly of thermal and transportation sectors; 
● Support energy efficiency initiatives to reduce total Program electricity demand 
and costs for participants; and 
● Explore, and implement when possible, other tools and incentives successfully 
established elsewhere in New Hampshire, in other states or around the world (for 
example, time-of-use rate structures).  
3. Engage the community to bring new ideas and resources into the Program, through 
Page 90 of 210

City of Keene 
 
Community Power Plan 
 
 
 
 
August 5, 2026 
 
 
 
 
                    5 
every means possible, over the life of the program. Also engage the community to 
assess how benefits of the Program can be allocated equitably. 
4. Work with regulators, utilities and suppliers to craft solutions and remove barriers to 
harnessing all cost-effective solutions, especially recognizing that increased 
electrification will be part of the solution toward 100% transportation and thermal 
renewable energy by 2050. 
5. Expand the Program’s impact by empowering other communities with similar goals. 
This includes sharing information and materials to help launch other programs as well 
as evaluating regional buying groups as to whether they provide greater cost savings 
to all participants through economies of scale.  
The vision for Keene Community Power is to launch a timely Community Power 
Program that provides community members with attractive choices and substantially 
enhanced renewable energy options at competitive prices, and opens a new promising 
community path to 100% renewable electricity in 2030.  
Community Power is emerging as a leading strategy to reach multiple community goals 
efficiently and equitably. The City of Keene looks forward to refining this vision for 
meeting our 100% renewable energy goals and all of Keene’s goals that are impacted by 
energy choices. 
 
II. Process to Develop and Approve Plan 
 
Before implementation, the Plan must be reviewed and approved by the Community 
Power Committee (“Committee”) and adopted by the Keene City Council.  The 
Committee will ensure that the Program satisfies all of the statutory requirements, 
including that the Plan provides universal access, reliability and equitable treatment for 
all classes of customers. This Plan was developed to demonstrate that the Program of the 
City satisfies all the requirements necessary for approval by the Committee and adoption 
by the City Council. 
 
This plan was developed through the following process, consistent with New Hampshire 
Revised Statutes Annotated (RSA) 53-E: 
 
1. Creation of Community Power Committee 
2. Creation of a Draft Plan with public hearings, 
3. Approval of Plan by Community Power Committee, 
4. Adoption of Plan by City Council, and 
5. Submission of Final Plan to Public Utilities Commission. 
 
Please see Exhibit I for detail on these steps. 
Page 91 of 210

City of Keene 
 
Community Power Plan 
 
 
 
 
August 5, 2026 
 
 
 
 
                    6 
 
III. Customer Participation  
 
III.a. Applicable classes of customers 
 
The Community Power Program will be available for the residential, commercial and 
industrial classes of electricity customers as defined by City’s electric distribution 
company, Eversource (“Applicable Classes”). See Eversource for current classes: 
https://www.eversource.com/content/nh/residential/my-account/billing-payments/about-your-
bill/rates-tariffs 
 
III.b. Universal access 
 
The Plan provides for universal access for all customers by guaranteeing that all customer 
classes will be included in the Program under equitable terms. 
 
All retail electric customers will have access to the Program. All retail electric customers 
receiving Default Service supply from the electric distribution utility will be eligible for 
automatic enrollment in the Program (“Eligible Customers”), and they will be 
automatically enrolled in the Program unless they choose to opt out.   
 
All customers will have the right to opt-out of the Program at any time with no charge. 
 
As required by the statute, there shall be equitable treatment of Applicable Classes within 
the Program. 
 
 
III.c. Equitable treatment 
 
The community power statute requires equitable treatment of all classes of customers 
subject to any differences arising from varying opportunities, tariffs and arrangements 
between different electric distribution utilities in their respective franchise territories. 
This does not mean that all classes of customers must be treated “equally,” but rather that 
similarly situated classes of customers be treated “equitably.” 
 
Among applicable classes of customers, the Plan makes four distinctions.  
 
First, the Program will distinguish among customer classes by soliciting separate pricing 
for each of the same customer classes the electric distribution utility uses for the 
distribution service.  
 
Second, the Program will distinguish between customers that participate in the New 
Hampshire Electric Assistance Program (EAP) and other customers by assigning a 
Page 92 of 210

City of Keene 
 
Community Power Plan 
 
 
 
 
August 5, 2026 
 
 
 
 
                    7 
default product to EAP customers and a default product to all other customers.  
 
Third, the Program will distinguish between customers receiving the default product and 
customers that affirmatively choose an optional product. Customers selecting an optional 
product will be charged the price associated with that product. 
 
Fourth, the Program will distinguish between customers that join the Program through an 
automatic enrollment process (i.e. customers who do not choose to opt-out) and 
customers that affirmatively elect to join the Program. Such distinction will determine 
whether the customer receives the price specified for their rate class and product set in 
the Electricity Supply Agreement (“Program pricing”) or a price based on market prices 
at the time the customer joins the Program. 
 
● Customers that join through an automatic enrollment process include a) the initial 
Eligible Customers at the start of the Program and b) new Eligible Customers that 
move into the City after the Program start-date. All initial Eligible Customers will 
receive the Program pricing for their rate class. Among new Eligible Customers, 
the Program will distinguish between new residential and small commercial 
customers, who will receive the Program pricing, and all other commercial and 
industrial customers, who may receive pricing based on market prices at the time 
the customer joins the Program.  
 
● Finally, customers that affirmatively elect to join include two types of customers: 
a) customers that were being served by a Competitive Supplier at the start of the 
Program but then later join the Program; and b) customers re-joining the Program 
after having previously opted out. Those customers that were being served by a 
Competitive Supplier at Program initiation but who later join the Program will be 
treated the same as new Eligible Customers – residential and small commercial 
customers will receive the Program pricing and all other commercial and industrial 
customers may be offered a price based on the then-current market rates. All 
customers that join the Program after having previously opted out may be offered 
a price based on then-current market rates rather than the Program price. This 
distinction is designed to limit any incentive for frequent switching back and forth 
between the Program and Default Service of the electric distribution utility. 
 
III.d. Reliability 
 
Reliability has both physical and financial components. The Program will address both 
through the Electricity Supply Agreement (“ESA”) with the Competitive Electric Power 
Supplier (“Competitive Supplier”), which shall be the Load Serving Entity. From a 
physical perspective, the ESA commits the Competitive Supplier to provide all-
requirements power supply and to use proper standards of management and operations. 
All-requirements power supply includes all of the electrical energy, capacity, reserves, 
Page 93 of 210

City of Keene 
 
Community Power Plan 
 
 
 
 
August 5, 2026 
 
 
 
 
                    8 
ancillary services, transmission services, transmission and distribution losses, congestion 
management, and other such services or products necessary to provide firm power supply 
to Program participants and meet the state’s Renewable Portfolio Standard and any 
additional renewable energy requirements of the default or optional products. The electric 
distribution utility will continue to remain responsible for delivery service, including the 
physical delivery of power to the customer, maintenance of the delivery system, and 
restoration of power in the event of an outage. From a financial perspective, the ESA 
requires the Competitive Supplier to pay actual damages for any failure to provide supply 
at the contracted rate (i.e., to pay the difference between the contract rate and the utility 
supply rate). The ESA requires the Competitive Supplier to maintain insurance and the 
Request for Proposals for a Competitive Supplier will require that an investment-grade 
entity either execute or guarantee the ESA. Accordingly, the Program satisfies the 
reliability requirement of the statute. 
 
 
IV. Organizational Structure  
 
IV.a Roles 
Community Power Committee (CPC): The Finance, Organization and Personnel 
Committee, a standing committee of the City Council, voted to request that the Mayor 
constitute an ad-hoc Community Power Committee, as the designee of the Mayor and as 
established under RSA 53-E:6, to develop and approve a Community Power Plan for 
submission to and adoption by the City Council, as the legislative body of the City. The 
Committee will develop a draft plan, hold public hearings on the plan to solicit public 
input, revise the draft plan based on that input, and ultimately submit an approved Plan to 
the City Council. See Exhibit I for detail on the public input process. 
 
City Council: In accordance with RSA 53-E:7, the City Council, as the legislative body of 
the municipality, will be the body to adopt the Community Power Plan after it has been 
approved by the Community Power Committee. The City Council will review and 
approve any proposed amendments to the Plan. 
 
City Manager: The City Manager is designated by the City Council to provide direct 
management and oversight of the Plan on behalf of the City. The City Manager, or their 
designee(s), shall regularly meet with the Community Power Consultant for the purpose 
of providing oversight of the Plan and shall make recommendations to the City Council 
on Plan amendments. The City Manager shall authorize the issuance of bids for power 
supply and shall negotiate and execute a Electric Service Agreements (“ESA”) consistent 
with the products and goals described in this Plan.  
 
Community Power Consultant:  The Community Power Consultant will manage certain 
Program activities under the direction of the City Manager. Their responsibilities will 
include managing the supply procurement, developing and implementing the public 
Page 94 of 210

City of Keene 
 
Community Power Plan 
 
 
 
 
August 5, 2026 
 
 
 
 
                    9 
education plan, interacting with the electric distribution utility and monitoring the supply 
contract, as detailed in the professional services agreement. 
Competitive Supplier:  The Competitive Supplier will provide power for the Program, 
provide customer support including staffing a toll-free number for customer questions, 
and fulfill other responsibilities as detailed in the ESA.  The Competitive Supplier shall 
be required to enter into an individual ESA with the City under terms deemed reasonable 
and appropriate for the retail electric customers by the City Manager. 
 
Buying Group:  The City may elect to join with other municipal aggregators in combining 
its load for purposes of soliciting bids from Competitive Suppliers.  The purpose of the 
Buying Group is to allow municipal aggregators to capture the benefits of collective 
purchasing power while retaining full municipal autonomy.  The City shall be 
represented by the City Manager, or their designee, on the executive committee of the 
Buying Group. The City, through the City Manager or their designee, shall select a 
Competitive Supplier based on the needs of the City and shall not be required to select 
the same terms or Competitive Supplier as other members of the Buying Group. 
 
Retail electric customers: Retail electric customers shall include all electric customers 
taking distribution service of electricity located within the geographic boundaries of the 
City of Keene. 
 
IV.b. Data Security 
Pursuant to RSA 363:38 and PUC 2004.19, the Program, as an aggregator, is required to 
protect individual customer data that it may receive as part of Program implementation. 
See Exhibit III for the data protection plan to be used by the Program. 
 
 
 
 
 
 
 
 
V. Electricity Supply Product Options  
 
V.a. Default and Optional Electricity Supply Products 
The Program offered the following electricity supply products in its initial ESA and may 
adjust these products in subsequent ESAs, taking into account the goals of the Program, 
market conditions and implementation experience. Current product offerings will always 
be posted at the Program website, KeeneCommunityPower.com. Any retail electric 
customer that joins through an automatic enrollment process, shall be enrolled into the 
Program’s default product, unless they affirmatively choose to enroll in any of the 
optional products. 
Page 95 of 210

City of Keene 
 
Community Power Plan 
 
 
 
 
August 5, 2026 
 
 
 
 
                    10 
 
Default Product  
(Automatic enrollment) 
Optional Products 
Product 
Name 
Keene 
 Local Green 
Keene  
Basic 
Keene  
50% Local Green 
Keene  
100% Local Green
Product 
Goals 
Increase renewable 
energy use while 
maintaining 
competitive rates  
Most competitive 
rate (no increase 
in renewable 
energy use) 
Significant 
increase in 
renewable energy 
use (e.g. 50%) 
Largest increase 
in renewable 
energy use (e.g. 
100%) 
 
 
● Default Product 
○ Keene Local Green: The Program intends to offer Keene Local Green as 
its default product. The Keene Local Green product has a goal of 
maintaining rough cost parity with Eversource’s Default Service supply 
while including extra renewable electricity above the Renewable Portfolio 
Standard (“RPS”) required in New Hampshire. The exact amount of extra 
renewable electricity will be determined after the receipt of bids from 
competitive suppliers. It is expected to include 5-10% extra renewable 
energy in the initial ESA. It is the City's goal to increase this amount in 
subsequent ESAs, while maintaining cost parity with Eversource’s Default 
Service.  This product is intended to include as much local renewable 
energy as possible, as defined in Section V.b. Including additional 
renewable energy in this product enables customers to have a meaningful 
impact on the reduction of greenhouse gas emissions through the support of 
local renewable energy sources. 
 
● Optional Products  
 
○ Keene Basic: Some customers may feel that the amount of new, renewable 
energy required by the RPS in New Hampshire is sufficient to fulfill their 
renewable energy objectives. This product offers the same amount of 
renewable energy as Default Service from Eversource as required by the 
RPS of New Hampshire. Keene Basic will be the lowest cost option in the 
Program. 
 
○ Keene 50% Local Green:  For customers that want more renewable 
electricity than is offered by Keene Local Green, this product offers up to 
50% local renewable energy above the RPS. The City reserves the right to 
adjust the amount of renewable energy to be included with this product and 
that amount will be the same for all customers choosing this option. This 
Page 96 of 210

City of Keene 
 
Community Power Plan 
 
 
 
 
August 5, 2026 
 
 
 
 
                    11 
product enables customers who chose this option to have a more 
meaningful impact on the reduction of greenhouse gas emissions through 
the support of local renewable energy sources. 
 
○ Keene 100% Local Green:  For customers that want more renewable 
electricity than is offered by Keene Local Green, this product offers up to 
100% local renewable energy above the RPS. City reserves the right to 
adjust the amount of renewable energy to be included with this product and 
that amount will be the same for all customers choosing this option. This 
product enables customers who chose this option to have a more 
meaningful impact on the reduction of greenhouse gas emissions through 
the support of local renewable energy sources. 
 
The Program reserves the right to adjust product names as needed.  
The Program notes that it cannot guarantee savings for any of its products compared to 
the utility Default Service rates, because utility Default Service rates may not be known 
for the entirety of any Program supply contract.  
 
Any charge for the additional renewable energy would be included in the rate submitted 
to the electric distribution utility or be purchased separately as Renewable Energy 
Certificates (“RECs”) from a third party. RECs are the accepted legal instrument used to 
track renewable energy generation and to substantiate claims of renewable energy use. 
For every one megawatt-hour (MWh) of renewable electricity that is generated and fed 
onto our electricity grid, one REC is created. In order to claim the use of a certain 
quantity of renewable energy, one must hold and retire an equivalent quantity of RECs. 
Retiring a REC ensures that there can be no double counting of renewable energy (i.e. no 
one else may claim to use the same REC once it has been retired). 
 
V.b. Green & Local Definitions 
 
The term “Green” means that the product contains additional renewable energy, 
substantiated through REC retirement, above that required by state law.  
 
“Local” means that the additional RECs come from renewable energy sources that are 
part of our ISO-New England electricity grid. This means the sources are located in New 
England or the energy is imported as allowed by ISO-New England from locations such 
as New York or eastern Canada. This stands in contrast to some electricity supplies that 
obtain RECs from national sources (e.g. Texas) in which the electricity is not part of our 
ISO-New England electricity grid.  
 
In its procurement, as described in Section VI.a, Keene seeks to support renewable 
energy generation located within Keene or as close to Keene in New Hampshire as 
possible. Keene also seeks to support the growth of renewable energy, thereby displacing 
Page 97 of 210

City of Keene 
 
Community Power Plan 
 
 
 
 
August 5, 2026 
 
 
 
 
                    12 
fossil fuels and reducing greenhouse gas (GHG) emissions. 
 
V.c. NH Class I Renewable Energy 
 
New Hampshire Class I renewable energy is known as “new renewable energy”. The 
State requires all electricity supplies to include a minimum quantity of Class I renewable 
energy, and that amount increases annually (currently plateauing after 2025). This 
increasing requirement, along with similar requirements in other New England states, has 
been a major driver of the growth of renewable energy in our region. If the Program 
voluntarily purchases additional Class I renewable energy at significant scale, Keene will 
augment this growth even further.  
 
Class I renewable energy can come from wind, solar, small hydroelectric, biomass, 
methane, as well as hydrogen and ocean thermal, tidal or wave energy. These categories 
align with the Keene Energy Plan’s support for “Green Power” as defined by the US 
Environmental Protection Agency (EPA). All Class I renewable energy must have started 
operation after January 1, 2006 and must be physically delivered to our regional 
electricity grid, which means it can come from New England, New York or eastern 
Canada.  
● Additional detail on NH Class I renewable energy, as well as the other 
classifications of renewable energy covered by the New Hampshire Renewable 
Portfolio Standard, may be found at https://www.energy.nh.gov/renewable-
energy/renewable-portfolio-standard  
● Additional detail on EPA’s Green Power definition can be found at 
https://www.epa.gov/green-power-markets/learn-about-green-power-market . 
 
As described above, the City intends to purchase a portion of the RECs from renewable 
energy generators and include these RECs in a renewable energy product. If RECs are 
obtained through the Competitive Supplier, any charge for these RECs would be included 
in the same rate submitted to the electric distribution utility. 
 
VI. Operation 
 
The implementation of the Community Power Program requires extensive interaction 
between the City, the Competitive Supplier, and the electric distribution utility. 
 
Following adoption of the Plan by the City Council, the key operational steps will be:   
 
a. Issue a Request for Proposals (RFP) for power supply, select a Competitive 
Supplier and provide notice 
b. Implement a public information program, including a Customer Notification 
Letters  
c. Enroll customers and provide service, including quarterly notifications and annual 
Page 98 of 210

City of Keene 
 
Community Power Plan 
 
 
 
 
August 5, 2026 
 
 
 
 
                    13 
reporting  
d. Plan for Program evolution 
 
These steps are described in the sections below. 
 
VI.a.  Issue an RFP for power supply, select a competitive supplier and 
provide notice 
 
The City, under direction of the City Manager or its designee, will solicit bids from 
leading competitive suppliers, including those currently supplying community power 
programs in New England and other states. In seeking bids from competitive suppliers, 
the City may solicit bids for its load individually or as part of a Buying Group with other 
municipal aggregators. The RFP will require that the supplier satisfy key threshold 
criteria, including:  
 
● Registration with the New Hampshire Public Utilities Commission (NHPUC) 
● Strong financial background  
● Experience serving the New England competitive market or community power 
programs (also known as municipal aggregations) in other states 
● Demonstrated ability, supported by references, to provide strong customer service. 
● Demonstrated ability to use Electronic Data Interchange (“EDI”) for enrollment of 
customers with the electric distribution utility or a plan to successfully complete 
testing required to use the electric distribution utility’s EDI prior to the mailing of 
the Customer Notification Letters 
 
In addition, suppliers will be required to agree to the substantive terms and conditions of 
the ESA, including, for example, the requirement to:  
 
● Provide all-requirements power supply at a fixed price  
● Allow customers to exit the Program at any time on their next regular meter read 
with no charge  
● Agree to specified customer service standards  
● Comply with all requirements of the NHPUC and the electric distribution utility  
 
The RFP will include data on Eligible Customer load and other characteristics provided 
to the City by the electric distribution utility pursuant to Puc 2204.02.  
 
The City will solicit price bids from suppliers that meet the threshold criteria and agree to 
the terms and conditions of the ESA. The City will request bids for a variety of term 
lengths (e.g. 12, 24, 36 or 48 months) and for power from different sources. The City 
Manager, or their designee(s), will determine the number of products, the appropriate 
level of renewable energy to be included with the default product and the optional 
products based upon their assessment of market conditions and what would be in the best 
Page 99 of 210

City of Keene 
 
Community Power Plan 
 
 
 
 
August 5, 2026 
 
 
 
 
                    14 
interest of retail electric customers at the time of the solicitation. As noted in Section 
V.a., all claims of renewable energy use will be substantiated by the supplier obtaining 
and retiring the appropriate quantity of RECs. The City will require bidders to identify 
the technology, vintage, and location of the renewable energy generators that are the 
sources of the RECs.  It will also require that the RECs be created and recorded in the 
New England Power Pool Generation Information System. The City may seek RECs 
from a variety of renewable energy sources; may elect to procure from those sources 
RECs, power or both; and will choose the best combination of environmental benefits 
and price. All additional RECs, above those required by the RPS, are initially expected to 
be New Hampshire Class I eligible RECs or RECs from sources located within the 
greater Monadnock region.  
 
The City may provide customers with renewable energy generation source information 
through a variety of vehicles including the Program web site, content disclosure labels 
and the customer notification letter. 
 
In consultation with its Community Power Consultant, the City Manager, or its designee, 
will evaluate the bid results including price, term and source. Whether the City conducts 
an individual solicitation or participates in a solicitation with a Buying Group, at the 
conclusion of the bidding process it will select a price, term and supplier appropriate for 
its retail electric customers. Participation in the Buying Group shall not require the City 
to select the same price, terms or supplier as other members of the Buying Group.  If a 
bid is satisfactory, the City Manager, or its designee, shall execute an Electric Service 
Agreement (“ESA”) with the selected supplier(s). The City reserves the right to select 
supplier(s) per customer class (as distinguished in Section III.c. to ensure equitable 
treatment).  If none of the bids is satisfactory, the City will reject all bids and repeat the 
solicitation for bids as often as needed until market conditions yield a price that is 
acceptable.  The City will only accept a bid that enables it to launch the Program with a 
price, terms and characteristics that meet the criteria set by their municipal officials. 
 
The City will provide written notice of its acceptance of a bid and the Program’s date of 
commencement of service to the NHPUC, the Office of Consumer Advocate, the 
Department of Energy as required by Puc 2204.04.  
 
The Program will utilize consolidated billing such that the participating customers 
receive a single bill from the electric distribution utility that includes the charges for the 
Program’s electricity supply and all other charges from the electric distribution utility. 
The Program will confirm this choice of billing service by notifying the electric 
distribution utility of prior to the enrollment of customers, including providing any 
applicable Product details required pursuant to Puc 2205.16.  
 
Page 100 of 210

City of Keene 
 
Community Power Plan 
 
 
 
 
August 5, 2026 
 
 
 
 
                    15 
VI.b.  Implement public information program including Customer 
Notification Letters  
 
An Education and Outreach Plan is required to fully inform and educate potential 
customers and participants in advance of automatic enrollment in the Community Power 
Program.  Customers, including customers with limited English language proficiency and 
disabilities, must be informed that they would be automatically enrolled in the Program 
and that they would have the right to opt-out of the Program without penalty. The 
purpose of the Education and Outreach Plan is to raise awareness and provide retail 
electric customers with information concerning their opportunities, options and rights for 
participation in the Program. To facilitate the Education and Outreach Plan, the City will 
utilize contact information for retail electric customers provided to the City by the 
electric distribution utility pursuant to Puc 2004.03. 
 
The Education and Outreach Plan (See Exhibit II) consists of five components: 
 
i. Initial Outreach and Education: This will be conducted after the selection of a 
Competitive Supplier and prior to arrival of the customer notification letter. It is 
intended to promote general awareness of the upcoming Program, minimize any 
questions generated by the arrival of the customer notification letter and maximize 
recipients’ ability to make an informed choice about their participation in the 
Program. This effort will include information about the goals of the Program, the 
basic terms and conditions including renewable energy components, and the opt-
out process. This effort will also include posting of the Program’s product 
information for residential and small commercial customers on the Department of 
Energy’s shopping comparison website. Such information will be posted on the 
website in advance of mailing the Customer Notification Letters. 
 
ii. Customer Notification Letters: In addition to the initial outreach and education 
initiatives, a notice (“Customer Notification Letter”) will be mailed to every retail 
electric customer. The Program will have two versions of this letter, one for 
Eligible Customers and one for other customers.  
 
The Customer Notification Letter for Eligible Customers will contain a description 
of the aggregation program; the implications to the City; the rights and 
responsibilities that the participants will have under the Program; all details, 
including all rates, on the products offered by the Program; explain that the 
customer will be automatically enrolled in the default product unless they choose 
otherwise and identify the deadline to make such a choice; have instructions for 
how to not participate (opt out) via web, phone or a pre-addressed envelope and 
opt-out reply card included with the letter; and instruction for how to enroll in an 
optional Program product. The opt-out period will last a minimum of 30 days from 
the date of mailing of the Customer Notification Letters. 
Page 101 of 210

City of Keene 
 
Community Power Plan 
 
 
 
 
August 5, 2026 
 
 
 
 
                    16 
 
The Customer Notification Letter for other customers will, at a minimum, contain a 
description of the aggregation program, the implications to the City, and 
instructions for how to enroll in any of the Program products if desired.  
 
Prior to the mailing of the Customer Notification Letters, the Program will confirm 
with the Competitive Supplier and the electric distribution utility that the 
Competitive Supplier is able to use EDI for enrollment of Default Service 
customers into the Program.   
 
iii. Opt-Out Period Education & Outreach: After the Customer Notification 
Letters have been sent, the City will continue its education and outreach to afford 
residents and businesses the opportunity to learn more and find answers to key 
questions relating to their decision to opt out or enroll in one of the optional 
products of the Program. This will include, at a minimum, a public information 
meeting within 15 days of the mailing of the customer notification letter.  
 
iv. Timeline and Preliminary Marketing Plan for Launch: This component 
identifies the steps the City intends to take in marketing the Program including 
identification of media and other community resources, examples of education and 
outreach documents, and an expected timeframe for the outreach effort. 
 
v. Ongoing Outreach & Education: This component describes the expected 
outreach and education activities following Program launch. Key elements include: 
 
● Program goals and performance, particularly as they relate to progress 
towards the City’s ambitious short- and long- term goals for renewable 
energy, particularly for 2030 and 2050.  
● On-going campaigns to recruit participation into its optional product(s) that 
contain more renewable energy than required by law (“Opt up campaigns”). 
Increasing participation in these products will serve the City’s goals to 
expand new renewable energy and increase overall renewable energy use; 
AND 
● Promotion and support of the NHSaves energy efficiency program, and 
future energy efficiency and weatherization programs 
The attached Education and Outreach Plan (Exhibit II) describes in detail the City’s 
anticipated outreach efforts, including a timeline. 
 
VI.c.  Enroll customers and provide service  
 
i. Enroll Customers: After the conclusion of the opt-out period (i.e. no sooner than 
Page 102 of 210

City of Keene 
 
Community Power Plan 
 
 
 
 
August 5, 2026 
 
 
 
 
                    17 
37 days from the date of the postmark of the Customer Notification Letters, which 
includes 3 days for mailing, 30 days for customer consideration, and an additional 3 
days for return of the replay card), the Competitive Supplier will enroll into the 
Program all retail electric customers on Default Service with the electric 
distribution utility who did not opt out and any other retail electric customers that 
have affirmatively requested in writing or through email to be enrolled into the 
Program. All enrollments and other transactions between the Competitive Supplier 
and the electric distribution utility will be conducted in compliance with the 
relevant provisions of New Hampshire Public Utilities Commission regulations, 
Terms and Conditions for Competitive Suppliers, and the protocols of the New 
Hampshire Electronic Business Transaction (EBT) standards. 
 
After enrollment of each customer, the Program may receive billing information for 
each enrolled customer from the electric distribution utility pursuant to Puc 
2205.13. 
 
ii. Provide Service: Once customers are enrolled, the Program will provide all-
requirements power supply service. The Program will also provide ongoing 
customer service, maintain the Program website, and process customer enrollments, 
ongoing opt outs, and customer selections of optional products.  The Program will 
provide Energy Source Disclosure labels to participants as required by RSA 
378:49.  
 
Prior to the expiration of the initial ESA, the City intends to solicit a new power 
supply agreement, as described in Section XIII. Method of Terminating and 
Entering Agreements with Other Entities. If the City elects not to enter into a 
new power supply agreement, participating customers would return to Default 
Service as described in Section XV. Extensions or Termination of Program.  
 
Retail electric customers that apply for new service with the electric distribution 
utility (e.g., new customers move into the City or move within the City), they will 
initially be enrolled in Default Service supply provided by the electric distribution 
utility. The Program will mail such customers a Customer Notification Letter for 
Eligible Customers per section IV.b.ii detailing the Plan and an opt-out card. At the 
end of the opt-out period they will be enrolled in the Program unless they elect to 
opt-out, per section IV.c.i. New customers also may proactively enroll by 
contacting the Program directly.  
 
The City will update the information on the Program’s products on the Department 
of Energy’s comparison shopping website whenever such information changes. 
 
iii. Annual Report: On an annual basis, the City Manager, or its designee(s) will 
report to the City Council on the status of the Community Power Program, 
Page 103 of 210

City of Keene 
 
Community Power Plan 
 
 
 
 
August 5, 2026 
 
 
 
 
                    18 
including the number of customers enrolled and opting-out, kilowatt-hour usage, 
customer savings, participation in renewable energy products, and such other 
information as the City may request. The information for this report will be 
prepared by the Community Power Consultant, and the Community Power 
Consultant will assist or lead in presenting to the City Council as desired by the 
City Manager.  
 
iv. Data Portal: The Community Power Consultant will make available to the City 
Manager and its designee(s) a secure, password-protected cloud-based data portal 
that provides the ability to run reports on key Program metrics and performance.  
 
VI.d.  Plan for Program evolution 
 
City seeks to continually improve the Program and progress towards its long-term goals. 
To this end, the Community Power Consultant and City will regularly assess new 
opportunities such as technologies, services, regulatory policy changes, and more for 
their applicability to the Program. Community Power Consultant will develop appropriate 
strategies to integrate these opportunities into the Program. Community Power 
Consultant will support the City to present new opportunities to the City Council for their 
consideration and approval, if amendments to the Plan are needed. 
 
VII. Funding   
 
All of the costs of the Program will be funded through the per kilowatt-hour rates 
established in the ESA. Only Program participants will pay for the costs of the Program, 
listed below.  
 
The primary cost will be the cost of the Competitive Supplier for the power supply, 
which will be funded through a per kilowatt-hour power supply rate component. These 
costs will be established through the competitive solicitation for a supplier.  
 
The administrative costs of the Program will be funded through a per kilowatt-hour 
administrative rate component that will be paid by the Competitive Supplier to the 
Community Power Consultant, as specified in the ESA. This rate component will cover 
the services of the Community Power Consultant, including developing the Community 
Power Plan, managing the supply procurement, developing and implementing the public 
education plan, providing customer support, interacting with the electric distribution 
utility, monitoring the supply contract, and providing ongoing reports. 
 
The City may choose to collect a per kilowatt-hour discretionary energy reserve fund rate 
component that will be paid by the Competitive Supplier to the City, as specified in the 
ESA. The City shall deposit and maintain such amounts in an enterprise fund to be used 
for the cost of providing energy-related benefits to Program participants and supporting 
Page 104 of 210

City of Keene 
 
Community Power Plan 
 
 
 
 
August 5, 2026 
 
 
 
 
                    19 
Program goals. Examples of such uses include (1) supporting development of new 
renewable energy projects, (2) supporting electrification of thermal and transportation 
uses, and (3) other energy-related programs and services. The City Council shall provide 
authorization for the use of funds from the discretionary energy reserve fund rate 
component. The City Manager will determine the appropriate amount of discretionary 
energy reserve fund rate component to include in each product in each ESA, within a 
range pre-approved by the City Council. 
 
VIII. Rate Setting and Other Costs to Participants 
 
The Program is offered on an opt-out basis, such that Eligible Customers will be 
automatically enrolled unless they proactively choose to opt out. 
 
As described above, the Program’s per kilowatt-hour rates will include the power supply,  
administrative, and discretionary energy reserve fund rate components, and applicable 
taxes pursuant to the ESA. Prices, terms, and conditions may differ among customer 
classes, which classes will be the same as the Default Service customer classes of the 
electric distribution utility.  The frequency of price changes will be determined through 
the competitive bid process.  The City expects to solicit bids for a number of different 
contract terms.  Prices may change as specified in the winning bid and customers will be 
notified of price changes through media releases and postings on the Community Power 
Program website. 
 
Regulatory events, such as new or altered requirements for the Renewable Portfolio 
Standard, or new taxes may result in a direct, material increase in costs during the term of 
the ESA. In such cases, the City and the Competitive Supplier will negotiate a potential 
change in the Program price. At least 30 days prior to the implementation of any such 
change, the City will notify customers of the change in price by issuing a media release 
and posting a notice in City Hall and on the Program website. The City shall also notify 
the NHPUC Consumer Services and External Affairs Division prior to implementation of 
any change in the Program price related to a regulatory event or new taxes. Such notice 
shall be provided prior to notifying customers and will include copies of all media 
releases, postings on the City and Program websites and any other communications the 
City intends to provide to customers regarding the price change. 
 
The Program affects only the electricity supply charges of the customers. Delivery 
charges will be unchanged and will continue to be charged by the electric distribution 
utility in accordance with tariffs approved by the NHPUC.  
 
Participants in the Program will receive one bill from the electric distribution utility that 
includes both the power supply charge of the Competitive Supplier and the delivery 
charge of the electric distribution utility.  Any applicable taxes will be billed as part of 
the Program’s power supply charge. 
Page 105 of 210

City of Keene 
 
Community Power Plan 
 
 
 
 
August 5, 2026 
 
 
 
 
                    20 
 
Participants in the Program will be able to opt-out of the Program and transfer to Default 
Service with the electric distribution utility or to another competitive supplier. Such 
requests submitted to the Program will be submitted by the Competitive Supplier to the 
electric distribution utility for processing on the customer’s next available regular meter 
read date. There shall be no penalty or exit fee for such transfer. Customers requesting 
transfer of supply service upon dates other than on the next available regular meter 
reading date may be charged an off-cycle meter reading and billing charge if such a 
service is available from the electric distribution utility. 
 
 
IX. Net Metering Compensation  
 
In accordance with RSA 362-A:9, II, the Program may determine the terms and 
conditions for net metering. In order to support the development of distributed energy 
resources within Keene, the Program will seek to offer net metering terms and conditions 
- for standard, alternative and group net metering - equal to or better than that provided 
on Default Service. To this end, the Program will evaluate the net metering terms and 
conditions offered by competitive suppliers as part of the procurement and bid selection 
process.  
 
To ensure net metering customers can make a fully informed decision on their 
participation in the Program, the Program will tailor all education and outreach materials 
to clearly communicate any and all differences between the net metering value and 
operation provided by the Program and Default Service. 
 
Additionally, the Program will evaluate how any proposed or implemented changes to the 
utility metering or billing infrastructure may create new opportunities to enhance the net 
metering benefits.  
 
 
X. Electric Assistance Program and other discounts 
 
The New Hampshire Electric Assistance Program (EAP) provides qualifying customers 
with a discount on their monthly electric bill. The New Hampshire Legislature authorized 
funding for this statewide program as part of electric utility deregulation. All electric 
utility ratepayers support the statewide EAP through the System Benefits Charge (SBC) 
portion of their electric bill.  
 
The EAP for income-eligible customers that may qualify for a discount off their monthly 
electric bill would continue for participants in the Program. The level of discount depends 
on household income, household size and electricity usage. 
 
Page 106 of 210

City of Keene 
 
Community Power Plan 
 
 
 
 
August 5, 2026 
 
 
 
 
                    21 
The EAP discount does apply to the Supplier Services portion of an electric bill when a 
customer chooses an independent supplier for their electricity needs. The participants in 
the Program who are enrolled in the EAP will receive their discounts by the same method 
they presently receive their discount. Participation in the Program is independent of 
enrollment in the EAP and does not impact the EAP discount.  
 
Other discount programs administered by Community Action Programs that address the 
needs of low-income residents would continue for participants in the Program. 
 
XI. Aggregating Municipalities & Buying Group  
 
Participating in a buying group may offer the potential for the City to expand its buying 
power for greater economies of scale and to support the City’s goal of acting as a regional 
leader, supporting other municipalities to access the benefits for Community Power. 
Keene will evaluate opportunities for such a buying group before issuing a bid for 
competitive supply. See Section VI.a. Issue an RFP for Power Supply and Select a 
Competitive Supplier for details on the implementation of a buying group. 
 
Additionally, the City reserves its right, in accordance with RSA 53-E:6, I, to join with 
other municipalities or counties for its Community Power Plan and implementing its 
Community Power Program. Any changes to the Community Power Plan must be 
reviewed and approved by the City Council. 
 
XII. Promoting Energy Efficiency 
 
In addition to supporting cost-competitive and cleaner electricity, the City seeks to 
leverage the Community Power Program to help reduce energy use. This will initially 
take the form of cross-promoting awareness of efficiency programs through the 
Program’s education and outreach. The Program will also evaluate opportunities for more 
direct support of energy efficiency.  
 
Promotional education will focus on existing energy efficiency and conservation 
programs, such as New Hampshire’s Weatherization Assistance Program for low-income 
households  and the New Hampshire Saves (NHSaves) program, which provides 
customers with information, incentives and support designed to save energy, reduce 
costs, and protect our environment statewide. NHSaves is funded by electric and natural 
gas ratepayers and delivered by Eversource, Liberty Utilities, New Hampshire Electric 
Cooperative and Unitil to make homes, businesses and towns more sustainable and more 
comfortable places to live and work, both now and in the future. Through NHSaves 
customers can receive a Home Energy Assessment. The assessment identifies energy-
saving opportunities in the home and provides the customer with an energy report. The 
report includes information on equipment rebates and no-cost products, as well as access 
to 0% financing and a limited time offers, such as up to 100% off approved insulation. 
Page 107 of 210

City of Keene 
 
Community Power Plan 
 
 
 
 
August 5, 2026 
 
 
 
 
                    22 
The assessment can also include delivery of energy-saving products recommended by the 
Energy Specialist, such as LED light bulbs, advanced power strips, and thermostats that 
can be installed right away to start saving money and energy. 
 
If and when additional energy efficiency and conservation programs or initiatives become 
available, the Program will evaluate how to incorporate them into its promotional 
outreach and education. 
 
XIII. Method of Entering and Terminating Agreements with Other 
Entities   
 
The process for entering, modifying, enforcing, and terminating all agreements associated 
with the Plan will comply with the municipal charter, federal and state law and rules and 
regulations, and the provisions of the relevant agreement. 
 
The City plans to use the same process described in Section IV.a. of this Plan to solicit 
bids and enter into any subsequent ESAs with the assistance of its then-current 
Community Power Consultant.  Customers will be notified of subsequent ESAs through 
press releases and public notices.  The transfer of customers from the existing supplier to 
the new supplier will be coordinated with the electric distribution utility using established 
Electronic Data Interchange (EDI) protocols. 
 
If the City determines that it requires the services of a Community Power Consultant after 
expiration of the existing agreement with GE/SP, it will evaluate opportunities to solicit a 
Community Power Consultant individually or as part of a group of municipalities 
aggregating the electric load of their respective customers. The City will solicit proposals 
for, and evaluate, potential Community Power Consultants using a competitive 
procurement process or alternative procedure which the City determines to be in the best 
interest of its customers and consistent with all applicable local, state and federal laws 
and regulations. 
 
XIV. Rights and Responsibilities of Program Participants 
 
All participants will have the right to opt out of the Program at any time without charge. 
They may exercise this right by any of the following:  1) calling the toll-free number of 
the Competitive Supplier; 2) contacting the electric distribution utility and asking to be 
returned to Default Service; or 3) enrolling with another competitive supplier. 
 
All participants will have available to them the customer protection provisions of the law 
and regulations of New Hampshire, including the right to question billing and service 
quality practices. Customers will be able to ask questions of and register complaints with 
the City, the Community Power Consultant, the Competitive Supplier, the electric 
distribution utility and the NHPUC. As appropriate, the City and the Community Power 
Page 108 of 210

City of Keene 
 
Community Power Plan 
 
 
 
 
August 5, 2026 
 
 
 
 
                    23 
Consultant will direct customer complaints to the Competitive Supplier, the electric 
distribution utility or the NHPUC.  
 
Participants will continue to be responsible for paying their bills and for providing access 
to metering and other equipment necessary to carry out utility operations.  Participants 
are responsible for requesting any exemption from the collection of any applicable taxes 
and must provide appropriate documentation of such exemption to the Competitive 
Supplier. 
 
XV. Extensions or Termination of Program   
 
Prior to the end of the term of the initial ESA, the City will solicit bids for a new supply 
agreement and plans to continue the Program with the same or new competitive supplier.   
 
Although the City is not contemplating a termination date, the Program could be 
terminated upon the termination or expiration of the ESA without any extension, renewal, 
or negotiation of a subsequent supply contract, or upon the decision of the City to 
dissolve the Program effective on the end date of the existing ESA. In the event of 
termination, customers would return to the Default Service of the electric distribution 
utility, unless they choose an alternative competitive supplier. The City will notify 
customers of a planned termination of the Program through media releases and postings 
on the Program website. 
 
The City will notify the electric distribution utility of the planned termination or 
extension of the Program in writing.  In particular, the City will provide the electric 
distribution utility notice: (1) 90 days prior to a planned termination of the Program; (2) 
90 days prior to the end of the anticipated term of the ESA; and (3) four business-days 
after the successful negotiation of a new ESA. The City will also provide written notice 
to the NHPUC 90 days prior to a planned termination, which notice shall include copies 
of all media releases, City Hall and website postings and other communications the City 
intends to provide customers regarding the termination of the Program and the return of 
participants to Default Service. The City will also provide written notice 90 days prior to 
a planned termination to the Office of the Consumer Advocate and the Department of 
Energy. 
 
In the event of unplanned termination of the Program because that the Program can no 
longer provide service to its customers, the Program shall provide immediate written 
notice to the NHPUC describing the market suspension or other event that caused the 
Program to no longer be able to provide service, the effective time of the inability to 
provide service, and the notice provided to customers of the timing and consequences of 
the cessation of the Program’s service. The Program shall file a copy of such notice at the 
same time to the office of the Office of the Consumer Advocate, the Department of 
Energy, and the electric distribution utility. 
Page 109 of 210

City of Keene 
 
Community Power Plan 
 
 
 
 
August 5, 2026 
 
 
 
 
                    24 
 
In the event of the termination of the Program, it is the responsibility and requirement of 
the Competitive Supplier to return the customers to Default Service of the electric 
distribution utility in accordance with the then applicable EDI rules and procedures. 
 
In the event of the termination of the Program, the balance of any funds accrued by the 
Program’s discretionary energy reserve fund, if any, would be available for distribution 
or application as directed by the City Council and in accordance with any applicable law 
and regulation. 
 
XVI. Planned Schedule  
 
The planned schedule below is presented for illustrative purposes. The final schedule will 
be established once the Program has received all necessary approvals and will ensure 
compliance with the all required notification timelines prior to Program commencement.   
 
Day 
Action or Event 
1 
Issue RFP for Competitive Supplier 
31 
ESA executed between City and Competitive Supplier. Program provides 
required notifications to NHPUC, Department of Energy, Office of 
Consumer Advocate, and electric distribution utility.  
32 
Competitive Supplier receives retail electric customer mailing data and data 
needed for Eligible Customer enrollment in Program 
48 
Competitive Supplier, at its expense, mails Customer Notification Letters to 
all retail electric customers, including identifying the return date by which 
the reply card envelopes for Eligible Customers must be mailed and 
postmarked 
51 
Retail electric customers receive Customer Notification Letter in the mail 
81 
Return date by which Eligible Customers deciding to opt-out must mail a 
reply card in pre-paid envelope to Competitive Supplier.  
85 
Competitive Supplier removes all Eligible Customers who opt out from the 
Eligible Customer list 
85 
Competitive Supplier sends “supplier enrolls customer” EDI for all Eligible 
Customers that did not opt-out and any other customers that affirmatively 
elected to opt-in to the Program. 
90 
 Service begins as of each customer's next meter read date 
Page 110 of 210

City of Keene 
 
Community Power Plan 
 
 
 
 
August 5, 2026 
 
 
 
 
                    25 
 
 
 
XVII. Conclusion 
 
Keene’s Community Power Program meets all of the requirements of the Community 
Power law, including providing universal access, a reliable power supply and treating all 
customer classes equitably. The City looks forward to launching the Program and 
pursuing the benefits of a competitive power supply, renewable energy, and electricity 
choice for its retail electric customers.
Page 111 of 210

City of Keene 
 
Community Power Plan - Exhibit I  
 
 
 
 
August 5, 2026    
 
 
 
 
               26 
 
 
Exhibit I - Historical Overview 
 
List of Revisions 
  
Adopted by City Council on May 6, 2021 
Amended July 31, 2022 
Approved by New Hampshire Public Utilities Commission October 3, 2022 
Adopted by City Council on November 3, 2022 
Amended February 10, 2025 
Adopted by City Council on March 20, 2025 
Amended August 5, 2026 
Formally adopted by City Council on TBD 
      
1. Creation of Community Power Committee  
On June 18, 2020 the Keene City Council approved the formation of an Ad-Hoc 
Community Power Committee (CPC). From City Council Minutes June 18, 2020: 
 
 
 
 
2. Creation of a Draft Plan with public hearings 
The Committee, supported by City Staff and the Community Power Consultant, 
Page 112 of 210

City of Keene 
 
Community Power Plan - Exhibit I  
 
 
 
 
August 5, 2026    
 
 
 
 
               27 
 
 
held two public information sessions on December 8, 2020 to promote awareness 
of the development of a Community Power Plan and to begin gathering input. 
Also on December 8, 2020, the Committee released a community survey open for 
approximately one month through January 7, 2021. The survey was available 
online and via paper in the Monadnock Shopper News. The online survey and the 
City’s website, KeeneEnergyPlan.com also hosted two educational videos about 
Community Power. KeeneEnergyPlan.com has hosted additional educational 
resources about Community Power, including an FAQ page, podcast and 
interviews with municipal leaders from active community power (also known as 
municipal aggregation) programs, such as Medford, Massachusetts.  
 
The survey received 126 responses, 97 online and 29 in paper via the Monadnock 
Shopper News. Key survey findings: 
● 86% of respondents currently receive supply from Eversource Default Service. 
Such customers would be eligible for automatic enrollment in the Program. 
● The survey had a well-distributed diversity of household income groups and 
age, as shown below: 
 
● Respondents identified a range of benefits they are interested in with 
Page 113 of 210

City of Keene 
 
Community Power Plan - Exhibit I  
 
 
 
 
August 5, 2026    
 
 
 
 
               28 
 
 
Community Power: 
 
● 92% of respondents were interested in including more renewable energy in 
their electricity. Of those interested, roughly half (45%) sought extra renewable 
energy if they could pay about the same they pay today. The other half (55%) 
was willing to pay a little or a lot more for extra renewable energy. 
 
● When analyzing preferences for renewable energy and cost by household 
income, a similar pattern remains for each income group.  
Those households under $50k were more likely than other income groups to 
want no extra renewable energy; however, 83% of the income group was still 
interested in more renewable energy. Of those interested, 50% sought extra 
renewable energy if they could pay about the same they pay today. The other 
33% was willing to pay a little or a lot more for extra renewable energy. 
 
Page 114 of 210

City of Keene 
 
Community Power Plan - Exhibit I  
 
 
 
 
August 5, 2026    
 
 
 
 
               29 
 
 
 
Do you want extra renewable energy, by household income? 
 
 
 
 
 
● Nearly three-quarters (73%) of participants had not performed an energy audit, 
and the percentages were nearly identical across household income groups. 
There appears to be widespread opportunity for energy efficiency 
improvements, with nearly three-quarters (71%) reporting that they keep their 
thermostat lower than they would like in winter and over half (51%) reporting 
their home is drafty or heating costs are too high. 
Energy efficiency 
 
 
 
Survey Conclusions:  
The majority of participants in Community Power programs typically remain in 
the default product rather than choosing any of the program optional products. 
Given the strong support for both renewable energy and cost parity demonstrated 
in the survey responses, it suggests that Keene would be well-served by a default 
Page 115 of 210

City of Keene 
 
Community Power Plan - Exhibit I  
 
 
 
 
August 5, 2026    
 
 
 
 
               30 
 
 
product designed with the goals of 1) achieving cost parity or savings compared to 
Eversource Default Service and 2) including some extra renewable energy.  
 
Additionally, the survey highlighted that, for those that can afford it, the program 
should offer options with substantially more renewable energy for a price 
premium. 
 
Although less than 8% of survey responses were not interested in extra renewable 
energy, it could be beneficial to have an optional product that would meet their 
needs by providing a lower-cost option with no extra renewable energy, 
particularly for those households in the lowest income bracket. 
 
There is substantial opportunity for energy audits and efficiency improvements, 
suggesting support for energy efficiency by the Program would be valuable. 
 
Respondents also cited an interest in local jobs, which the Program can support 
through demand for additional local renewable energy and by promotion greater 
participation in energy efficiency programs. Regional cooperation, particularly 
with neighboring municipalities, would amplify this impact as well. 
 
Draft Plan: Public Hearings & Comments 
The Committee held two additional public meetings on January 26, 2021(12:00 
pm and 6:30 pm) to present the survey findings, discuss how the results would be 
incorporated into the draft Community Power Plan, and provide an overview of 
other details to expect in the Community Power Plan. 
On February 5, 2021 the draft Community Power Plan was posted publicly to the 
program website, KeeneCommunityPower.com. During the Committee’s meeting 
on February 12, 2021, the Committee announced the availability of the draft 
Community Power Plan, invited comment and scheduled two public hearings for 
March 30, 2021 (12:00 pm and 6:30 pm). The Committee and the City promoted 
awareness of the draft Plan through diverse means including a formal hearing 
notice in the newspaper, press releases, postings on the City website and social 
media, and email outreach to the City’s Community Power email list. The public 
was encouraged to submit comments ahead of the public hearings using the online 
comment form on the program’s website, KeeneCommunityPower.com, and 
email, phone or written comment to the City’s Community Development 
department. 
The Committee received comments ahead of and during the public hearings. All 
public comment is available in the Committee’s meeting packet for April 8, 2021. 
3. Approval of Plan by Community Power Committee 
Page 116 of 210

City of Keene 
 
Community Power Plan - Exhibit I  
 
 
 
 
August 5, 2026    
 
 
 
 
               31 
 
 
The Committee discussed public comments and potential changes to the 
Community Power Plan during their Committee meeting on April 2, 2021. 
Additional public comment was provided during the meeting, and the Committee 
determined to reconvene on April 8, 2021 (see the Committee’s meeting packet 
for April 8, 2021 for additional comment received). 
 
In response to some of the public comments, the Committee revised the plan as 
follows: 
● Adjusted the language describing the likely sources of additional renewable 
energy in the City’s first supply contract to make it clear that local renewable 
energy generated within the “greater Monadnock region” could also be 
included, in addition to NH Class I renewable energy. 
● Revised the procurement language to clearly allow for the procurement of 
power and Renewable Energy Credits (RECs) from the same facility (also 
known as “bundled”) or purchase only one or the other from a facility (also 
known as “unbundled”). 
● Revised the procurement language to allow for the selection of multiple 
suppliers (for example, one for residential and small commercial and one for 
large industrial). 
● Modified language throughout the plan to clarify what is meant by the term 
“local” in different contexts (e.g. “renewables that are on the ISO-New 
England electricity grid,” or “within or as close as possible to Keene in New 
Hampshire”). 
 
The revised plan, including a red-line and clean version dated April 5, 2021, was 
included in the Committee’s meeting packet for the meeting on April 8, 2021. 
During the meeting, the Committee discussed the revisions. The Committee then 
unanimously voted to approve the plan and recommend it to the City Council for 
adoption.  
 
Subsequent to the meeting, on April 8, 2021, summary detail of the public 
hearings, public comment, Committee’s deliberation and vote was added to the 
Historical Overview. 
 
4. Adoption of Plan by City Council 
At the City Council meeting on April 15, 2021 the Community Power Committee’s 
report, which unanimously approved the City of Keene Community Power Plan and 
recommended adoption to the City Council, was read. The report was referred to the 
Finance, Organization & Personnel Committee (FOP). The FOP Committee met on 
April 22, 2021 to review the Plan. Representatives from City staff, the Community 
Power Committee and the Community Power Consultant presented to the FOP 
Committee, and following questions and discussion, the FOP Committee unanimously 
Page 117 of 210

City of Keene 
 
Community Power Plan - Exhibit I  
 
 
 
 
August 5, 2026    
 
 
 
 
               32 
 
 
voted to recommend adoption of the Plan.  At the City Council meeting on May 6, 
2021, the FOP Committee’s recommendation was reported to the City Council, and 
the Council voted unanimously to adopt the Plan.  
 
Subsequent to the meeting, on May 10, 2021, summary detail of the City Council 
review and adoption process was added to the Historical Overview. 
 
5. Revision of Plan 
The City amended the Plan in mid-March 2022 to better address questions of data 
security based on feedback provided by the Public Utilities Commission in orders on 
other Community Power plans. The City submitted its Plan to the Commission in 
April 2022 (DE 22-022), and it received an order in June 2022 which encouraged the 
City to re-submit the Plan closer to or after the completion of the rulemaking process 
for Community Power.  
 
On July 27, 2022, the Commission voted to approve Community Power rules. The 
City further amended the Plan on July 31, 2022  to appropriately reference those rules.  
 
6. Submission of Revised Plan to Public Utilities Commission 
The City submitted the revised Plan to the Public Utilities Commission (PUC) on 
August 3, 2022 under the existing docket number (DE 22-022) and the PUC approved 
the revised Plan on October 3, 2022. 
 
7. Adoption of Revised Plan by City Council 
The City Council adopted the revised Plan at their meeting on November 3, 2022. 
Subsequent to the meeting, summary detail of the vote (#7) and the submission to the 
PUC (#6) were added to this Exhibit I.  
 
8. Adoption of Revised Plan by City Council 
The City amended the plan in February 2025 to enable it to collect additional revenue 
in its rates to support energy-related projects that would benefit Program participants. 
The City Council adopted the revised Plan at their meeting on March 20, 2025. 
 
9.  Adoption of Revised Plan by City Council 
The City amended the Plan in August 2026 to enable different default products for 
customers on the New Hampshire Electric Assistance Program (EAP). The City 
Council adopted the revised Plan at their meeting on TBD.
Page 118 of 210

City of Keene                                                                                   Community Power Plan - Exhibit II 
 
 
 
 
August 5, 2026    
 
 
 
 
               33 
 
 
Exhibit II - Education & Outreach Plan 
 
1.   Initial Outreach and Education 
 
The initial outreach and education will provide a description of the Program for retail 
electric customers and will be conducted via traditional print and TV channels, social 
media, a dedicated website, public presentations and personal communications to 
inform retail electric customers about the Program and will include a toll-free number. 
This effort will provide specific information about the Program and increase public 
awareness of the goals of the Program and the upcoming opt-out notification process. 
 
If any Program materials were to reference cost savings for any part of the Program, a 
notice would be included which states that the City cannot guarantee that the Program 
will provide customers with prices lower than the distribution utility’s Default Service 
rate over the full term of any supply contract entered into by the City. 
 
1.1   Media Outreach 
 
Prior to the launch of the Program, the City will initiate media outreach that may 
include the use of local cable television shows, newspapers and social media to 
provide greater public education and to describe the Program, the opt-out process, the 
website, and the toll-free telephone number. Outreach may also include public service 
announcements (PSAs), scheduling interviews of Program spokespersons with local 
media outlets, and securing a positive media presence. 
 
A news release may be distributed to help achieve the aforementioned goals. Follow-
up news releases may be used to update the media on the status of the progress of the 
Program.  
 
1.2   Notices and Public Postings 
 
Brochures/flyers will be distributed in City offices describing the Program, the opt-out 
process and the toll-free telephone number in order to further reinforce the Program's 
details. Brochures/flyers may be placed in key gathering areas or buildings (e.g. 
library, Senior Center, etc.) which will create the necessary repetition of messages 
required to motivate customer action and build awareness and understanding. 
 
1.3   Customer Service Center 
 
The Program will maintain a toll-free telephone number to address retail electric 
customers’ questions regarding the Program, deregulation, the opt-out process, price 
information and other issues such customers may raise. 
Page 119 of 210

City of Keene                                                                                   Community Power Plan - Exhibit II 
 
 
 
 
August 5, 2026    
 
 
 
 
               34 
 
 
 
1.4   Website 
 
All information regarding the Program will be posted on the Program website, which 
is linked to the website of the City: https://keenecommunitypower.com/. The Program 
website will have links to the website of the electric distribution utility, the New 
Hampshire Public Utilities Commission (NHPUC), Department of Energy, and the 
Competitive Supplier. 
 
1.5   Public Presentations 
 
The Program will provide presentations to municipal officials and to interested 
community groups.  
 
1.6   Outreach to Persons with Limited English Proficiency or Disabilities 
 
The Program plans to make printed materials available in English. To accommodate 
limited English-speaking residents, the City will provide a translation option on its 
Program website (which contains all details on the Program including a description of 
the Program and its products, the implications to the City, and the rights and 
responsibilities that the participants will have under the Program) that will translate 
any written materials on the website into over 100 different languages. The website 
also will be designed with the goal of being compliant with the Americans with 
Disabilities Act (“ADA”) and will include formats that allow the content to be read 
out loud by computer assistive technology.  Outreach efforts will be communicated in 
print and audio formats to provide access to both the hearing and visually impaired. 
 
2.   Customer Notification Letter 
 
The Customer Notification Letters will be sent via standard mail to the billing address 
of each retail electric customer per section IV.b.II of the Plan.  The Program will have 
two versions of this letter, one for Eligible Customers and one for other customers. 
The Competitive Supplier shall bear all expenses regarding the Customer Notification 
Letters. 
 
2.1 Customer Notification Letter for Eligible Customers 
Per section III.b of the Plan, all retail electric customers receiving Default Service 
supply from the electric distribution utility will be eligible for automatic enrollment in 
the Program (“Eligible Customers”). The notification envelope will be designed to 
appear as an official City communication and it will be clearly marked as containing 
time sensitive information related to the Program. The notification will contain a letter 
describing the Program.  
Page 120 of 210

City of Keene                                                                                   Community Power Plan - Exhibit II 
 
 
 
 
August 5, 2026    
 
 
 
 
               35 
 
 
 
The letter will inform Eligible Customers: 
 
a)  about the Program, implications to the City and provide information regarding 
participation and participants’ responsibilities and rights; 
b)  that they have the right to opt-out of the Program without penalty; 
c)  of all charges, prominently stated, with a comparison of price and primary 
terms of the Competitive Supplier and the current Default Service offering; 
d)  that any savings under the Program compared to Default Service cannot be 
guaranteed because the Default Service rate is subject to changes 
e)  about the opt-out process; and 
f)  in languages other than English for appropriate customer groups (i.e. toll-free 
telephone number). 
 
The letter will also contain an opt-out reply card with a simple check off and signature 
line for Eligible Customers who do not wish to participate. The envelope will be pre-
stamped for return of the opt-out reply card in order to protect customer privacy.  
 
Eligible Customers will have 33 days from the date of the mailing to mail back the 
opt-out card in a pre-addressed postage-paid envelope and the customer notification 
shall identify the specific date by which the envelopes containing the opt-out card 
must be postmarked.  Automatic enrollment of customers will not start until three 
days after the date specified for the postmark of the return envelopes to allow for 
receipt of the opt-out cards prior to the start of automatic enrollments. New Eligible 
Customers will be enrolled in the Program in accordance with applicable Local 
Distributor Company rules. Upon initiation of service, these new Eligible Customers 
will receive the same customer information as all other Eligible Customers. 
 
2.2. Customer Notification Letter for Other Customers 
The Customer Notification Letter for other customers will, at a minimum, contain a 
description of the aggregation program, the implications to the City, and instructions 
for how to enroll in any of the Program products if desired.  
 
 
3. Opt-Out Period Education & Outreach 
 
After the Customer Notification Letters have been sent, City will continue its 
education and outreach to afford residents and businesses the opportunity to learn 
more and find answers to key questions relating to their decision to opt out or enroll in 
one of the optional products of the Program. This process will include, at a minimum, 
a public information meeting within 15 days of the mailing of the customer 
notification letter. It will also include a similar range of outreach activities as 
Page 121 of 210

City of Keene                                                                                   Community Power Plan - Exhibit II 
 
 
 
 
August 5, 2026    
 
 
 
 
               36 
 
 
enumerated in section 1.1 to 1.6. 
 
4. Timeline and Preliminary Marketing Plan for Launch 
 
The timeline and preliminary marketing plan identifies the steps the City may take to 
inform the community about the Program, as described in Sections 1 through 3 of 
Exhibit II. The schedule is designed to work towards the estimated date when the 
Customer Notification Letter is scheduled to arrive in customer mailboxes. The dates 
may be adjusted to ensure compliance with the minimum written notification 
timelines for the date of commencement of service to the NHPUC, the Office of 
Consumer Advocate, the Department of Energy Puc 2205.16.   
 
The costs and implementation will be handled by the Community Power Consultant, 
under the direction of the City. 
 
From estimated date Customer Notification Letter arrives in customer mailboxes 
Action 
Days before  
Days after  
A. Update Program & Shopping Comparison 
Websites  
15 
Ongoing 
B. Work with local media resources 
15 
30 
C. Active social media outreach 
15 
30 
D. Initial person presentations 
15 
30 
E. Distribute marketing materials 
15 
30 
F. Customer help line 
15 
Ongoing 
G. Mail postcard to all Eligible Customers 
5 
- 
H. Customer Notification Letters arrives 
0 
0 
 
A. Program & Shopping Comparison Website Update: 
Timeframe: 15 days before the estimated date that the customer notification letter 
arrives in customer mailboxes, then maintained on an ongoing basis.  
 
The Program’s website is https://keenecommunitypower.com/. After executing an 
ESA, the Program will update this website with a description of the Program and its 
Page 122 of 210

City of Keene                                                                                   Community Power Plan - Exhibit II 
 
 
 
 
August 5, 2026    
 
 
 
 
               37 
 
 
products, the implications to the City, and the rights and responsibilities that the 
participants will have under the Program. 
 
The shopping comparison website is maintained by the Department of Energy to 
enable consumers to shop for electricity supply products. The Program will post its 
product information for residential and small commercial customers on the shopping 
comparison website. Such information will be posted on the website in advance of 
mailing the Customer Notification Letters.  
 
B. Work with local media resources: 
Timeframe: 15 days before to 30 days after the estimated date that the customer 
notification letter arrives. 
 
Area Newspapers: 
 
The City will work with area print and online newspapers to disseminate accurate and 
timely information about the Program. As part of this targeted outreach to these 
papers, the City may seek a meeting with the editorial board to establish a good 
foundation for continued dialogue over the course of the contract. Other newspaper 
outlets may include other local publications. 
 
● These papers include: Keene Sentinel, Monadnock Shopper News, and the 
New Hampshire Union Leader  
 
Local Public Access Television: 
 
The City intends to work with Cheshire TV channels for public (1301) and 
government (1302) access. City can record interviews about the Program and PSAs 
for upcoming meetings.  
 
Other Television and Radio Stations 
 
Develop press releases to send to other TV stations and radio stations.  
● TV stations include WMUR (ABC, MANCHESTER, NH) Channel 9; WUTF 
(INDEPENDENT, WORCESTER, MA) Channel 27; WVTA (PBS, 
WINDSOR, VT) Channel 41; WWJE (INDEPENDENT, DERRY, NH) 
Channel 50; WEKW (PBS, KEENE, NH) Channel 52; WNEU (NBC, 
MERRIMACK, NH) Channel 60; 
● Radio stations include WVBA (88.9 FM) Brattleboro, VT; WEVO (89.1 FM) 
Concord, NH; WEVN (90.7 FM) Keene, NH; WEEY (93.5 FM) Swanzey, 
NH; WSNI (97.7 FM) Keene, NH; WINQ (103.1 FM) Keene, NH; WKNE 
Page 123 of 210

City of Keene                                                                                   Community Power Plan - Exhibit II 
 
 
 
 
August 5, 2026    
 
 
 
 
               38 
 
 
(103.7 FM) Keene, NH; WYRY (105.5 FM) Keene, NH; WCNL (1010 AM) 
Newport, NH; WKBK (1290 AM) Keene, NH; WTSA (1450 AM) Brattleboro, 
VT 
 
Municipal Staff Interviews 
Develop Q&A Scripts and prepare municipal staff or volunteers for interviews. 
 
C. Active Social Media Outreach 
Timeframe: 15 days before to 30 days after the estimated date that the customer 
notification letter arrives.  
 
Boost all traditional media coverage on social media platforms, with the goal of 
driving traffic to the dedicated website of the City.  
  
In concert with the communication leads of the City, develop a campaign of planned 
tweets and Facebook posts, timed to coincide with important milestones in order to 
keep ratepayers informed, particularly those that may not interact with traditional 
media on a regular basis. Draft content and graphics to accompany the posts, to be 
made by City staff. 
 
● These accounts may include: City of Keene (Instagram, Facebook); City 
Manager (Twitter); Keene Community Development (Instagram, Facebook & 
Twitter) and Keene Public Library (Instagram, Facebook & Twitter). 
  
Monitor various channels such as Facebook and Instagram for relevant conversations 
and questions about the Program. Draft responses to comments and questions and 
utilize social media as a critical tool in engaging with members of the community. 
● These accounts may include: “Downtown Keene” Facebook page 
(@downtownkeene); the “Keene, NH” Facebook group (5.5k members); and 
“Keene NH Community Forum” Facebook group (1.5k members) 
 
Identify key social media influencers in the City, including lawmakers, advocates and 
reporters. Develop a spreadsheet of the social media handles/accounts and reach out 
to them to keep them informed about the Program. 
 
D. In Person Presentations 
Timeframe: 15 days before to 30 days after the estimated date that the customer 
notification letter arrives. This will include, as required in RSA 53:E-7, a public 
information meeting within 15 days of the mailing of the customer notification letter. 
Page 124 of 210

City of Keene                                                                                   Community Power Plan - Exhibit II 
 
 
 
 
August 5, 2026    
 
 
 
 
               39 
 
 
 
Local Groups 
 
Connect with local groups and associations to see if representatives of the City can 
participate in an upcoming meeting or offer to host a dedicated event. Seek their 
assistance in identifying how to best connect with customers with limited-English 
capabilities or disabilities that may prevent them from accessing Program 
information. 
 
● Example groups include: Neighborhood associations, Social service agencies, 
Business Focus Group, Rotary, Kiwanis, Lions, Chamber, Clean Energy team, 
Keene Young Professionals, Downtown Group, Board of Realtors, Keene 
Senior Center, Keene Off-campus Housing (landlords and tenants), Keene 
State College English as a Second Language (ESL) classes, CALL Program 
(Cheshire Academy for Lifelong Learning). 
 
Reaching the business community will be important. Presenting to the Chamber of 
Commerce can start this dialogue and lead to additional outreach to and connection 
with businesses. 
 
Council Meetings 
 
Present or provide materials for the Council meetings and any constituent meeting 
they may have. 
 
E. Distribute marketing materials 
Timeframe: 15 days before to 30 days after the estimated date that the customer 
Notification Letter arrives.  
 
Many groups may have a natural interest in promoting awareness about the Program 
and can be provided with electronic and hard-copy materials with reference 
information for the Program.  
 
Distribute to key locations such as Municipal Offices and Public Library. 
 
F. Customer Help Line 
Timeframe: 15 days before the estimated date that the customer notification letter 
arrives and ongoing thereafter.  
 
Establish customer helplines with the Competitive Supplier and Community Power 
Consultant to answer customer inquiries. 
 
Page 125 of 210

City of Keene                                                                                   Community Power Plan - Exhibit II 
 
 
 
 
August 5, 2026    
 
 
 
 
               40 
 
 
G. Mail Postcard to all Eligible Customers 
Timeframe: 5 days before the estimated date that the customer notification letter 
arrives. 
 
Post Card 
 
Send out to Eligible Customers prior to Customer Notification Letter. Establishes that 
there is a community-sponsored Program and increases the likelihood that recipient 
engages with the more detailed Customer Notification Letter. 
 
H. Customer Notification Letters arrive 
Sent to all retail electric customers. See section 2 above for details.  
 
 
5.   Ongoing Outreach and Education 
 
The City intends to continue outreach and education for customers after enrollment in 
the Program. The costs and implementation will be handled by the Community Power 
Consultant, under the direction of the City. These efforts will include: 
 
● Program impact: Key metrics relating to cost performance, renewable energy 
purchases and Program enrollment. Particularly as the Program 
accomplishments relate to progress towards the City’s ambitious short- and 
long- term goals for renewable energy and greenhouse gas emission reduction. 
This will also include the Energy Source Disclosure labels for the electricity 
supply;  
 
● Opt up campaigns: On-going campaigns to recruit participation into its 
optional product(s) that contain more renewable energy than required by law 
(“Opt up campaigns”). Increasing participation in these products will serve the 
City’s goals to expand new renewable energy and reduce greenhouse gas 
emissions;  
   
● Customer awareness: Rights and procedures for Program participants; contact 
information for customer inquiries, responses to frequently asked questions, 
and details regarding the Program’s electric supply and renewable attributes.   
 
● Public input: As the Program considers changes to further its progress toward 
a 100% renewable future and other goals, City will manage outreach to solicit 
input and feedback from the community.  
 
● Program changes and evolution: Any changes in offerings and prices, which 
will be posted on the Program website that is linked to the website of the City. 
Page 126 of 210

City of Keene                                                                                   Community Power Plan - Exhibit II 
 
 
 
 
August 5, 2026    
 
 
 
 
               41 
 
 
 
The Program will utilize similar mediums for on-going education and outreach as for 
the initial launch education and outreach, including but not limited to: social media, 
traditional media, in-person meetings and presentations, outreach to local groups, 
video, and mail.  
 
Translation of all materials will be provided as necessary to reach communities with 
limited English proficiency. 
Page 127 of 210

City of Keene                                                                                  Community Power Plan - Exhibit III 
 
 
 
 
August 5, 2026    
 
 
 
 
               42 
 
 
 
Exhibit III - Data Protection Plan 
 
      
I. 
Introduction 
 
The City of Keene (the “Municipality”) is developing a Community Power program 
(the “Program”), pursuant to RSA 53-E. A municipality that implements such a 
program is known as an aggregator (“Aggregator”). RSA 363:38 and PUC 2004.19 
require that service providers, including Aggregators, protect individual and 
confidential customer data (“Individual Customer Data”). Individual Customer Data, 
as defined in RSA 363:38 and expanded in PUC 2004.19, means information that is 
collected as part of providing electric services to a customer that can identify, singly or 
in combination, that specific customer, and includes the customer name, address, and 
account number and the quantity, characteristics, or time of consumption by the 
customer, and also includes specific customer payment, financial, banking, and credit 
information. Further, Aggregators must only use Individual Customer Data for the 
Program’s primary purpose, which may include 1) providing or billing for electric 
service, 2) meeting electric system, electric grid, or other operational needs, and 3) 
researching, developing and implementing new rate structures or demand response, 
customer assistance, energy management or energy efficiency programs. The 
Municipality’s Community Power Consultant has developed this Data Protection Plan 
to  ensure that Individual Customer Data obtained as part of operation of the Program 
will be protected from disclosure and/or inappropriate use. 
 
II.  
Elements of the Plan 
 
1. Access to Customer Data 
 
As part of the Program, the Community Power Consultant , local designees of the 
Municipality, and competitive electricity suppliers (“Suppliers”) selected to provide 
electricity for the Program (collectively, “Data Administrators”) will receive access to 
certain information on file with a customer’s local distribution company (“LDC” or 
“electric distribution utility”), including, among other things, the customer’s name, 
mailing address, and energy usage history (“Customer Data”). In particular, depending 
on the status of implementation of the Program, LDC’s may provide four types of 
Customer Data to Data Administrators: a) aggregated customer data, b) eligible 
customer data, c) retail electric customer contact information, and d) enrolled customer 
information. Each type of Customer Data is described more fully below.  
 
a. Aggregated Customer Data – contains certain information for all electric 
customers within a municipality, aggregated by rate class or other grouping. This 
Page 128 of 210

City of Keene                                                                                  Community Power Plan - Exhibit III 
 
 
 
 
August 5, 2026    
 
 
 
 
               43 
 
 
may include data such as the number of customers by rate class, counts of 
customers participating in net energy metering by rate class, counts of customers 
participating in electric assistance program by rate class, the aggregated energy 
(kWh) for electricity consumption by month for the past 12 months or more by 
rate class, and revenue, receipts and past-due accounts receivable.  
 
b.  Eligible Customer Data – contains certain information for each electricity 
customer currently receiving utility-provided default service within a 
municipality. This may include data such as capacity tags for current, prior and 
next power years, energy (kWh) for electricity consumption for the past 12 
months or more, meter reading cycle, whether customer net meters and under 
which terms, and group net metering data including whether customer is a group 
net metering host or member of a net metering group, whether a group net 
metering customer-generator operates as a low-moderate income community 
solar project, the size of any such net metered generation and the year and month 
it was placed into service.   
 
c. Retail Electric Customer Contact Information – comprises certain customer 
contact information for the provision of Program communications, such as 
Customer Notification Letters to retail electric  customers. This may include such 
data as the customer of record’s name, mailing address, account number, meter 
number, rate class, and email address.  
 
d.  Enrolled Customer Data – contains certain information for all individual 
customers who elected not to opt-out of the Program during the opt-out period. 
This may include such data as Name of customer and customer contact, Mailing 
address, Service address, Account number and related meter numbers, Name key, 
Contact information such as phone numbers, email address, Billing account 
number, Preferred billing and communication method, Billing cycle, Meter read 
date or cycle, Form or type of meter reading, Capacity tag information for past 
two years, current power year and forecasted next power year, Most recent 24 
months of usage data, Current and historic status of net metering, distributed 
generation, Preferred billing and communication method, payment plans and 
electric assistance program participation, and Rate class. 
 
 
2. Data Security 
 
All Customer Data that is not anonymized (i.e. presented or aggregated in such a way 
that removes information that can be used to identify the individual customer that it 
pertains to, such that it does not constitute individual customer data as defined by RSA 
363:37, I or PUC 2002.09) shall be considered Individual Customer Data. 
Page 129 of 210

City of Keene                                                                                  Community Power Plan - Exhibit III 
 
 
 
 
August 5, 2026    
 
 
 
 
               44 
 
 
 
Data Administrators will utilize industry standard physical, technical, and 
administrative controls and procedures to safeguard Individual Customer Data 
collected as part of the Program and to prevent unauthorized or accidental access, 
destruction, loss, alteration, or disclosure of, to protect against anticipated threats or 
hazards to the security, confidentiality, or integrity of, and to permit only the 
appropriate use of, such customer information. 
 
To protect the confidentiality, integrity, and availability of Individual Customer Data, 
Data Administrators will utilize a variety of industry standard physical and logical 
access controls, firewalls, password protections, intrusion detection/prevention 
systems, network and database monitoring, and backup systems. These systems will 
be designed to cover all networks, servers, computers, notebooks, laptops, PDAs, 
mobile phones, or other devices that contain Individual Customer Data, or through 
which Individual Customer Data is made available.  
 
Data Administrators will limit access to Individual Customer Data to those persons 
and entities having a specific business purpose for maintaining and processing such 
information. Those granted access to Individual Customer Data will be trained on their 
responsibilities to protect the confidentiality, integrity, and availability of such 
information. 
 
Data Administrators will work cooperatively with the LDC(s), as necessary, to 
implement this Data Protection Plan, and will at a minimum, implement the following 
actions: 
 
a. Conduct a risk assessment to identify and assess reasonably foreseeable 
internal and external risks to the security, confidentiality, and integrity of 
electronic, paper, and other records containing Individual Customer Data and 
evaluate and improve, where necessary, the effectiveness of their safeguards 
for limiting those internal and external risks; 
b. Timely notify the LDC(s) of any important modifications of this Data 
Protection Plan within a reasonable amount of time; 
c. Review and, as appropriate, revise this Data Protection Plan: (i) at least 
annually or whenever there is a material change in their business practices that 
may reasonably affect the security or integrity of Customer Data; (ii) in 
accordance with prevailing industry practices and applicable law; and (iii) as 
reasonably requested by the LDC(s). If the Data Administrators modify this 
Data Protection Plan following such a review, the Data Administrators will 
promptly notify the LDC(s) of such modifications and will provide the 
modifications to the LDC(s) in writing upon a LDC’s request. The Data 
Administrators will at no time alter or modify this Data Protection Plan in such 
Page 130 of 210

City of Keene                                                                                  Community Power Plan - Exhibit III 
 
 
 
 
August 5, 2026    
 
 
 
 
               45 
 
 
a way that will weaken or compromise the confidentiality, security, or integrity 
of Individual Customer Data; 
d. Maintain and enforce this Data Protection Plan in all locations where 
Individual Customer Data is processed by the Data Administrators; 
e. Conduct security testing using a third party to provide monitoring penetration 
and intrusion testing with respect to Data Administrators systems and promptly 
provide a copy of the results to the LDC(s), provided that the third party may 
redact IP addresses and other client names and information; 
f. Provide annual security awareness training to all individuals having access to 
Individual Customer Data and maintain a record of such training; and 
g. Implement a standard process for identifying, assessing, and mitigating 
security risks. 
 
3. Confidentiality 
 
Data Administrators will not sell Individual Customer Data to others unless such sale 
is specifically authorized by the customer, or is required by law or court order. Data 
Administrators will not share, disclose, or provide Individual Customer Data to others, 
including their affiliates, unless such disclosure, or provision is required to operate the 
Program (i.e., the Program’s “primary purpose”, per RSA 363:38), is specifically 
authorized by the customer, or is required by law or court order. If Data Administrators 
request customer authorization to disclose Individual Customer Data, Data 
Administrators will first describe to the customer the information they intend to release 
and provide details concerning the recipient of such information. 
 
Data Administrators will hold all Customer Data in strict confidence and except as 
otherwise needed for provision of the Program, required by law, or permitted as below, 
(a) not disclose Individual Customer Data to any other person or entity (including but 
not limited to Suppliers, subcontractors, and affiliates or members of the Community 
Power Consultant ; (b) not process Individual Customer Data outside of the United 
States; (c) not process Individual Customer Data other than in connection with the 
Program; (d) not process Individual Customer Data for any marketing purposes other 
than in connection with the Program; (e) limit reproduction of Individual Customer 
Data to the extent required for the Program; (f) store Individual Customer Data in a 
secure fashion at a secure location in the United States that is not accessible to any 
person or entity not authorized to receive the Individual Customer Data; and (g) 
otherwise use at least the same degree of care to avoid publication or dissemination of 
the Individual Customer Data as Data Administrators employ (or would employ) with 
respect to their own confidential information that they do not (or would not) desire to 
have published or disseminated, but in no event less than reasonable care.  
 
4. Disclosure of Individual Customer Data 
Page 131 of 210

City of Keene                                                                                  Community Power Plan - Exhibit III 
 
 
 
 
August 5, 2026    
 
 
 
 
               46 
 
 
Notwithstanding the provisions of Section 3 above, the Data Administrators may 
disclose Individual Customer Data to their representatives who have a legitimate need 
to know or use such Individual Customer Data for the sole and limited purposes of 
administering and/or conducting the Program. Such representatives will first be advised 
of the sensitive and confidential nature of such Individual Customer Data and agree to 
comply with the provisions of this Data Protection Plan. Pursuant to PUC 200.19, Data 
Administrators may also provide Individual Customer Data to third parties for the 
purposes of 1) billing for electric service, 2) meeting electric system, electric grid, or 
other operational needs, and 3) implementing demand response, customer assistance, 
energy management or energy efficiency programs. Any such third parties will be 
required by contract to comply with the provisions of this Data Protection Plan. 
In the event that Data Administrators or any of their representatives receive notice that 
they have, will, or may become compelled, pursuant to applicable law or regulation or 
legal process, to disclose any Individual Customer Data (whether by receipt of oral 
questions, interrogatories, requests for information or documents in legal proceedings, 
subpoenas, civil investigative demands, other similar processes or otherwise), Data 
Administrators will, except to the extent prohibited by law, immediately notify the 
LDC(s), orally and in writing, of the pending or threatened compulsion. To the extent 
lawfully allowable, the LDC(s) will have the right to consult with the Data 
Administrators and the parties will cooperate, in advance of any disclosure, to 
undertake any lawfully permissible steps to reduce and/or minimize the extent of 
Individual Customer Data that must be disclosed. The LDC(s) will also have the right 
to seek an appropriate protective order or other remedy reducing and/or minimizing the 
extent of Individual Customer Data that must be disclosed.  
Data Administrators and their representatives will disclose only such Individual  
Customer Data which they are advised by legal counsel that they are legally required 
to disclose in order to comply with such applicable law or regulation or legal process 
(as such may be affected by any protective order or other remedy obtained by LDC) 
and Data Administrators and their representatives will use all reasonable efforts to 
ensure that all Individual Customer Data that is so disclosed will be accorded 
confidential treatment. 
 
5. Return/Destruction of Individual Customer Data 
 
Upon the expiration of the Program, or as otherwise required by law or Commission 
order, the Data Administrators will destroy all copies of any Individual Customer Data 
(including any and all extracts, compilations, studies or other documents based upon, 
derived from or containing Individual Customer Data) within their or their 
representatives’ possession (including destroying Individual Customer Data from all 
systems, records, archives and backups), and all subsequent use and processing of the 
Page 132 of 210

City of Keene                                                                                  Community Power Plan - Exhibit III 
 
 
 
 
August 5, 2026    
 
 
 
 
               47 
 
 
Individual Customer Data by the Data Administrators and their representatives will 
cease.  
 
Notwithstanding the foregoing, the Data Administrators and their representatives will 
not erase Individual Customer Data contained in an archived computer system backup 
maintained in accordance with their respective security or disaster recovery procedures. 
The Data Administrators will not provide access to or recovery of Individual Customer 
Data from such computer backup system and will keep all such Individual Customer 
Data confidential in accordance with this Data Protection Plan. 
 
6. Data Security Incidents 
 
The Data Administrators are responsible for any and all security incidents involving 
Individual Customer Data that is processed as part of the Program. The Data 
Administrators will notify the LDC(s) in writing immediately (and in any event within 
twenty-four (24) hours) whenever the Data Administrators reasonably believe that there 
has been a data security incident involving Individual Customer Data. After providing 
such notice, the Data Administrators will investigate the incident, and immediately take 
all necessary steps to eliminate or contain any exposure of Individual Customer Data. 
The Data Administrators will provide the LDC(s) with reasonable assistance and 
cooperation in the furtherance of any correction, remediation, or investigation of any 
such data security incidents and/or the mitigation of any damage, including any 
notification required by law or that LDC(s) may determine appropriate to send to 
individuals impacted or potentially impacted by such data security incident(s), and/or 
the provision of any credit reporting service required by law or that LDC(s) deems 
appropriate to provide to such individuals.  
 
Unless required by law, the Data Administrators will not notify any individual or any 
third party other than law enforcement of any potential data security incidents involving 
Individual Customer Data without first consulting with, and obtaining the permission 
of, the LDC(s). Within 30 days of identifying or being informed of a data security 
incident, the Data Administrators will develop and execute a plan, with the cooperation 
of the LDC(s), which reduces the likelihood of a recurrence of such data security 
incident(s). 
 
7. Additional Protections 
 
The Data Administrators will comply with all applicable privacy and security laws to 
which it is subject, including this Data Protection Plan. 
 
The Data Administrators will safely secure and/or encrypt all Individual Customer 
Data during storage and transmission. 
Page 133 of 210

City of Keene                                                                                  Community Power Plan - Exhibit III 
 
 
 
 
August 5, 2026    
 
 
 
 
               48 
 
 
 
The Data Administrators will have in place appropriate and reasonable processes and 
systems, including this Data Protection Plan, to protect the security of Individual 
Customer Data and to prevent a data security incident, including, without limitation, a 
breach resulting from or arising out of the Data Administrators’ internal use, 
processing, or other transmission of Individual Customer Data, whether between or 
among their representatives, subsidiaries and affiliates, or any other person or entity 
acting on behalf of the Data Administrators. 
 
The Data Administrators will work cooperatively with the LDC(s) to implement this 
Data Protection Plan, including: establishing policies and procedures to provide 
reasonable and prompt assistance to LDC(s) in responding to any and all requests, 
complaints, or other communications received from any individual who is or may be 
the subject of a data security incident involving Customer Data to the extent such 
request, complaint or other communication relates to the Data Administrators’ 
processing of such individual’s Individual Customer Data; and establishing policies 
and procedures to provide all reasonable and prompt assistance to LDC(s) in 
responding to any and all requests, complaints, or other communications received from 
any individual, government, government agency, regulatory authority, or other entity 
that is or may have an interest in the Individual Customer Data, data theft or other 
unauthorized release of Individual Customer Data, disclosure of Individual Customer 
Data, or misuse of Individual Customer Data to the extent such request, complaint or 
other communication relates to Data Administrators’ processing of such individual’s 
Individual Customer Data. 
 
8. Use of Individual Customer Data 
 
The Data Administrators will only use Individual Customer Data for the primary 
purposes, as defined in RSA 363:37, which may include 1) providing or billing for 
electric service, 2) meeting electric system, electric grid, or other operational needs, and 
3) researching, developing and implementing new rate structures or demand response, 
customer assistance, energy management or energy efficiency programs. 
 
II. 
Conclusion 
 
The Data Protection Plan meets all of the requirements of RSA 363:38, RSA 363:37 
and PUC 2004.19.  
      
 
 
Page 134 of 210

 
 
 
 
 
 
 
CITY OF KEENE 
COMMUNITY POWER PLAN 
 
Adopted May 6, 2021February 10, 2025  
Amendment Adopted March 20, 2026 
Formally adopted by City Council on May 6, 2021 
Amended July 31, 2022 
Approved by New Hampshire Public Utilities Commission October 3, 2022 
Formally adopted by City Council on November 3, 2022 
Amended February 10, 2025 
Formally adopted by City Council on March 20, 2025 
Amended August 5, 2026 
Formally adopted by City Council on TBD
Page 135 of 210

City of Keene 
 
Community Power Plan 
 
 
 
 
TABLE OF CONTENTS 
 
I. Community Power Goals and Vision 
2II. Process to Develop and Approve Plan
 
4III. Customer Participation
 
5III.a. Applicable classes of customers
 
5III.b. Universal access
 
5III.c. Equitable treatment
 
5III.d. Reliability
 
7IV. Organizational Structure
 
7IV.a Roles
 
7IV.b. Data Security
 
8V. Electricity Supply Product Options
 
9V.a. Default and Optional Electricity Supply Products
 
9V.b. Green & Local Definitions
 
11V.c. NH Class I Renewable Energy
 
11VI. Operation
 
12VI.a.  Issue an RFP for power supply, select a competitive supplier and provide notice
 
12VI.b.  Implement public information program including Customer Notification Letters
 
14VI.c.  Enroll customers and provide service
 
16VI.d.  Plan for Program evolution
 
17VII. Funding
 
17VIII. Rate Setting and Other Costs to Participants
 
18IX. Net Metering Compensation
 
19X. Electric Assistance Program and other discounts
 
20XI. Aggregating Municipalities & Buying Group
 
20XII. Promoting Energy Efficiency
 
20XIII. Method of Entering and Terminating Agreements with Other Entities
 
21XIV. Rights and Responsibilities of Program Participants
 
22XV. Extensions or Termination of Program
 
22XVI. Planned Schedule
 
23XVII. Conclusion
 
24Exhibit I - Historical Overview
 
25Exhibit II - Education & Outreach Plan
 
32Exhibit III - Data Protection Plan
 
41 
 
I. Community Power Goals and Vision 
 
The City of Keene will develop and implement its Community Power Program 
(“Program”) as described in this Community Power Plan (“Plan”).  
 
Community Power creates new electricity supply choices for Keene residents and 
businesses with the potential for cost and environmental benefits beyond that of the 
Default Service supply from the electric distribution utility, Eversource. Instead of simply 
utilizing Eversource’s electricity supply, Keene will bundle together the electricity needs 
of its residents and small businesses and put out a bid for an electricity supplier to 
provide the necessary electricity at competitive prices. With Community Power, the City 
is able to make strategic decisions about when to solicit bids, lock in fixed pricing for 
multiple years, and increase the amount of renewable energy above the existing statewide 
minimum. Eversource will continue to manage billing and maintain wires and poles. 
Page 136 of 210

City of Keene 
 
Community Power Plan 
 
 
 
 
August 5, 2026 
 
 
 
 
                    3 
 
Community Power is part of the City’s comprehensive climate and energy planning 
process. One of the primary goals of Keene’s process, embodied in the City Council’s 
2018 Resolution R 2018-36, is to achieve 100% renewable electricity use: 
“It is the goal of the City of Keene that all electricity consumed in the City will 
come from renewable energy sources by the year 2030 and that 100% of all 
thermal energy and energy used for transportation come from renewable energy 
sources by the year 2050. This goal will apply to the entire Keene community, not 
just municipal government operations. 
Keene’s climate and energy planning process also seeks to support equity, energy 
efficiency, job creation, and climate resilience and preparedness. 
To establish specific goals and a vision for the Program, the City held information 
sessions and surveyed community members to ask about their priorities and preferences. 
While individual opinions differed, there was strong support from the majority of survey 
respondents from all income classes and age groups for five community priorities related 
to electricity supply:  
● Choice for electricity options 
● Control of electricity costs 
● Competitive rates and lower bills 
● Increased local renewable energy 
● Local jobs 
 
 
Particularly strong among 
respondents was support for 
renewable energy. As shown at 
right, over 90% of all respondents 
indicated a desire for extra 
renewables, and almost half 
indicated a willingness to pay more 
for extra renewables.  
The desire for extra renewable 
energy generally held across age and 
household income brackets, with the 
strongest support overall in the 
middle income bracket, as shown below. 
Page 137 of 210

City of Keene 
 
Community Power Plan 
 
 
 
 
August 5, 2026 
 
 
 
 
                    4 
 
Do you want extra renewable energy, by household income? 
 
 
 
 
 
Detailed survey results can be found in Exhibit I.  
The Keene community goals translate into the following goals for Keene’s Community 
Power Program: 
1. Establish a standard (or default) electricity supply product that delivers economic 
value via competitive rates, uses more renewable energy, and supports the growth of 
local renewable energy as defined in Section V.b.  
2. Increase the contribution of renewables toward 100% renewable electricity for the 
entire Program by 2030, using optional products, tools and incentives that include: 
● Provide optional electricity supply products with alternative renewable electricity 
amounts (for example, 100%). Options afford individual participants the 
opportunity to meet higher renewable goals immediately and increase the overall 
renewable energy impact of the Program; 
● Catalyze the development of distributed energy resources within Keene, such as 
rooftop solar, by providing enhanced net metering and other incentives;  
● Explore opportunities to support the development of and utilize new renewable 
energy supply at utility scale within our region;  
● Support electrification, particularly of thermal and transportation sectors; 
● Support energy efficiency initiatives to reduce total Program electricity demand 
and costs for participants; and 
● Explore, and implement when possible, other tools and incentives successfully 
established elsewhere in New Hampshire, in other states or around the world (for 
example, time-of-use rate structures).  
3. Engage the community to bring new ideas and resources into the Program, through 
Page 138 of 210

City of Keene 
 
Community Power Plan 
 
 
 
 
August 5, 2026 
 
 
 
 
                    5 
every means possible, over the life of the program. Also engage the community to 
assess how benefits of the Program can be allocated equitably. 
4. Work with regulators, utilities and suppliers to craft solutions and remove barriers to 
harnessing all cost-effective solutions, especially recognizing that increased 
electrification will be part of the solution toward 100% transportation and thermal 
renewable energy by 2050. 
5. Expand the Program’s impact by empowering other communities with similar goals. 
This includes sharing information and materials to help launch other programs as well 
as evaluating regional buying groups as to whether they provide greater cost savings 
to all participants through economies of scale.  
The vision for Keene Community Power is to launch a timely Community Power 
Program that provides community members with attractive choices and substantially 
enhanced renewable energy options at competitive prices, and opens a new promising 
community path to 100% renewable electricity in 2030.  
Community Power is emerging as a leading strategy to reach multiple community goals 
efficiently and equitably. The City of Keene looks forward to refining this vision for 
meeting our 100% renewable energy goals and all of Keene’s goals that are impacted by 
energy choices. 
 
II. Process to Develop and Approve Plan 
 
Before implementation, the Plan must be reviewed and approved by the Community 
Power Committee (“Committee”) and adopted by the Keene City Council.  The 
Committee will ensure that the Program satisfies all of the statutory requirements, 
including that the Plan provides universal access, reliability and equitable treatment for 
all classes of customers. This Plan was developed to demonstrate that the Program of the 
City satisfies all the requirements necessary for approval by the Committee and adoption 
by the City Council. 
 
This plan was developed through the following process, consistent with New Hampshire 
Revised Statutes Annotated (RSA) 53-E: 
 
1. Creation of Community Power Committee 
2. Creation of a Draft Plan with public hearings, 
3. Approval of Plan by Community Power Committee, 
4. Adoption of Plan by City Council, and 
5. Submission of Final Plan to Public Utilities Commission. 
 
Please see Exhibit I for detail on these steps. 
Page 139 of 210

City of Keene 
 
Community Power Plan 
 
 
 
 
August 5, 2026 
 
 
 
 
                    6 
 
III. Customer Participation  
 
III.a. Applicable classes of customers 
 
The Community Power Program will be available for the residential, commercial and 
industrial classes of electricity customers as defined by City’s electric distribution 
company, Eversource (“Applicable Classes”). See Eversource for current classes: 
https://www.eversource.com/content/nh/residential/my-account/billing-payments/about-your-
bill/rates-tariffs 
 
III.b. Universal access 
 
The Plan provides for universal access for all customers by guaranteeing that all customer 
classes will be included in the Program under equitable terms. 
 
All retail electric customers will have access to the Program. All retail electric customers 
receiving Default Service supply from the electric distribution utility will be eligible for 
automatic enrollment in the Program (“Eligible Customers”), and they will be 
automatically enrolled in the Program unless they choose to opt out.   
 
All customers will have the right to opt-out of the Program at any time with no charge. 
 
As required by the statute, there shall be equitable treatment of Applicable Classes within 
the Program. 
 
 
III.c. Equitable treatment 
 
The community power statute requires equitable treatment of all classes of customers 
subject to any differences arising from varying opportunities, tariffs and arrangements 
between different electric distribution utilities in their respective franchise territories. 
This does not mean that all classes of customers must be treated “equally,” but rather that 
similarly situated classes of customers be treated “equitably.” 
 
Among applicable classes of customers, the Plan makes fourthree distinctions.  
 
First, the Program will distinguish among customer classes by soliciting separate pricing 
for each of the same customer classes the electric distribution utility uses for the 
distribution service.  
 
Second, the Program will distinguish between customers that participate in the New 
Hampshire Electric Assistance Program (EAP) and other customers by assigning a 
Page 140 of 210

City of Keene 
 
Community Power Plan 
 
 
 
 
August 5, 2026 
 
 
 
 
                    7 
default product to EAP customers and a default product to all other customers.  
 
ThirdSecond, the Program will distinguish between customers receiving the default 
product and customers that affirmatively choose an optional product. Customers selecting 
an optional product will be charged the price associated with that product. 
 
FourthThird, the Program will distinguish between customers that join the Program 
through an automatic enrollment process (i.e. customers who do not choose to opt-out) 
and customers that affirmatively elect to join the Program. Such distinction will 
determine whether the customer receives the price specified for their rate class and 
product set in the Electricity Supply Agreement (“Program pricing”) or a price based on 
market prices at the time the customer joins the Program. 
 
● Customers that join through an automatic enrollment process include a) the initial 
Eligible Customers at the start of the Program and b) new Eligible Customers that 
move into the City after the Program start-date. All initial Eligible Customers will 
receive the Program pricing for their rate class. Among new Eligible Customers, 
the Program will distinguish between new residential and small commercial 
customers, who will receive the Program pricing, and all other commercial and 
industrial customers, who may receive pricing based on market prices at the time 
the customer joins the Program.  
 
● Finally, customers that affirmatively elect to join include two types of customers: 
a) customers that were being served by a Competitive Supplier at the start of the 
Program but then later join the Program; and b) customers re-joining the Program 
after having previously opted out. Those customers that were being served by a 
Competitive Supplier at Program initiation but who later join the Program will be 
treated the same as new Eligible Customers – residential and small commercial 
customers will receive the Program pricing and all other commercial and industrial 
customers may be offered a price based on the then-current market rates. All 
customers that join the Program after having previously opted out may be offered 
a price based on then-current market rates rather than the Program price. This 
distinction is designed to limit any incentive for frequent switching back and forth 
between the Program and Default Service of the electric distribution utility. 
 
III.d. Reliability 
 
Reliability has both physical and financial components. The Program will address both 
through the Electricity Supply Agreement (“ESA”) with the Competitive Electric Power 
Supplier (“Competitive Supplier”), which shall be the Load Serving Entity. From a 
physical perspective, the ESA commits the Competitive Supplier to provide all-
requirements power supply and to use proper standards of management and operations. 
All-requirements power supply includes all of the electrical energy, capacity, reserves, 
Page 141 of 210

City of Keene 
 
Community Power Plan 
 
 
 
 
August 5, 2026 
 
 
 
 
                    8 
ancillary services, transmission services, transmission and distribution losses, congestion 
management, and other such services or products necessary to provide firm power supply 
to Program participants and meet the state’s Renewable Portfolio Standard and any 
additional renewable energy requirements of the default or optional products. The electric 
distribution utility will continue to remain responsible for delivery service, including the 
physical delivery of power to the customer, maintenance of the delivery system, and 
restoration of power in the event of an outage. From a financial perspective, the ESA 
requires the Competitive Supplier to pay actual damages for any failure to provide supply 
at the contracted rate (i.e., to pay the difference between the contract rate and the utility 
supply rate). The ESA requires the Competitive Supplier to maintain insurance and the 
Request for Proposals for a Competitive Supplier will require that an investment-grade 
entity either execute or guarantee the ESA. Accordingly, the Program satisfies the 
reliability requirement of the statute. 
 
 
IV. Organizational Structure  
 
IV.a Roles 
Community Power Committee (CPC): The Finance, Organization and Personnel 
Committee, a standing committee of the City Council, voted to request that the Mayor 
constitute an ad-hoc Community Power Committee, as the designee of the Mayor and as 
established under RSA 53-E:6, to develop and approve a Community Power Plan for 
submission to and adoption by the City Council, as the legislative body of the City. The 
Committee will develop a draft plan, hold public hearings on the plan to solicit public 
input, revise the draft plan based on that input, and ultimately submit an approved Plan to 
the City Council. See Exhibit I for detail on the public input process. 
 
City Council: In accordance with RSA 53-E:7, the City Council, as the legislative body of 
the municipality, will be the body to adopt the Community Power Plan after it has been 
approved by the Community Power Committee. The City Council will review and 
approve any proposed amendments to the Plan. 
 
City Manager: The City Manager is designated by the City Council to provide direct 
management and oversight of the Plan on behalf of the City. The City Manager, or their 
designee(s), shall regularly meet with the Community Power Consultant for the purpose 
of providing oversight of the Plan and shall make recommendations to the City Council 
on Plan amendments. The City Manager shall authorize the issuance of bids for power 
supply and shall negotiate and execute a Electric Service Agreements (“ESA”) consistent 
with the products and goals described in this Plan.  
 
Community Power Consultant:  The Community Power Consultant will manage certain 
Program activities under the direction of the City Manager. Their responsibilities will 
include managing the supply procurement, developing and implementing the public 
Page 142 of 210

City of Keene 
 
Community Power Plan 
 
 
 
 
August 5, 2026 
 
 
 
 
                    9 
education plan, interacting with the electric distribution utility and monitoring the supply 
contract, as detailed in the professional services agreement.. Through a competitive 
procurement process the City has selected the partnership of Good Energy, L.P. and 
Standard Power (“GE/SP”) to provide these services. 
 
Competitive Supplier:  The Competitive Supplier will provide power for the Program, 
provide customer support including staffing a toll-free number for customer questions, 
and fulfill other responsibilities as detailed in the ESA.  The Competitive Supplier shall 
be required to enter into an individual ESA with the City under terms deemed reasonable 
and appropriate for the retail electric customers by the City Manager. 
 
Buying Group:  The City may elect to join with other municipal aggregators in combining 
its load for purposes of soliciting bids from Competitive Suppliers.  The purpose of the 
Buying Group is to allow municipal aggregators to capture the benefits of collective 
purchasing power while retaining full municipal autonomy.  The City shall be 
represented by the City Manager, or their designee, on the executive committee of the 
Buying Group. The City, through the City Manager or their designee, shall select a 
Competitive Supplier based on the needs of the City and shall not be required to select 
the same terms or Competitive Supplier as other members of the Buying Group. 
 
Retail electric customers: Retail electric customers shall include all electric customers 
taking distribution service of electricity located within the geographic boundaries of the 
City of Keene. 
 
IV.b. Data Security 
Pursuant to RSA 363:38 and PUC 2004.19, the Program, as an aggregator, is required to 
protect individual customer data that it may receive as part of Program implementation. 
See Exhibit III for the data protection plan to be used by the Program. 
 
 
 
 
 
 
 
 
V. Electricity Supply Product Options  
 
V.a. Default and Optional Electricity Supply Products 
The Program offered the following electricity supply products in its initial ESA and may 
adjust these products in subsequent ESAs, taking into account the goals of the Program, 
market conditions and implementation experience. Current product offerings will always 
be posted at the Program website, KeeneCommunityPower.com. Any retail electric 
Page 143 of 210

City of Keene 
 
Community Power Plan 
 
 
 
 
August 5, 2026 
 
 
 
 
                    10 
customer that joins through an automatic enrollment process, shall be enrolled into the 
Program’s default product, unless they affirmatively choose to enroll in any of the 
optional products. 
 
Default Product  
(Automatic enrollment) 
Optional Products 
Product 
Name 
Keene 
 Local Green 
Keene  
Basic 
Keene  
50% Local Green 
Keene  
100% Local Green
Product 
Goals 
Increase renewable 
energy use while 
maintaining 
competitive rates  
Most competitive 
rate (no increase 
in renewable 
energy use) 
Significant 
increase in 
renewable energy 
use (e.g. 50%) 
Largest increase 
in renewable 
energy use (e.g. 
100%) 
 
 
● Default Product 
○ Keene Local Green: The Program intends to offer Keene Local Green as 
its default product. The Keene Local Green product has a goal of 
maintaining rough cost parity with Eversource’s Default Service supply 
while including extra renewable electricity above the Renewable Portfolio 
Standard (“RPS”) required in New Hampshire. The exact amount of extra 
renewable electricity will be determined after the receipt of bids from 
competitive suppliers. It is expected to include 5-10% extra renewable 
energy in the initial ESA. It is the City's goal to increase this amount in 
subsequent ESAs, while maintaining cost parity with Eversource’s Default 
Service.  This product is intended to include as much local renewable 
energy as possible, as defined in Section V.b. Including additional 
renewable energy in this product enables customers to have a meaningful 
impact on the reduction of greenhouse gas emissions through the support of 
local renewable energy sources. 
 
● Optional Products  
 
○ Keene Basic: Some customers may feel that the amount of new, renewable 
energy required by the RPS in New Hampshire is sufficient to fulfill their 
renewable energy objectives. This product offers the same amount of 
renewable energy as Default Service from Eversource as required by the 
RPS of New Hampshire. Keene Basic will be the lowest cost option in the 
Program. 
 
○ Keene 50% Local Green:  For customers that want more renewable 
electricity than is offered by Keene Local Green, this product offers up to 
Page 144 of 210

City of Keene 
 
Community Power Plan 
 
 
 
 
August 5, 2026 
 
 
 
 
                    11 
50% local renewable energy above the RPS. The City reserves the right to 
adjust the amount of renewable energy to be included with this product and 
that amount will be the same for all customers choosing this option. This 
product enables customers who chose this option to have a more 
meaningful impact on the reduction of greenhouse gas emissions through 
the support of local renewable energy sources. 
 
○ Keene 100% Local Green:  For customers that want more renewable 
electricity than is offered by Keene Local Green, this product offers up to 
100% local renewable energy above the RPS. City reserves the right to 
adjust the amount of renewable energy to be included with this product and 
that amount will be the same for all customers choosing this option. This 
product enables customers who chose this option to have a more 
meaningful impact on the reduction of greenhouse gas emissions through 
the support of local renewable energy sources. 
 
The Program reserves the right to adjust product names as needed.  
The Program notes that it cannot guarantee savings for any of its products compared to 
the utility Default Service rates, because utility Default Service rates may not be known 
for the entirety of any Program supply contract.  
 
Any charge for the additional renewable energy would be included in the rate submitted 
to the electric distribution utility or be purchased separately as Renewable Energy 
Certificates (“RECs”) from a third party. RECs are the accepted legal instrument used to 
track renewable energy generation and to substantiate claims of renewable energy use. 
For every one megawatt-hour (MWh) of renewable electricity that is generated and fed 
onto our electricity grid, one REC is created. In order to claim the use of a certain 
quantity of renewable energy, one must hold and retire an equivalent quantity of RECs. 
Retiring a REC ensures that there can be no double counting of renewable energy (i.e. no 
one else may claim to use the same REC once it has been retired). 
 
V.b. Green & Local Definitions 
 
The term “Green” means that the product contains additional renewable energy, 
substantiated through REC retirement, above that required by state law.  
 
“Local” means that the additional RECs come from renewable energy sources that are 
part of our ISO-New England electricity grid. This means the sources are located in New 
England or the energy is imported as allowed by ISO-New England from locations such 
as New York or eastern Canada. This stands in contrast to some electricity supplies that 
obtain RECs from national sources (e.g. Texas) in which the electricity is not part of our 
ISO-New England electricity grid.  
 
Page 145 of 210

City of Keene 
 
Community Power Plan 
 
 
 
 
August 5, 2026 
 
 
 
 
                    12 
In its procurement, as described in Section VI.a, Keene seeks to support renewable 
energy generation located within Keene or as close to Keene in New Hampshire as 
possible. Keene also seeks to support the growth of renewable energy, thereby displacing 
fossil fuels and reducing greenhouse gas (GHG) emissions. 
 
V.c. NH Class I Renewable Energy 
 
New Hampshire Class I renewable energy is known as “new renewable energy”. The 
State requires all electricity supplies to include a minimum quantity of Class I renewable 
energy, and that amount increases annually (currently plateauing after 2025). This 
increasing requirement, along with similar requirements in other New England states, has 
been a major driver of the growth of renewable energy in our region. If the Program 
voluntarily purchases additional Class I renewable energy at significant scale, Keene will 
augment this growth even further.  
 
Class I renewable energy can come from wind, solar, small hydroelectric, biomass, 
methane, as well as hydrogen and ocean thermal, tidal or wave energy. These categories 
align with the Keene Energy Plan’s support for “Green Power” as defined by the US 
Environmental Protection Agency (EPA). All Class I renewable energy must have started 
operation after January 1, 2006 and must be physically delivered to our regional 
electricity grid, which means it can come from New England, New York or eastern 
Canada.  
● Additional detail on NH Class I renewable energy, as well as the other 
classifications of renewable energy covered by the New Hampshire Renewable 
Portfolio Standard, may be found at https://www.energy.nh.gov/renewable-
energy/renewable-portfolio-standard  
● Additional detail on EPA’s Green Power definition can be found at 
https://www.epa.gov/green-power-markets/learn-about-green-power-market . 
 
As described above, the City intends to purchase a portion of the RECs from renewable 
energy generators and include these RECs in a renewable energy product. If RECs are 
obtained through the Competitive Supplier, any charge for these RECs would be included 
in the same rate submitted to the electric distribution utility. 
 
VI. Operation 
 
The implementation of the Community Power Program requires extensive interaction 
between the City, the Competitive Supplier, and the electric distribution utility. 
 
Following adoption of the Plan by the City Council, the key operational steps will be:   
 
a. Issue a Request for Proposals (RFP) for power supply, select a Competitive 
Supplier and provide notice 
Page 146 of 210

City of Keene 
 
Community Power Plan 
 
 
 
 
August 5, 2026 
 
 
 
 
                    13 
b. Implement a public information program, including a Customer Notification 
Letters  
c. Enroll customers and provide service, including quarterly notifications and annual 
reporting  
d. Plan for Program evolution 
 
These steps are described in the sections below. 
 
VI.a.  Issue an RFP for power supply, select a competitive supplier and 
provide notice 
 
The City, under direction of the City Manager or its designee, will solicit bids from 
leading competitive suppliers, including those currently supplying community power 
programs in New England and other states. In seeking bids from competitive suppliers, 
the City may solicit bids for its load individually or as part of a Buying Group with other 
municipal aggregators. The RFP will require that the supplier satisfy key threshold 
criteria, including:  
 
● Registration with the New Hampshire Public Utilities Commission (NHPUC) 
● Strong financial background  
● Experience serving the New England competitive market or community power 
programs (also known as municipal aggregations) in other states 
● Demonstrated ability, supported by references, to provide strong customer service. 
● Demonstrated ability to use Electronic Data Interchange (“EDI”) for enrollment of 
customers with the electric distribution utility or a plan to successfully complete 
testing required to use the electric distribution utility’s EDI prior to the mailing of 
the Customer Notification Letters 
 
In addition, suppliers will be required to agree to the substantive terms and conditions of 
the ESA, including, for example, the requirement to:  
 
● Provide all-requirements power supply at a fixed price  
● Allow customers to exit the Program at any time on their next regular meter read 
with no charge  
● Agree to specified customer service standards  
● Comply with all requirements of the NHPUC and the electric distribution utility  
 
The RFP will include data on Eligible Customer load and other characteristics provided 
to the City by the electric distribution utility pursuant to Puc 2204.02.  
 
The City will solicit price bids from suppliers that meet the threshold criteria and agree to 
the terms and conditions of the ESA. The City will request bids for a variety of term 
lengths (e.g. 12, 24, 36 or 48 months) and for power from different sources. The City 
Page 147 of 210

City of Keene 
 
Community Power Plan 
 
 
 
 
August 5, 2026 
 
 
 
 
                    14 
Manager, or their designee(s), will determine the number of products, the appropriate 
level of renewable energy to be included with the default product and the optional 
products based upon their assessment of market conditions and what would be in the best 
interest of retail electric customers at the time of the solicitation. As noted in Section 
V.a., all claims of renewable energy use will be substantiated by the supplier obtaining 
and retiring the appropriate quantity of RECs. The City will require bidders to identify 
the technology, vintage, and location of the renewable energy generators that are the 
sources of the RECs.  It will also require that the RECs be created and recorded in the 
New England Power Pool Generation Information System. The City may seek RECs 
from a variety of renewable energy sources; may elect to procure from those sources 
RECs, power or both; and will choose the best combination of environmental benefits 
and price. All additional RECs, above those required by the RPS, are initially expected to 
be New Hampshire Class I eligible RECs or RECs from sources located within the 
greater Monadnock region.  
 
The City may provide customers with renewable energy generation source information 
through a variety of vehicles including the Program web site, content disclosure labels 
and the customer notification letter. 
 
In consultation with its Community Power Consultant, the City Manager, or its designee, 
will evaluate the bid results including price, term and source. Whether the City conducts 
an individual solicitation or participates in a solicitation with a Buying Group, at the 
conclusion of the bidding process it will select a price, term and supplier appropriate for 
its retail electric customers. Participation in the Buying Group shall not require the City 
to select the same price, terms or supplier as other members of the Buying Group.  If a 
bid is satisfactory, the City Manager, or its designee, shall execute an Electric Service 
Agreement (“ESA”) with the selected supplier(s). The City reserves the right to select 
supplier(s) per customer class (as distinguished in Section III.c. to ensure equitable 
treatment).  If none of the bids is satisfactory, the City will reject all bids and repeat the 
solicitation for bids as often as needed until market conditions yield a price that is 
acceptable.  The City will only accept a bid that enables it to launch the Program with a 
price, terms and characteristics that meet the criteria set by their municipal officials. 
 
The City will provide written notice of its acceptance of a bid and the Program’s date of 
commencement of service to the NHPUC, the Office of Consumer Advocate, the 
Department of Energy as required by Puc 2204.04.  
 
The Program will utilize consolidated billing such that the participating customers 
receive a single bill from the electric distribution utility that includes the charges for the 
Program’s electricity supply and all other charges from the electric distribution utility. 
The Program will confirm this choice of billing service by notifying the electric 
distribution utility of prior to the enrollment of customers, including providing any 
applicable Product details required pursuant to Puc 2205.16.  
Page 148 of 210

City of Keene 
 
Community Power Plan 
 
 
 
 
August 5, 2026 
 
 
 
 
                    15 
 
VI.b.  Implement public information program including Customer 
Notification Letters  
 
An Education and Outreach Plan is required to fully inform and educate potential 
customers and participants in advance of automatic enrollment in the Community Power 
Program.  Customers, including customers with limited English language proficiency and 
disabilities, must be informed that they would be automatically enrolled in the Program 
and that they would have the right to opt-out of the Program without penalty. The 
purpose of the Education and Outreach Plan is to raise awareness and provide retail 
electric customers with information concerning their opportunities, options and rights for 
participation in the Program. To facilitate the Education and Outreach Plan, the City will 
utilize contact information for retail electric customers provided to the City by the 
electric distribution utility pursuant to Puc 2004.03. 
 
The Education and Outreach Plan (See Exhibit II) consists of five components: 
 
i. Initial Outreach and Education: This will be conducted after the selection of a 
Competitive Supplier and prior to arrival of the customer notification letter. It is 
intended to promote general awareness of the upcoming Program, minimize any 
questions generated by the arrival of the customer notification letter and maximize 
recipients’ ability to make an informed choice about their participation in the 
Program. This effort will include information about the goals of the Program, the 
basic terms and conditions including renewable energy components, and the opt-
out process. This effort will also include posting of the Program’s product 
information for residential and small commercial customers on the Department of 
Energy’s shopping comparison website. Such information will be posted on the 
website in advance of mailing the Customer Notification Letters. 
 
ii. Customer Notification Letters: In addition to the initial outreach and education 
initiatives, a notice (“Customer Notification Letter”) will be mailed to every retail 
electric customer. The Program will have two versions of this letter, one for 
Eligible Customers and one for other customers.  
 
The Customer Notification Letter for Eligible Customers will contain a description 
of the aggregation program; the implications to the City; the rights and 
responsibilities that the participants will have under the Program; all details, 
including all rates, on the products offered by the Program; explain that the 
customer will be automatically enrolled in the default product unless they choose 
otherwise and identify the deadline to make such a choice; have instructions for 
how to not participate (opt out) via web, phone or a pre-addressed envelope and 
opt-out reply card included with the letter; and instruction for how to enroll in an 
optional Program product. The opt-out period will last a minimum of 30 days from 
Page 149 of 210

City of Keene 
 
Community Power Plan 
 
 
 
 
August 5, 2026 
 
 
 
 
                    16 
the date of mailing of the Customer Notification Letters. 
 
The Customer Notification Letter for other customers will, at a minimum, contain a 
description of the aggregation program, the implications to the City, and 
instructions for how to enroll in any of the Program products if desired.  
 
Prior to the mailing of the Customer Notification Letters, the Program will confirm 
with the Competitive Supplier and the electric distribution utility that the 
Competitive Supplier is able to use EDI for enrollment of Default Service 
customers into the Program.   
 
iii. Opt-Out Period Education & Outreach: After the Customer Notification 
Letters have been sent, the City will continue its education and outreach to afford 
residents and businesses the opportunity to learn more and find answers to key 
questions relating to their decision to opt out or enroll in one of the optional 
products of the Program. This will include, at a minimum, a public information 
meeting within 15 days of the mailing of the customer notification letter.  
 
iv. Timeline and Preliminary Marketing Plan for Launch: This component 
identifies the steps the City intends to take in marketing the Program including 
identification of media and other community resources, examples of education and 
outreach documents, and an expected timeframe for the outreach effort. 
 
v. Ongoing Outreach & Education: This component describes the expected 
outreach and education activities following Program launch. Key elements include: 
 
● Program goals and performance, particularly as they relate to progress 
towards the City’s ambitious short- and long- term goals for renewable 
energy, particularly for 2030 and 2050.  
● On-going campaigns to recruit participation into its optional product(s) that 
contain more renewable energy than required by law (“Opt up campaigns”). 
Increasing participation in these products will serve the City’s goals to 
expand new renewable energy and increase overall renewable energy use; 
AND 
● Promotion and support of the NHSaves energy efficiency program, and 
future energy efficiency and weatherization programs 
The attached Education and Outreach Plan (Exhibit II) describes in detail the City’s 
anticipated outreach efforts, including a timeline. 
 
VI.c.  Enroll customers and provide service  
 
Page 150 of 210

City of Keene 
 
Community Power Plan 
 
 
 
 
August 5, 2026 
 
 
 
 
                    17 
i. Enroll Customers: After the conclusion of the opt-out period (i.e. no sooner than 
37 days from the date of the postmark of the Customer Notification Letters, which 
includes 3 days for mailing, 30 days for customer consideration, and an additional 3 
days for return of the replay card), the Competitive Supplier will enroll into the 
Program all retail electric customers on Default Service with the electric 
distribution utility who did not opt out and any other retail electric customers that 
have affirmatively requested in writing or through email to be enrolled into the 
Program. All enrollments and other transactions between the Competitive Supplier 
and the electric distribution utility will be conducted in compliance with the 
relevant provisions of New Hampshire Public Utilities Commission regulations, 
Terms and Conditions for Competitive Suppliers, and the protocols of the New 
Hampshire Electronic Business Transaction (EBT) standards. 
 
After enrollment of each customer, the Program may receive billing information for 
each enrolled customer from the electric distribution utility pursuant to Puc 
2205.13. 
 
ii. Provide Service: Once customers are enrolled, the Program will provide all-
requirements power supply service. The Program will also provide ongoing 
customer service, maintain the Program website, and process customer enrollments, 
ongoing opt outs, and customer selections of optional products.  The Program will 
provide Energy Source Disclosure labels to participants as required by RSA 
378:49.  
 
Prior to the expiration of the initial ESA, the City intends to solicit a new power 
supply agreement, as described in Section XIII. Method of Terminating and 
Entering Agreements with Other Entities. If the City elects not to enter into a 
new power supply agreement, participating customers would return to Default 
Service as described in Section XV. Extensions or Termination of Program.  
 
Retail electric customers that apply for new service with the electric distribution 
utility (e.g., new customers move into the City or move within the City), they will 
initially be enrolled in Default Service supply provided by the electric distribution 
utility. The Program will mail such customers a Customer Notification Letter for 
Eligible Customers per section IV.b.ii detailing the Plan and an opt-out card. At the 
end of the opt-out period they will be enrolled in the Program unless they elect to 
opt-out, per section IV.c.i. New customers also may proactively enroll by 
contacting the Program directly.  
 
The City will update the information on the Program’s products on the Department 
of Energy’s comparison shopping website whenever such information changes. 
 
iii. Annual Report: On an annual basis, the City Manager, or its designee(s) will 
Page 151 of 210

City of Keene 
 
Community Power Plan 
 
 
 
 
August 5, 2026 
 
 
 
 
                    18 
report to the City Council on the status of the Community Power Program, 
including the number of customers enrolled and opting-out, kilowatt-hour usage, 
customer savings, participation in renewable energy products, and such other 
information as the City may request. The information for this report will be 
prepared by the Community Power Consultant, and the Community Power 
Consultant will assist or lead in presenting to the City Council as desired by the 
City Manager.  
 
iv. Data Portal: The Community Power Consultant will make available to the City 
Manager and its designee(s) a secure, password-protected cloud-based data portal 
that provides the ability to run reports on key Program metrics and performance.  
 
VI.d.  Plan for Program evolution 
 
City seeks to continually improve the Program and progress towards its long-term goals. 
To this end, the Community Power Consultant and City will regularly assess new 
opportunities such as technologies, services, regulatory policy changes, and more for 
their applicability to the Program. Community Power Consultant will develop appropriate 
strategies to integrate these opportunities into the Program. Community Power 
Consultant will support the City to present new opportunities to the City Council for their 
consideration and approval, if amendments to the Plan are needed. 
 
VII. Funding   
 
All of the costs of the Program will be funded through the per kilowatt-hour rates 
established in the ESA. Only Program participants will pay for the costs of the Program, 
listed below.  
 
The primary cost will be the cost of the Competitive Supplier for the power supply, 
which will be funded through a per kilowatt-hour power supply rate component. These 
costs will be established through the competitive solicitation for a supplier.  
 
The administrative costs of the Program will be funded through a per kilowatt-hour 
administrative rate component that will be paid by the Competitive Supplier to the 
Community Power Consultant, as specified in the ESA. This rate component will cover 
the services of the Community Power Consultant, including developing the Community 
Power Plan, managing the supply procurement, developing and implementing the public 
education plan, providing customer support, interacting with the electric distribution 
utility, monitoring the supply contract, and providing ongoing reports. 
 
The City may choose to collect a per kilowatt-hour discretionary energy reserve fund rate 
component that will be paid by the Competitive Supplier to the City, as specified in the 
ESA. The City shall deposit and maintain such amounts in an enterprise fund to be used 
Page 152 of 210

City of Keene 
 
Community Power Plan 
 
 
 
 
August 5, 2026 
 
 
 
 
                    19 
for the cost of providing energy-related benefits to Program participants and supporting 
Program goals. Examples of such uses include (1) supporting development of new 
renewable energy projects, (2) supporting electrification of thermal and transportation 
uses, and (3) other energy-related programs and services. The City Council shall provide 
authorization for the use of funds from the discretionary energy reserve fund rate 
component. The City Manager will determine the appropriate amount of discretionary 
energy reserve fund rate component to include in each product in each ESA, within a 
range pre-approved by the City Council. 
 
VIII. Rate Setting and Other Costs to Participants 
 
The Program is offered on an opt-out basis, such that Eligible Customers will be 
automatically enrolled unless they proactively choose to opt out. 
 
As described above, the Program’s per kilowatt-hour rates will include the power supply,  
administrative, and discretionary energy reserve fund rate components, and applicable 
taxes pursuant to the ESA. Prices, terms, and conditions may differ among customer 
classes, which classes will be the same as the Default Service customer classes of the 
electric distribution utility.  The frequency of price changes will be determined through 
the competitive bid process.  The City expects to solicit bids for a number of different 
contract terms.  Prices may change as specified in the winning bid and customers will be 
notified of price changes through media releases and postings on the Community Power 
Program website. 
 
Regulatory events, such as new or altered requirements for the Renewable Portfolio 
Standard, or new taxes may result in a direct, material increase in costs during the term of 
the ESA. In such cases, the City and the Competitive Supplier will negotiate a potential 
change in the Program price. At least 30 days prior to the implementation of any such 
change, the City will notify customers of the change in price by issuing a media release 
and posting a notice in City Hall and on the Program website. The City shall also notify 
the NHPUC Consumer Services and External Affairs Division prior to implementation of 
any change in the Program price related to a regulatory event or new taxes. Such notice 
shall be provided prior to notifying customers and will include copies of all media 
releases, postings on the City and Program websites and any other communications the 
City intends to provide to customers regarding the price change. 
 
The Program affects only the electricity supply charges of the customers. Delivery 
charges will be unchanged and will continue to be charged by the electric distribution 
utility in accordance with tariffs approved by the NHPUC.  
 
Participants in the Program will receive one bill from the electric distribution utility that 
includes both the power supply charge of the Competitive Supplier and the delivery 
charge of the electric distribution utility.  Any applicable taxes will be billed as part of 
Page 153 of 210

City of Keene 
 
Community Power Plan 
 
 
 
 
August 5, 2026 
 
 
 
 
                    20 
the Program’s power supply charge. 
 
Participants in the Program will be able to opt-out of the Program and transfer to Default 
Service with the electric distribution utility or to another competitive supplier. Such 
requests submitted to the Program will be submitted by the Competitive Supplier to the 
electric distribution utility for processing on the customer’s next available regular meter 
read date. There shall be no penalty or exit fee for such transfer. Customers requesting 
transfer of supply service upon dates other than on the next available regular meter 
reading date may be charged an off-cycle meter reading and billing charge if such a 
service is available from the electric distribution utility. 
 
 
IX. Net Metering Compensation  
 
In accordance with RSA 362-A:9, II, the Program may determine the terms and 
conditions for net metering. In order to support the development of distributed energy 
resources within Keene, the Program will seek to offer net metering terms and conditions 
- for standard, alternative and group net metering - equal to or better than that provided 
on Default Service. To this end, the Program will evaluate the net metering terms and 
conditions offered by competitive suppliers as part of the procurement and bid selection 
process.  
 
To ensure net metering customers can make a fully informed decision on their 
participation in the Program, the Program will tailor all education and outreach materials 
to clearly communicate any and all differences between the net metering value and 
operation provided by the Program and Default Service. 
 
Additionally, the Program will evaluate how any proposed or implemented changes to the 
utility metering or billing infrastructure may create new opportunities to enhance the net 
metering benefits.  
 
 
X. Electric Assistance Program and other discounts 
 
The New Hampshire Electric Assistance Program (EAP) provides qualifying customers 
with a discount on their monthly electric bill. The New Hampshire Legislature authorized 
funding for this statewide program as part of electric utility deregulation. All electric 
utility ratepayers support the statewide EAP through the System Benefits Charge (SBC) 
portion of their electric bill.  
 
The EAP for income-eligible customers that may qualify for a discount off their monthly 
electric bill would continue for participants in the Program. The level of discount depends 
on household income, household size and electricity usage. 
Page 154 of 210

City of Keene 
 
Community Power Plan 
 
 
 
 
August 5, 2026 
 
 
 
 
                    21 
 
The EAP discount does apply to the Supplier Services portion of an electric bill when a 
customer chooses an independent supplier for their electricity needs. The participants in 
the Program who are enrolled in the EAP will receive their discounts by the same method 
they presently receive their discount. Participation in the Program is independent of 
enrollment in the EAP and does not impact the EAP discount.  
 
Other discount programs administered by Community Action Programs that address the 
needs of low-income residents would continue for participants in the Program. 
 
XI. Aggregating Municipalities & Buying Group  
 
Participating in a buying group may offer the potential for the City to expand its buying 
power for greater economies of scale and to support the City’s goal of acting as a regional 
leader, supporting other municipalities to access the benefits for Community Power. 
Keene will evaluate opportunities for such a buying group before issuing a bid for 
competitive supply. See Section VI.a. Issue an RFP for Power Supply and Select a 
Competitive Supplier for details on the implementation of a buying group. 
 
Additionally, the City reserves its right, in accordance with RSA 53-E:6, I, to join with 
other municipalities or counties for its Community Power Plan and implementing its 
Community Power Program. Any changes to the Community Power Plan must be 
reviewed and approved by the City Council. 
 
XII. Promoting Energy Efficiency 
 
In addition to supporting cost-competitive and cleaner electricity, the City seeks to 
leverage the Community Power Program to help reduce energy use. This will initially 
take the form of cross-promoting awareness of efficiency programs through the 
Program’s education and outreach. The Program will also evaluate opportunities for more 
direct support of energy efficiency.  
 
Promotional education will focus on existing energy efficiency and conservation 
programs, such as New Hampshire’s Weatherization Assistance Program for low-income 
households  and the New Hampshire Saves (NHSaves) program, which provides 
customers with information, incentives and support designed to save energy, reduce 
costs, and protect our environment statewide. NHSaves is funded by electric and natural 
gas ratepayers and delivered by Eversource, Liberty Utilities, New Hampshire Electric 
Cooperative and Unitil to make homes, businesses and towns more sustainable and more 
comfortable places to live and work, both now and in the future. Through NHSaves 
customers can receive a Home Energy Assessment. The assessment identifies energy-
saving opportunities in the home and provides the customer with an energy report. The 
report includes information on equipment rebates and no-cost products, as well as access 
Page 155 of 210

City of Keene 
 
Community Power Plan 
 
 
 
 
August 5, 2026 
 
 
 
 
                    22 
to 0% financing and a limited time offers, such as up to 100% off approved insulation. 
The assessment can also include delivery of energy-saving products recommended by the 
Energy Specialist, such as LED light bulbs, advanced power strips, and thermostats that 
can be installed right away to start saving money and energy. 
 
If and when additional energy efficiency and conservation programs or initiatives become 
available, the Program will evaluate how to incorporate them into its promotional 
outreach and education. 
 
XIII. Method of Entering and Terminating Agreements with Other 
Entities   
 
The process for entering, modifying, enforcing, and terminating all agreements associated 
with the Plan will comply with the municipal charter, federal and state law and rules and 
regulations, and the provisions of the relevant agreement. 
 
The City plans to use the same process described in Section IV.a. of this Plan to solicit 
bids and enter into any subsequent ESAs with the assistance of its then-current 
Community Power Consultant.  Customers will be notified of subsequent ESAs through 
press releases and public notices.  The transfer of customers from the existing supplier to 
the new supplier will be coordinated with the electric distribution utility using established 
Electronic Data Interchange (EDI) protocols. 
 
If the City determines that it requires the services of a Community Power Consultant after 
expiration of the existing agreement with GE/SP, it will evaluate opportunities to solicit a 
Community Power Consultant individually or as part of a group of municipalities 
aggregating the electric load of their respective customers. The City will solicit proposals 
for, and evaluate, potential Community Power Consultants using a competitive 
procurement process or alternative procedure which the City determines to be in the best 
interest of its customers and consistent with all applicable local, state and federal laws 
and regulations. 
 
XIV. Rights and Responsibilities of Program Participants 
 
All participants will have the right to opt out of the Program at any time without charge. 
They may exercise this right by any of the following:  1) calling the toll-free number of 
the Competitive Supplier; 2) contacting the electric distribution utility and asking to be 
returned to Default Service; or 3) enrolling with another competitive supplier. 
 
All participants will have available to them the customer protection provisions of the law 
and regulations of New Hampshire, including the right to question billing and service 
quality practices. Customers will be able to ask questions of and register complaints with 
the City, the Community Power Consultant, the Competitive Supplier, the electric 
Page 156 of 210

City of Keene 
 
Community Power Plan 
 
 
 
 
August 5, 2026 
 
 
 
 
                    23 
distribution utility and the NHPUC. As appropriate, the City and the Community Power 
Consultant will direct customer complaints to the Competitive Supplier, the electric 
distribution utility or the NHPUC.  
 
Participants will continue to be responsible for paying their bills and for providing access 
to metering and other equipment necessary to carry out utility operations.  Participants 
are responsible for requesting any exemption from the collection of any applicable taxes 
and must provide appropriate documentation of such exemption to the Competitive 
Supplier. 
 
XV. Extensions or Termination of Program   
 
Prior to the end of the term of the initial ESA, the City will solicit bids for a new supply 
agreement and plans to continue the Program with the same or new competitive supplier.   
 
Although the City is not contemplating a termination date, the Program could be 
terminated upon the termination or expiration of the ESA without any extension, renewal, 
or negotiation of a subsequent supply contract, or upon the decision of the City to 
dissolve the Program effective on the end date of the existing ESA. In the event of 
termination, customers would return to the Default Service of the electric distribution 
utility, unless they choose an alternative competitive supplier. The City will notify 
customers of a planned termination of the Program through media releases and postings 
on the Program website. 
 
The City will notify the electric distribution utility of the planned termination or 
extension of the Program in writing.  In particular, the City will provide the electric 
distribution utility notice: (1) 90 days prior to a planned termination of the Program; (2) 
90 days prior to the end of the anticipated term of the ESA; and (3) four business-days 
after the successful negotiation of a new ESA. The City will also provide written notice 
to the NHPUC 90 days prior to a planned termination, which notice shall include copies 
of all media releases, City Hall and website postings and other communications the City 
intends to provide customers regarding the termination of the Program and the return of 
participants to Default Service. The City will also provide written notice 90 days prior to 
a planned termination to the Office of the Consumer Advocate and the Department of 
Energy. 
 
In the event of unplanned termination of the Program because that the Program can no 
longer provide service to its customers, the Program shall provide immediate written 
notice to the NHPUC describing the market suspension or other event that caused the 
Program to no longer be able to provide service, the effective time of the inability to 
provide service, and the notice provided to customers of the timing and consequences of 
the cessation of the Program’s service. The Program shall file a copy of such notice at the 
same time to the office of the Office of the Consumer Advocate, the Department of 
Page 157 of 210

City of Keene 
 
Community Power Plan 
 
 
 
 
August 5, 2026 
 
 
 
 
                    24 
Energy, and the electric distribution utility. 
 
In the event of the termination of the Program, it is the responsibility and requirement of 
the Competitive Supplier to return the customers to Default Service of the electric 
distribution utility in accordance with the then applicable EDI rules and procedures. 
 
In the event of the termination of the Program, the balance of any funds accrued by the 
Program’s discretionary energy reserve fund, if any, would be available for distribution 
or application as directed by the City Council and in accordance with any applicable law 
and regulation. 
 
XVI. Planned Schedule  
 
The planned schedule below is presented for illustrative purposes. The final schedule will 
be established once the Program has received all necessary approvals and will ensure 
compliance with the all required notification timelines prior to Program commencement.   
 
Day 
Action or Event 
1 
Issue RFP for Competitive Supplier 
31 
ESA executed between City and Competitive Supplier. Program provides 
required notifications to NHPUC, Department of Energy, Office of 
Consumer Advocate, and electric distribution utility.  
32 
Competitive Supplier receives retail electric customer mailing data and data 
needed for Eligible Customer enrollment in Program 
48 
Competitive Supplier, at its expense, mails Customer Notification Letters to 
all retail electric customers, including identifying the return date by which 
the reply card envelopes for Eligible Customers must be mailed and 
postmarked 
51 
Retail electric customers receive Customer Notification Letter in the mail 
81 
Return date by which Eligible Customers deciding to opt-out must mail a 
reply card in pre-paid envelope to Competitive Supplier.  
85 
Competitive Supplier removes all Eligible Customers who opt out from the 
Eligible Customer list 
85 
Competitive Supplier sends “supplier enrolls customer” EDI for all Eligible 
Customers that did not opt-out and any other customers that affirmatively 
elected to opt-in to the Program. 
Page 158 of 210

City of Keene 
 
Community Power Plan 
 
 
 
 
August 5, 2026 
 
 
 
 
                    25 
90 
 Service begins as of each customer's next meter read date 
 
 
 
XVII. Conclusion 
 
Keene’s Community Power Program meets all of the requirements of the Community 
Power law, including providing universal access, a reliable power supply and treating all 
customer classes equitably. The City looks forward to launching the Program and 
pursuing the benefits of a competitive power supply, renewable energy, and electricity 
choice for its retail electric customers.
Page 159 of 210

City of Keene 
 
Community Power Plan - Exhibit I  
 
 
 
 
August 5, 2026February 10, 2025      
 
 
 
 
               26 
 
 
Exhibit I - Historical Overview 
 
List of Revisions 
  
Adopted by City Council on May 6, 2021 
Amended July 31, 2022 
Approved by New Hampshire Public Utilities Commission October 3, 2022 
Adopted by City Council on November 3, 2022 
Amended February 10, 2025 
Adopted by City Council on March 20, 2025 
Amended August 5, 2026 
Formally adopted by City Council on TBD 
      
1. Creation of Community Power Committee  
On June 18, 2020 the Keene City Council approved the formation of an Ad-Hoc 
Community Power Committee (CPC). From City Council Minutes June 18, 2020: 
 
 
 
 
2. Creation of a Draft Plan with public hearings 
The Committee, supported by City Staff and the Community Power Consultant, 
Page 160 of 210

City of Keene 
 
Community Power Plan - Exhibit I  
 
 
 
 
August 5, 2026February 10, 2025      
 
 
 
 
               27 
 
 
held two public information sessions on December 8, 2020 to promote awareness 
of the development of a Community Power Plan and to begin gathering input. 
Also on December 8, 2020, the Committee released a community survey open for 
approximately one month through January 7, 2021. The survey was available 
online and via paper in the Monadnock Shopper News. The online survey and the 
City’s website, KeeneEnergyPlan.com also hosted two educational videos about 
Community Power. KeeneEnergyPlan.com has hosted additional educational 
resources about Community Power, including an FAQ page, podcast and 
interviews with municipal leaders from active community power (also known as 
municipal aggregation) programs, such as Medford, Massachusetts.  
 
The survey received 126 responses, 97 online and 29 in paper via the Monadnock 
Shopper News. Key survey findings: 
● 86% of respondents currently receive supply from Eversource Default Service. 
Such customers would be eligible for automatic enrollment in the Program. 
● The survey had a well-distributed diversity of household income groups and 
age, as shown below: 
 
● Respondents identified a range of benefits they are interested in with 
Page 161 of 210

City of Keene 
 
Community Power Plan - Exhibit I  
 
 
 
 
August 5, 2026February 10, 2025      
 
 
 
 
               28 
 
 
Community Power: 
 
● 92% of respondents were interested in including more renewable energy in 
their electricity. Of those interested, roughly half (45%) sought extra renewable 
energy if they could pay about the same they pay today. The other half (55%) 
was willing to pay a little or a lot more for extra renewable energy. 
 
● When analyzing preferences for renewable energy and cost by household 
income, a similar pattern remains for each income group.  
Those households under $50k were more likely than other income groups to 
want no extra renewable energy; however, 83% of the income group was still 
interested in more renewable energy. Of those interested, 50% sought extra 
renewable energy if they could pay about the same they pay today. The other 
33% was willing to pay a little or a lot more for extra renewable energy. 
 
Page 162 of 210

City of Keene 
 
Community Power Plan - Exhibit I  
 
 
 
 
August 5, 2026February 10, 2025      
 
 
 
 
               29 
 
 
 
Do you want extra renewable energy, by household income? 
 
 
 
 
 
● Nearly three-quarters (73%) of participants had not performed an energy audit, 
and the percentages were nearly identical across household income groups. 
There appears to be widespread opportunity for energy efficiency 
improvements, with nearly three-quarters (71%) reporting that they keep their 
thermostat lower than they would like in winter and over half (51%) reporting 
their home is drafty or heating costs are too high. 
Energy efficiency 
 
 
 
Survey Conclusions:  
The majority of participants in Community Power programs typically remain in 
the default product rather than choosing any of the program optional products. 
Given the strong support for both renewable energy and cost parity demonstrated 
in the survey responses, it suggests that Keene would be well-served by a default 
Page 163 of 210

City of Keene 
 
Community Power Plan - Exhibit I  
 
 
 
 
August 5, 2026February 10, 2025      
 
 
 
 
               30 
 
 
product designed with the goals of 1) achieving cost parity or savings compared to 
Eversource Default Service and 2) including some extra renewable energy.  
 
Additionally, the survey highlighted that, for those that can afford it, the program 
should offer options with substantially more renewable energy for a price 
premium. 
 
Although less than 8% of survey responses were not interested in extra renewable 
energy, it could be beneficial to have an optional product that would meet their 
needs by providing a lower-cost option with no extra renewable energy, 
particularly for those households in the lowest income bracket. 
 
There is substantial opportunity for energy audits and efficiency improvements, 
suggesting support for energy efficiency by the Program would be valuable. 
 
Respondents also cited an interest in local jobs, which the Program can support 
through demand for additional local renewable energy and by promotion greater 
participation in energy efficiency programs. Regional cooperation, particularly 
with neighboring municipalities, would amplify this impact as well. 
 
Draft Plan: Public Hearings & Comments 
The Committee held two additional public meetings on January 26, 2021(12:00 
pm and 6:30 pm) to present the survey findings, discuss how the results would be 
incorporated into the draft Community Power Plan, and provide an overview of 
other details to expect in the Community Power Plan. 
On February 5, 2021 the draft Community Power Plan was posted publicly to the 
program website, KeeneCommunityPower.com. During the Committee’s meeting 
on February 12, 2021, the Committee announced the availability of the draft 
Community Power Plan, invited comment and scheduled two public hearings for 
March 30, 2021 (12:00 pm and 6:30 pm). The Committee and the City promoted 
awareness of the draft Plan through diverse means including a formal hearing 
notice in the newspaper, press releases, postings on the City website and social 
media, and email outreach to the City’s Community Power email list. The public 
was encouraged to submit comments ahead of the public hearings using the online 
comment form on the program’s website, KeeneCommunityPower.com, and 
email, phone or written comment to the City’s Community Development 
department. 
The Committee received comments ahead of and during the public hearings. All 
public comment is available in the Committee’s meeting packet for April 8, 2021. 
3. Approval of Plan by Community Power Committee 
Page 164 of 210

City of Keene 
 
Community Power Plan - Exhibit I  
 
 
 
 
August 5, 2026February 10, 2025      
 
 
 
 
               31 
 
 
The Committee discussed public comments and potential changes to the 
Community Power Plan during their Committee meeting on April 2, 2021. 
Additional public comment was provided during the meeting, and the Committee 
determined to reconvene on April 8, 2021 (see the Committee’s meeting packet 
for April 8, 2021 for additional comment received). 
 
In response to some of the public comments, the Committee revised the plan as 
follows: 
● Adjusted the language describing the likely sources of additional renewable 
energy in the City’s first supply contract to make it clear that local renewable 
energy generated within the “greater Monadnock region” could also be 
included, in addition to NH Class I renewable energy. 
● Revised the procurement language to clearly allow for the procurement of 
power and Renewable Energy Credits (RECs) from the same facility (also 
known as “bundled”) or purchase only one or the other from a facility (also 
known as “unbundled”). 
● Revised the procurement language to allow for the selection of multiple 
suppliers (for example, one for residential and small commercial and one for 
large industrial). 
● Modified language throughout the plan to clarify what is meant by the term 
“local” in different contexts (e.g. “renewables that are on the ISO-New 
England electricity grid,” or “within or as close as possible to Keene in New 
Hampshire”). 
 
The revised plan, including a red-line and clean version dated April 5, 2021, was 
included in the Committee’s meeting packet for the meeting on April 8, 2021. 
During the meeting, the Committee discussed the revisions. The Committee then 
unanimously voted to approve the plan and recommend it to the City Council for 
adoption.  
 
Subsequent to the meeting, on April 8, 2021, summary detail of the public 
hearings, public comment, Committee’s deliberation and vote was added to the 
Historical Overview. 
 
4. Adoption of Plan by City Council 
At the City Council meeting on April 15, 2021 the Community Power Committee’s 
report, which unanimously approved the City of Keene Community Power Plan and 
recommended adoption to the City Council, was read. The report was referred to the 
Finance, Organization & Personnel Committee (FOP). The FOP Committee met on 
April 22, 2021 to review the Plan. Representatives from City staff, the Community 
Power Committee and the Community Power Consultant presented to the FOP 
Committee, and following questions and discussion, the FOP Committee unanimously 
Page 165 of 210

City of Keene 
 
Community Power Plan - Exhibit I  
 
 
 
 
August 5, 2026February 10, 2025      
 
 
 
 
               32 
 
 
voted to recommend adoption of the Plan.  At the City Council meeting on May 6, 
2021, the FOP Committee’s recommendation was reported to the City Council, and 
the Council voted unanimously to adopt the Plan.  
 
Subsequent to the meeting, on May 10, 2021, summary detail of the City Council 
review and adoption process was added to the Historical Overview. 
 
5. Revision of Plan 
The City amended the Plan in mid-March 2022 to better address questions of data 
security based on feedback provided by the Public Utilities Commission in orders on 
other Community Power plans. The City submitted its Plan to the Commission in 
April 2022 (DE 22-022), and it received an order in June 2022 which encouraged the 
City to re-submit the Plan closer to or after the completion of the rulemaking process 
for Community Power.  
 
On July 27, 2022, the Commission voted to approve Community Power rules. The 
City further amended the Plan on July 31, 2022  to appropriately reference those rules.  
 
6. Submission of Revised Plan to Public Utilities Commission 
The City submitted the revised Plan to the Public Utilities Commission (PUC) on 
August 3, 2022 under the existing docket number (DE 22-022) and the PUC approved 
the revised Plan on October 3, 2022. 
 
7. Adoption of Revised Plan by City Council 
The City Council adopted the revised Plan at their meeting on November 3, 2022. 
Subsequent to the meeting, summary detail of the vote (#7) and the submission to the 
PUC (#6) were added to this Exhibit I.  
 
8. Adoption of Revised Plan by City Council 
The City amended the plan in February 2025 to enable it to collect additional revenue 
in its rates to support energy-related projects that would benefit Program participants. 
The City Council adopted the revised Plan at their meeting on March 20, 2025. 
 
9.  Adoption of Revised Plan by City Council 
The City amended the Plan in August 2026 to enable different default products for 
customers on the New Hampshire Electric Assistance Program (EAP). The City 
Council adopted the revised Plan at their meeting on TBD.
Page 166 of 210

City of Keene                                                                                   Community Power Plan - Exhibit II 
 
 
 
 
August 5, 2026February 10, 2025      
 
 
 
 
               33 
 
 
Exhibit II - Education & Outreach Plan 
 
1.   Initial Outreach and Education 
 
The initial outreach and education will provide a description of the Program for retail 
electric customers and will be conducted via traditional print and TV channels, social 
media, a dedicated website, public presentations and personal communications to 
inform retail electric customers about the Program and will include a toll-free number. 
This effort will provide specific information about the Program and increase public 
awareness of the goals of the Program and the upcoming opt-out notification process. 
 
If any Program materials were to reference cost savings for any part of the Program, a 
notice would be included which states that the City cannot guarantee that the Program 
will provide customers with prices lower than the distribution utility’s Default Service 
rate over the full term of any supply contract entered into by the City. 
 
1.1   Media Outreach 
 
Prior to the launch of the Program, the City will initiate media outreach that may 
include the use of local cable television shows, newspapers and social media to 
provide greater public education and to describe the Program, the opt-out process, the 
website, and the toll-free telephone number. Outreach may also include public service 
announcements (PSAs), scheduling interviews of Program spokespersons with local 
media outlets, and securing a positive media presence. 
 
A news release may be distributed to help achieve the aforementioned goals. Follow-
up news releases may be used to update the media on the status of the progress of the 
Program.  
 
1.2   Notices and Public Postings 
 
Brochures/flyers will be distributed in City offices describing the Program, the opt-out 
process and the toll-free telephone number in order to further reinforce the Program's 
details. Brochures/flyers may be placed in key gathering areas or buildings (e.g. 
library, Senior Center, etc.) which will create the necessary repetition of messages 
required to motivate customer action and build awareness and understanding. 
 
1.3   Customer Service Center 
 
The Program will maintain a toll-free telephone number to address retail electric 
customers’ questions regarding the Program, deregulation, the opt-out process, price 
information and other issues such customers may raise. 
Page 167 of 210

City of Keene                                                                                   Community Power Plan - Exhibit II 
 
 
 
 
August 5, 2026February 10, 2025      
 
 
 
 
               34 
 
 
 
1.4   Website 
 
All information regarding the Program will be posted on the Program website, which 
is linked to the website of the City: https://keenecommunitypower.com/. The Program 
website will have links to the website of the electric distribution utility, the New 
Hampshire Public Utilities Commission (NHPUC), Department of Energy, and the 
Competitive Supplier. 
 
1.5   Public Presentations 
 
The Program will provide presentations to municipal officials and to interested 
community groups.  
 
1.6   Outreach to Persons with Limited English Proficiency or Disabilities 
 
The Program plans to make printed materials available in English. To accommodate 
limited English-speaking residents, the City will provide a translation option on its 
Program website (which contains all details on the Program including a description of 
the Program and its products, the implications to the City, and the rights and 
responsibilities that the participants will have under the Program) that will translate 
any written materials on the website into over 100 different languages. The website 
also will be designed with the goal of being compliant with the Americans with 
Disabilities Act (“ADA”) and will include formats that allow the content to be read 
out loud by computer assistive technology.  Outreach efforts will be communicated in 
print and audio formats to provide access to both the hearing and visually impaired. 
 
2.   Customer Notification Letter 
 
The Customer Notification Letters will be sent via standard mail to the billing address 
of each retail electric customer per section IV.b.II of the Plan.  The Program will have 
two versions of this letter, one for Eligible Customers and one for other customers. 
The Competitive Supplier shall bear all expenses regarding the Customer Notification 
Letters. 
 
2.1 Customer Notification Letter for Eligible Customers 
Per section III.b of the Plan, all retail electric customers receiving Default Service 
supply from the electric distribution utility will be eligible for automatic enrollment in 
the Program (“Eligible Customers”). The notification envelope will be designed to 
appear as an official City communication and it will be clearly marked as containing 
time sensitive information related to the Program. The notification will contain a letter 
describing the Program.  
Page 168 of 210

City of Keene                                                                                   Community Power Plan - Exhibit II 
 
 
 
 
August 5, 2026February 10, 2025      
 
 
 
 
               35 
 
 
 
The letter will inform Eligible Customers: 
 
a)  about the Program, implications to the City and provide information regarding 
participation and participants’ responsibilities and rights; 
b)  that they have the right to opt-out of the Program without penalty; 
c)  of all charges, prominently stated, with a comparison of price and primary 
terms of the Competitive Supplier and the current Default Service offering; 
d)  that any savings under the Program compared to Default Service cannot be 
guaranteed because the Default Service rate is subject to changes 
e)  about the opt-out process; and 
f)  in languages other than English for appropriate customer groups (i.e. toll-free 
telephone number). 
 
The letter will also contain an opt-out reply card with a simple check off and signature 
line for Eligible Customers who do not wish to participate. The envelope will be pre-
stamped for return of the opt-out reply card in order to protect customer privacy.  
 
Eligible Customers will have 33 days from the date of the mailing to mail back the 
opt-out card in a pre-addressed postage-paid envelope and the customer notification 
shall identify the specific date by which the envelopes containing the opt-out card 
must be postmarked.  Automatic enrollment of customers will not start until three 
days after the date specified for the postmark of the return envelopes to allow for 
receipt of the opt-out cards prior to the start of automatic enrollments. New Eligible 
Customers will be enrolled in the Program in accordance with applicable Local 
Distributor Company rules. Upon initiation of service, these new Eligible Customers 
will receive the same customer information as all other Eligible Customers. 
 
2.2. Customer Notification Letter for Other Customers 
The Customer Notification Letter for other customers will, at a minimum, contain a 
description of the aggregation program, the implications to the City, and instructions 
for how to enroll in any of the Program products if desired.  
 
 
3. Opt-Out Period Education & Outreach 
 
After the Customer Notification Letters have been sent, City will continue its 
education and outreach to afford residents and businesses the opportunity to learn 
more and find answers to key questions relating to their decision to opt out or enroll in 
one of the optional products of the Program. This process will include, at a minimum, 
a public information meeting within 15 days of the mailing of the customer 
notification letter. It will also include a similar range of outreach activities as 
Page 169 of 210

City of Keene                                                                                   Community Power Plan - Exhibit II 
 
 
 
 
August 5, 2026February 10, 2025      
 
 
 
 
               36 
 
 
enumerated in section 1.1 to 1.6. 
 
4. Timeline and Preliminary Marketing Plan for Launch 
 
The timeline and preliminary marketing plan identifies the steps the City may take to 
inform the community about the Program, as described in Sections 1 through 3 of 
Exhibit II. The schedule is designed to work towards the estimated date when the 
Customer Notification Letter is scheduled to arrive in customer mailboxes. The dates 
may be adjusted to ensure compliance with the minimum written notification 
timelines for the date of commencement of service to the NHPUC, the Office of 
Consumer Advocate, the Department of Energy Puc 2205.16.   
 
The costs and implementation will be handled by the Community Power Consultant, 
under the direction of the City. 
 
From estimated date Customer Notification Letter arrives in customer mailboxes 
Action 
Days before  
Days after  
A. Update Program & Shopping Comparison 
Websites  
15 
Ongoing 
B. Work with local media resources 
15 
30 
C. Active social media outreach 
15 
30 
D. Initial person presentations 
15 
30 
E. Distribute marketing materials 
15 
30 
F. Customer help line 
15 
Ongoing 
G. Mail postcard to all Eligible Customers 
5 
- 
H. Customer Notification Letters arrives 
0 
0 
 
A. Program & Shopping Comparison Website Update: 
Timeframe: 15 days before the estimated date that the customer notification letter 
arrives in customer mailboxes, then maintained on an ongoing basis.  
 
The Program’s website is https://keenecommunitypower.com/. After executing an 
ESA, the Program will update this website with a description of the Program and its 
Page 170 of 210

City of Keene                                                                                   Community Power Plan - Exhibit II 
 
 
 
 
August 5, 2026February 10, 2025      
 
 
 
 
               37 
 
 
products, the implications to the City, and the rights and responsibilities that the 
participants will have under the Program. 
 
The shopping comparison website is maintained by the Department of Energy to 
enable consumers to shop for electricity supply products. The Program will post its 
product information for residential and small commercial customers on the shopping 
comparison website. Such information will be posted on the website in advance of 
mailing the Customer Notification Letters.  
 
B. Work with local media resources: 
Timeframe: 15 days before to 30 days after the estimated date that the customer 
notification letter arrives. 
 
Area Newspapers: 
 
The City will work with area print and online newspapers to disseminate accurate and 
timely information about the Program. As part of this targeted outreach to these 
papers, the City may seek a meeting with the editorial board to establish a good 
foundation for continued dialogue over the course of the contract. Other newspaper 
outlets may include other local publications. 
 
● These papers include: Keene Sentinel, Monadnock Shopper News, and the 
New Hampshire Union Leader  
 
Local Public Access Television: 
 
The City intends to work with Cheshire TV channels for public (1301) and 
government (1302) access. City can record interviews about the Program and PSAs 
for upcoming meetings.  
 
Other Television and Radio Stations 
 
Develop press releases to send to other TV stations and radio stations.  
● TV stations include WMUR (ABC, MANCHESTER, NH) Channel 9; WUTF 
(INDEPENDENT, WORCESTER, MA) Channel 27; WVTA (PBS, 
WINDSOR, VT) Channel 41; WWJE (INDEPENDENT, DERRY, NH) 
Channel 50; WEKW (PBS, KEENE, NH) Channel 52; WNEU (NBC, 
MERRIMACK, NH) Channel 60; 
● Radio stations include WVBA (88.9 FM) Brattleboro, VT; WEVO (89.1 FM) 
Concord, NH; WEVN (90.7 FM) Keene, NH; WEEY (93.5 FM) Swanzey, 
NH; WSNI (97.7 FM) Keene, NH; WINQ (103.1 FM) Keene, NH; WKNE 
Page 171 of 210

City of Keene                                                                                   Community Power Plan - Exhibit II 
 
 
 
 
August 5, 2026February 10, 2025      
 
 
 
 
               38 
 
 
(103.7 FM) Keene, NH; WYRY (105.5 FM) Keene, NH; WCNL (1010 AM) 
Newport, NH; WKBK (1290 AM) Keene, NH; WTSA (1450 AM) Brattleboro, 
VT 
 
Municipal Staff Interviews 
Develop Q&A Scripts and prepare municipal staff or volunteers for interviews. 
 
C. Active Social Media Outreach 
Timeframe: 15 days before to 30 days after the estimated date that the customer 
notification letter arrives.  
 
Boost all traditional media coverage on social media platforms, with the goal of 
driving traffic to the dedicated website of the City.  
  
In concert with the communication leads of the City, develop a campaign of planned 
tweets and Facebook posts, timed to coincide with important milestones in order to 
keep ratepayers informed, particularly those that may not interact with traditional 
media on a regular basis. Draft content and graphics to accompany the posts, to be 
made by City staff. 
 
● These accounts may include: City of Keene (Instagram, Facebook); City 
Manager (Twitter); Keene Community Development (Instagram, Facebook & 
Twitter) and Keene Public Library (Instagram, Facebook & Twitter). 
  
Monitor various channels such as Facebook and Instagram for relevant conversations 
and questions about the Program. Draft responses to comments and questions and 
utilize social media as a critical tool in engaging with members of the community. 
● These accounts may include: “Downtown Keene” Facebook page 
(@downtownkeene); the “Keene, NH” Facebook group (5.5k members); and 
“Keene NH Community Forum” Facebook group (1.5k members) 
 
Identify key social media influencers in the City, including lawmakers, advocates and 
reporters. Develop a spreadsheet of the social media handles/accounts and reach out 
to them to keep them informed about the Program. 
 
D. In Person Presentations 
Timeframe: 15 days before to 30 days after the estimated date that the customer 
notification letter arrives. This will include, as required in RSA 53:E-7, a public 
information meeting within 15 days of the mailing of the customer notification letter. 
Page 172 of 210

City of Keene                                                                                   Community Power Plan - Exhibit II 
 
 
 
 
August 5, 2026February 10, 2025      
 
 
 
 
               39 
 
 
 
Local Groups 
 
Connect with local groups and associations to see if representatives of the City can 
participate in an upcoming meeting or offer to host a dedicated event. Seek their 
assistance in identifying how to best connect with customers with limited-English 
capabilities or disabilities that may prevent them from accessing Program 
information. 
 
● Example groups include: Neighborhood associations, Social service agencies, 
Business Focus Group, Rotary, Kiwanis, Lions, Chamber, Clean Energy team, 
Keene Young Professionals, Downtown Group, Board of Realtors, Keene 
Senior Center, Keene Off-campus Housing (landlords and tenants), Keene 
State College English as a Second Language (ESL) classes, CALL Program 
(Cheshire Academy for Lifelong Learning). 
 
Reaching the business community will be important. Presenting to the Chamber of 
Commerce can start this dialogue and lead to additional outreach to and connection 
with businesses. 
 
Council Meetings 
 
Present or provide materials for the Council meetings and any constituent meeting 
they may have. 
 
E. Distribute marketing materials 
Timeframe: 15 days before to 30 days after the estimated date that the customer 
Notification Letter arrives.  
 
Many groups may have a natural interest in promoting awareness about the Program 
and can be provided with electronic and hard-copy materials with reference 
information for the Program.  
 
Distribute to key locations such as Municipal Offices and Public Library. 
 
F. Customer Help Line 
Timeframe: 15 days before the estimated date that the customer notification letter 
arrives and ongoing thereafter.  
 
Establish customer helplines with the Competitive Supplier and Community Power 
Consultant to answer customer inquiries. 
 
Page 173 of 210

City of Keene                                                                                   Community Power Plan - Exhibit II 
 
 
 
 
August 5, 2026February 10, 2025      
 
 
 
 
               40 
 
 
G. Mail Postcard to all Eligible Customers 
Timeframe: 5 days before the estimated date that the customer notification letter 
arrives. 
 
Post Card 
 
Send out to Eligible Customers prior to Customer Notification Letter. Establishes that 
there is a community-sponsored Program and increases the likelihood that recipient 
engages with the more detailed Customer Notification Letter. 
 
H. Customer Notification Letters arrive 
Sent to all retail electric customers. See section 2 above for details.  
 
 
5.   Ongoing Outreach and Education 
 
The City intends to continue outreach and education for customers after enrollment in 
the Program. The costs and implementation will be handled by the Community Power 
Consultant, under the direction of the City. These efforts will include: 
 
● Program impact: Key metrics relating to cost performance, renewable energy 
purchases and Program enrollment. Particularly as the Program 
accomplishments relate to progress towards the City’s ambitious short- and 
long- term goals for renewable energy and greenhouse gas emission reduction. 
This will also include the Energy Source Disclosure labels for the electricity 
supply;  
 
● Opt up campaigns: On-going campaigns to recruit participation into its 
optional product(s) that contain more renewable energy than required by law 
(“Opt up campaigns”). Increasing participation in these products will serve the 
City’s goals to expand new renewable energy and reduce greenhouse gas 
emissions;  
   
● Customer awareness: Rights and procedures for Program participants; contact 
information for customer inquiries, responses to frequently asked questions, 
and details regarding the Program’s electric supply and renewable attributes.   
 
● Public input: As the Program considers changes to further its progress toward 
a 100% renewable future and other goals, City will manage outreach to solicit 
input and feedback from the community.  
 
● Program changes and evolution: Any changes in offerings and prices, which 
will be posted on the Program website that is linked to the website of the City. 
Page 174 of 210

City of Keene                                                                                   Community Power Plan - Exhibit II 
 
 
 
 
August 5, 2026February 10, 2025      
 
 
 
 
               41 
 
 
 
The Program will utilize similar mediums for on-going education and outreach as for 
the initial launch education and outreach, including but not limited to: social media, 
traditional media, in-person meetings and presentations, outreach to local groups, 
video, and mail.  
 
Translation of all materials will be provided as necessary to reach communities with 
limited English proficiency. 
Page 175 of 210

City of Keene                                                                                  Community Power Plan - Exhibit III 
 
 
 
 
August 5, 2026February 10, 2025      
 
 
 
 
               42 
 
 
 
Exhibit III - Data Protection Plan 
 
      
I. 
Introduction 
 
The City of Keene (the “Municipality”) is developing a Community Power program 
(the “Program”), pursuant to RSA 53-E. A municipality that implements such a 
program is known as an aggregator (“Aggregator”). RSA 363:38 and PUC 2004.19 
require that service providers, including Aggregators, protect individual and 
confidential customer data (“Individual Customer Data”). Individual Customer Data, 
as defined in RSA 363:38 and expanded in PUC 2004.19, means information that is 
collected as part of providing electric services to a customer that can identify, singly or 
in combination, that specific customer, and includes the customer name, address, and 
account number and the quantity, characteristics, or time of consumption by the 
customer, and also includes specific customer payment, financial, banking, and credit 
information. Further, Aggregators must only use Individual Customer Data for the 
Program’s primary purpose, which may include 1) providing or billing for electric 
service, 2) meeting electric system, electric grid, or other operational needs, and 3) 
researching, developing and implementing new rate structures or demand response, 
customer assistance, energy management or energy efficiency programs. The 
Municipality’s Community Power Consultant hasaggregation consultants, Good 
Energy and Standard Power, have developed this Data Protection Plan to  ensure that 
Individual Customer Data obtained as part of operation of the Program will be protected 
from disclosure and/or inappropriate use. 
 
II.  
Elements of the Plan 
 
1. Access to Customer Data 
 
As part of the Program, the Community Power Consultant Good Energy, Standard 
Power, local designees of the Municipality, and competitive electricity suppliers 
(“Suppliers”) selected to provide electricity for the Program (collectively, “Data 
Administrators”) will receive access to certain information on file with a customer’s 
local distribution company (“LDC” or “electric distribution utility”), including, among 
other things, the customer’s name, mailing address, and energy usage history 
(“Customer Data”). In particular, depending on the status of implementation of the 
Program, LDC’s may provide four types of Customer Data to Data Administrators: a) 
aggregated customer data, b) eligible customer data, c) retail electric customer contact 
information, and d) enrolled customer information. Each type of Customer Data is 
described more fully below.  
 
Page 176 of 210

City of Keene                                                                                  Community Power Plan - Exhibit III 
 
 
 
 
August 5, 2026February 10, 2025      
 
 
 
 
               43 
 
 
a. Aggregated Customer Data – contains certain information for all electric 
customers within a municipality, aggregated by rate class or other grouping. This 
may include data such as the number of customers by rate class, counts of 
customers participating in net energy metering by rate class, counts of customers 
participating in electric assistance program by rate class, the aggregated energy 
(kWh) for electricity consumption by month for the past 12 months or more by 
rate class, and revenue, receipts and past-due accounts receivable.  
 
b.  Eligible Customer Data – contains certain information for each electricity 
customer currently receiving utility-provided default service within a 
municipality. This may include data such as capacity tags for current, prior and 
next power years, energy (kWh) for electricity consumption for the past 12 
months or more, meter reading cycle, whether customer net meters and under 
which terms, and group net metering data including whether customer is a group 
net metering host or member of a net metering group, whether a group net 
metering customer-generator operates as a low-moderate income community 
solar project, the size of any such net metered generation and the year and month 
it was placed into service.   
 
c. Retail Electric Customer Contact Information – comprises certain customer 
contact information for the provision of Program communications, such as 
Customer Notification Letters to retail electric  customers. This may include such 
data as the customer of record’s name, mailing address, account number, meter 
number, rate class, and email address.  
 
d.  Enrolled Customer Data – contains certain information for all individual 
customers who elected not to opt-out of the Program during the opt-out period. 
This may include such data as Name of customer and customer contact, Mailing 
address, Service address, Account number and related meter numbers, Name key, 
Contact information such as phone numbers, email address, Billing account 
number, Preferred billing and communication method, Billing cycle, Meter read 
date or cycle, Form or type of meter reading, Capacity tag information for past 
two years, current power year and forecasted next power year, Most recent 24 
months of usage data, Current and historic status of net metering, distributed 
generation, Preferred billing and communication method, payment plans and 
electric assistance program participation, and Rate class. 
 
 
2. Data Security 
 
All Customer Data that is not anonymized (i.e. presented or aggregated in such a way 
that removes information that can be used to identify the individual customer that it 
Page 177 of 210

City of Keene                                                                                  Community Power Plan - Exhibit III 
 
 
 
 
August 5, 2026February 10, 2025      
 
 
 
 
               44 
 
 
pertains to, such that it does not constitute individual customer data as defined by RSA 
363:37, I or PUC 2002.09) shall be considered Individual Customer Data. 
 
Data Administrators will utilize industry standard physical, technical, and 
administrative controls and procedures to safeguard Individual Customer Data 
collected as part of the Program and to prevent unauthorized or accidental access, 
destruction, loss, alteration, or disclosure of, to protect against anticipated threats or 
hazards to the security, confidentiality, or integrity of, and to permit only the 
appropriate use of, such customer information. 
 
To protect the confidentiality, integrity, and availability of Individual Customer Data, 
Data Administrators will utilize a variety of industry standard physical and logical 
access controls, firewalls, password protections, intrusion detection/prevention 
systems, network and database monitoring, and backup systems. These systems will 
be designed to cover all networks, servers, computers, notebooks, laptops, PDAs, 
mobile phones, or other devices that contain Individual Customer Data, or through 
which Individual Customer Data is made available.  
 
Data Administrators will limit access to Individual Customer Data to those persons 
and entities having a specific business purpose for maintaining and processing such 
information. Those granted access to Individual Customer Data will be trained on their 
responsibilities to protect the confidentiality, integrity, and availability of such 
information. 
 
Data Administrators will work cooperatively with the LDC(s), as necessary, to 
implement this Data Protection Plan, and will at a minimum, implement the following 
actions: 
 
a. Conduct a risk assessment to identify and assess reasonably foreseeable 
internal and external risks to the security, confidentiality, and integrity of 
electronic, paper, and other records containing Individual Customer Data and 
evaluate and improve, where necessary, the effectiveness of their safeguards 
for limiting those internal and external risks; 
b. Timely notify the LDC(s) of any important modifications of this Data 
Protection Plan within a reasonable amount of time; 
c. Review and, as appropriate, revise this Data Protection Plan: (i) at least 
annually or whenever there is a material change in their business practices that 
may reasonably affect the security or integrity of Customer Data; (ii) in 
accordance with prevailing industry practices and applicable law; and (iii) as 
reasonably requested by the LDC(s). If the Data Administrators modify this 
Data Protection Plan following such a review, the Data Administrators will 
promptly notify the LDC(s) of such modifications and will provide the 
Page 178 of 210

City of Keene                                                                                  Community Power Plan - Exhibit III 
 
 
 
 
August 5, 2026February 10, 2025      
 
 
 
 
               45 
 
 
modifications to the LDC(s) in writing upon a LDC’s request. The Data 
Administrators will at no time alter or modify this Data Protection Plan in such 
a way that will weaken or compromise the confidentiality, security, or integrity 
of Individual Customer Data; 
d. Maintain and enforce this Data Protection Plan in all locations where 
Individual Customer Data is processed by the Data Administrators; 
e. Conduct security testing using a third party to provide monitoring penetration 
and intrusion testing with respect to Data Administrators systems and promptly 
provide a copy of the results to the LDC(s), provided that the third party may 
redact IP addresses and other client names and information; 
f. Provide annual security awareness training to all individuals having access to 
Individual Customer Data and maintain a record of such training; and 
g. Implement a standard process for identifying, assessing, and mitigating 
security risks. 
 
3. Confidentiality 
 
Data Administrators will not sell Individual Customer Data to others unless such sale 
is specifically authorized by the customer, or is required by law or court order. Data 
Administrators will not share, disclose, or provide Individual Customer Data to others, 
including their affiliates, unless such disclosure, or provision is required to operate the 
Program (i.e., the Program’s “primary purpose”, per RSA 363:38), is specifically 
authorized by the customer, or is required by law or court order. If Data Administrators 
request customer authorization to disclose Individual Customer Data, Data 
Administrators will first describe to the customer the information they intend to release 
and provide details concerning the recipient of such information. 
 
Data Administrators will hold all Customer Data in strict confidence and except as 
otherwise needed for provision of the Program, required by law, or permitted as below, 
(a) not disclose Individual Customer Data to any other person or entity (including but 
not limited to Suppliers, subcontractors, and affiliates or members of the Community 
Power Consultant Good Energy and Standard Power); (b) not process Individual 
Customer Data outside of the United States; (c) not process Individual Customer Data 
other than in connection with the Program; (d) not process Individual Customer Data 
for any marketing purposes other than in connection with the Program; (e) limit 
reproduction of Individual Customer Data to the extent required for the Program; (f) 
store Individual Customer Data in a secure fashion at a secure location in the United 
States that is not accessible to any person or entity not authorized to receive the 
Individual Customer Data; and (g) otherwise use at least the same degree of care to 
avoid publication or dissemination of the Individual Customer Data as Data 
Administrators employ (or would employ) with respect to their own confidential 
Page 179 of 210

City of Keene                                                                                  Community Power Plan - Exhibit III 
 
 
 
 
August 5, 2026February 10, 2025      
 
 
 
 
               46 
 
 
information that they do not (or would not) desire to have published or disseminated, 
but in no event less than reasonable care.  
 
4. Disclosure of Individual Customer Data 
Notwithstanding the provisions of Section 3 above, the Data Administrators may 
disclose Individual Customer Data to their representatives who have a legitimate need 
to know or use such Individual Customer Data for the sole and limited purposes of 
administering and/or conducting the Program. Such representatives will first be advised 
of the sensitive and confidential nature of such Individual Customer Data and agree to 
comply with the provisions of this Data Protection Plan. Pursuant to PUC 200.19, Data 
Administrators may also provide Individual Customer Data to third parties for the 
purposes of 1) billing for electric service, 2) meeting electric system, electric grid, or 
other operational needs, and 3) implementing demand response, customer assistance, 
energy management or energy efficiency programs. Any such third parties will be 
required by contract to comply with the provisions of this Data Protection Plan. 
In the event that Data Administrators or any of their representatives receive notice that 
they have, will, or may become compelled, pursuant to applicable law or regulation or 
legal process, to disclose any Individual Customer Data (whether by receipt of oral 
questions, interrogatories, requests for information or documents in legal proceedings, 
subpoenas, civil investigative demands, other similar processes or otherwise), Data 
Administrators will, except to the extent prohibited by law, immediately notify the 
LDC(s), orally and in writing, of the pending or threatened compulsion. To the extent 
lawfully allowable, the LDC(s) will have the right to consult with the Data 
Administrators and the parties will cooperate, in advance of any disclosure, to 
undertake any lawfully permissible steps to reduce and/or minimize the extent of 
Individual Customer Data that must be disclosed. The LDC(s) will also have the right 
to seek an appropriate protective order or other remedy reducing and/or minimizing the 
extent of Individual Customer Data that must be disclosed.  
Data Administrators and their representatives will disclose only such Individual  
Customer Data which they are advised by legal counsel that they are legally required 
to disclose in order to comply with such applicable law or regulation or legal process 
(as such may be affected by any protective order or other remedy obtained by LDC) 
and Data Administrators and their representatives will use all reasonable efforts to 
ensure that all Individual Customer Data that is so disclosed will be accorded 
confidential treatment. 
 
5. Return/Destruction of Individual Customer Data 
 
Upon the expiration of the Program, or as otherwise required by law or Commission 
order, the Data Administrators will destroy all copies of any Individual Customer Data 
Page 180 of 210

City of Keene                                                                                  Community Power Plan - Exhibit III 
 
 
 
 
August 5, 2026February 10, 2025      
 
 
 
 
               47 
 
 
(including any and all extracts, compilations, studies or other documents based upon, 
derived from or containing Individual Customer Data) within their or their 
representatives’ possession (including destroying Individual Customer Data from all 
systems, records, archives and backups), and all subsequent use and processing of the 
Individual Customer Data by the Data Administrators and their representatives will 
cease.  
 
Notwithstanding the foregoing, the Data Administrators and their representatives will 
not erase Individual Customer Data contained in an archived computer system backup 
maintained in accordance with their respective security or disaster recovery procedures. 
The Data Administrators will not provide access to or recovery of Individual Customer 
Data from such computer backup system and will keep all such Individual Customer 
Data confidential in accordance with this Data Protection Plan. 
 
6. Data Security Incidents 
 
The Data Administrators are responsible for any and all security incidents involving 
Individual Customer Data that is processed as part of the Program. The Data 
Administrators will notify the LDC(s) in writing immediately (and in any event within 
twenty-four (24) hours) whenever the Data Administrators reasonably believe that there 
has been a data security incident involving Individual Customer Data. After providing 
such notice, the Data Administrators will investigate the incident, and immediately take 
all necessary steps to eliminate or contain any exposure of Individual Customer Data. 
The Data Administrators will provide the LDC(s) with reasonable assistance and 
cooperation in the furtherance of any correction, remediation, or investigation of any 
such data security incidents and/or the mitigation of any damage, including any 
notification required by law or that LDC(s) may determine appropriate to send to 
individuals impacted or potentially impacted by such data security incident(s), and/or 
the provision of any credit reporting service required by law or that LDC(s) deems 
appropriate to provide to such individuals.  
 
Unless required by law, the Data Administrators will not notify any individual or any 
third party other than law enforcement of any potential data security incidents involving 
Individual Customer Data without first consulting with, and obtaining the permission 
of, the LDC(s). Within 30 days of identifying or being informed of a data security 
incident, the Data Administrators will develop and execute a plan, with the cooperation 
of the LDC(s), which reduces the likelihood of a recurrence of such data security 
incident(s). 
 
7. Additional Protections 
 
Page 181 of 210

City of Keene                                                                                  Community Power Plan - Exhibit III 
 
 
 
 
August 5, 2026February 10, 2025      
 
 
 
 
               48 
 
 
The Data Administrators will comply with all applicable privacy and security laws to 
which it is subject, including this Data Protection Plan. 
 
The Data Administrators will safely secure and/or encrypt all Individual Customer 
Data during storage and transmission. 
 
The Data Administrators will have in place appropriate and reasonable processes and 
systems, including this Data Protection Plan, to protect the security of Individual 
Customer Data and to prevent a data security incident, including, without limitation, a 
breach resulting from or arising out of the Data Administrators’ internal use, 
processing, or other transmission of Individual Customer Data, whether between or 
among their representatives, subsidiaries and affiliates, or any other person or entity 
acting on behalf of the Data Administrators. 
 
The Data Administrators will work cooperatively with the LDC(s) to implement this 
Data Protection Plan, including: establishing policies and procedures to provide 
reasonable and prompt assistance to LDC(s) in responding to any and all requests, 
complaints, or other communications received from any individual who is or may be 
the subject of a data security incident involving Customer Data to the extent such 
request, complaint or other communication relates to the Data Administrators’ 
processing of such individual’s Individual Customer Data; and establishing policies 
and procedures to provide all reasonable and prompt assistance to LDC(s) in 
responding to any and all requests, complaints, or other communications received from 
any individual, government, government agency, regulatory authority, or other entity 
that is or may have an interest in the Individual Customer Data, data theft or other 
unauthorized release of Individual Customer Data, disclosure of Individual Customer 
Data, or misuse of Individual Customer Data to the extent such request, complaint or 
other communication relates to Data Administrators’ processing of such individual’s 
Individual Customer Data. 
 
8. Use of Individual Customer Data 
 
The Data Administrators will only use Individual Customer Data for the primary 
purposes, as defined in RSA 363:37, which may include 1) providing or billing for 
electric service, 2) meeting electric system, electric grid, or other operational needs, and 
3) researching, developing and implementing new rate structures or demand response, 
customer assistance, energy management or energy efficiency programs. 
 
II. 
Conclusion 
 
The Data Protection Plan meets all of the requirements of RSA 363:38, RSA 363:37 
and PUC 2004.19.  
Page 182 of 210

City of Keene                                                                                  Community Power Plan - Exhibit III 
 
 
 
 
August 5, 2026February 10, 2025      
 
 
 
 
               49 
 
 
      
 
 
Page 183 of 210

 
2026-429 
 
 
CITY OF KEENE 
NEW HAMPSHIRE 
 
ITEM #G.1. 
 
  
   
Meeting Date: 
September 17, 2026 
  
  
To: 
Mayor and Keene City Council 
  
  
From: 
Megan Fortson, Planner 
  
  
Through: 
Mari Brunner, Senior Planner 
Paul Andrus, Community Development Director 
  
  
  
 
Subject: 
Proposed Amendments to the Keene Community Power Program — 
Energy & Climate Committee 
  
  
 
  
Recommendation: 
A motion by Dr. Koning for the Energy and Climate Committee to support the changes to the 
Community Power Program was duly seconded by Ms. Maxfield.  
 
The motion for the Energy and Climate Committee to support the changes to the Community Power 
Program carried unanimously on a roll call vote. 
  
Attachments: 
None  
  
Background: 
At their meeting on August 26, 2026, the Energy & Climate Committee (ECC) discussed a potential 
update to the Keene Community Power Program. The update would allow for customers qualifying 
for the Electric Assistance Program (EAP) to be automatically enrolled in the lowest-cost option 
offered through the Keene Community Power Program, called Keene Basic. Included below is an 
excerpt from the draft minutes of this meeting. At the conclusion of their discussion, the ECC voted 
unanimously to support the changes to the Community Power Plan. 
 
3. Community Power Update – Implementing Keene Basic Default for Low Income Customers 
 
Ms. Fortson explained that Senior Planner Mari Brunner had been speaking with Good Energy about 
creating a new lower default option for people receiving assistance from Eversource; they would be 
automatically enrolled into it. That would require the City to create an updated Community Power 
Plan, which would have to be approved by City Council. She also thought it had to be approved by 
the New Hampshire Public Utilities Commission. She said this is something that would cross 
Committee members’ desks in the future. She called the automatic enrollment exciting. She was 
unsure whether it would be people already on Community Power or only those newly enrolled. Ms. 
Fortson recalled the Allison McNeill from Good Energy mentioning this during the July 22nd ECC 
Page 184 of 210

 
2026-429 
 
meeting and said it was happening a little sooner than she expected but it would be great. 
 
Mr. Pipp noted that Keene Community Power has Keene Basic, Keene 10, Keene Standard, and 
Keene 100 as options. He asked about the base amount of renewable energy included in each 
option. Discussion ensued. 
 
Ms. Brunner arrived at 4:49 PM. 
 
Ms. Brunner said this would be for anybody who is on the New Hampshire Electric Assistance 
Program (EAP). The City had already confirmed with Direct Energy that they have the data they need 
to auto-enroll those customers into the basic option. Moving forward, when there is a sweep or new 
pricing rollout, those customers would be automatically enrolled in the lowest cost option unless they 
opt for a different option or want to opt out. For right now, anybody that is already elected to go to 
Keene 100 would stay on that. If they are currently on Keene 50, they will go down to the Basic. If 
they had chosen Keene 10, they would stay on Keene 10. Ms. Brunner had posted the plan on 
KeeneCommunityPower.com. Changes to the plan are on pages five and six under the “Equitable 
Treatment” section, which would be modified to state that the City would be distinguishing between 
customers that participate in the EAP and others. Other changes proposed to the plan include, 
instead of specifying a specific company as the community power consultant, just saying “community 
power consultants.” The other change proposed is under the “Historical Overview” section to include 
changes in liability. Ms. Brunner hoped for a recommendation from the Committee to the City Council 
on whether the ECC, as the advisory committee for the Community Power Program, supports this 
change. 
 
A motion by Dr. Koning for the Energy and Climate Committee to support the changes to the 
Community Power Program was duly seconded by Ms. Maxfield.  
 
Ms. Maxfield asked if the Keene Basic would include 35% renewable. Ms. Brunner said Keene Basic 
would remain 25% renewable energy as mandated by the state and Keene 10 would remain the 
option with 35% renewable energy included. 
 
Discussion ensued about whether the consultant had the necessary data to ensure that any new 
customer enrolled into the Community Power Program that is also part of the EAP would be 
automatically put into the Keene Basic option. Ms. Brunner was unsure this could be done 
retroactively for other EAP customers already part of the Community Power Program. 
 
Ms. Brunner said that the current Community Power contract will be in place through 2027 and then 
they would negotiate new pricing. 
 
Councilor Lake recalled discussions on the Council floor where there had been a lot of debate about 
costs, especially related to low-income households. He was trying to balance that against the goal of 
trying to have 100% renewable energy. He said this change technically fits with the goal of trying to 
get to 100% renewables, so he was in support of it. He wanted to make sure it would be financially 
responsible at the same time.  
 
Ms. Maxfield said it would only be 300 people out of 12,000 program participants qualify for the EAP, 
so the potential impact to the 100% renewable energy goal would be very low.  
 
Chair Leversee said the other big variable there is what the electricity rates are for renewals. So, if 
Page 185 of 210

 
2026-429 
 
rates go down, then all the goals line up. He said we would have to see as the contracts come 
forward too. Mr. Pipp wondered through Councilor Lake if there would be the possibility for some sort 
of fund through Eversource or Southwestern Community Services to get assistance paying for a 
percentage of renewable energy. He said right now it is nine-tenths of a cent to go from basic to 50% 
renewable; he said the marginal cost is not that big to bump people up. He did not know if there 
would be a way to tweak the financial support through other resources and community services to 
help cover that. Ms. Brunner replied that the concept was discussed when this program was originally 
being developed and a part of the confusion around the naming of the various options is that initially 
the Keene 100 option was going to be 100% additional renewable energy, so customers who chose 
that option would actually be choosing to purchase more RECs (renewable energy credits) than 
needed to cover their energy usage, so that it would offset the customers who cannot afford that. She 
said that is something they could look at again in the future. She said she would be hesitant to try 
and change any of those fuel assistance programs because they are so heavily regulated already 
that adding any other variables into the mix could make it unfeasible to work. 
 
The motion for the Energy and Climate Committee to support the changes to the Community Power 
Program carried unanimously on a roll call vote.  
 
Ms. Fortson confirmed that Ms. Brunner did not need a letter from the Chair for City Council. Ms. 
Brunner said she would just need a report from the ECC which she would create from the discussion 
in the minutes. This would go to City Council on September 17, 2026 and to the Council’s Finance, 
Organization and Personnel (FOP) Committee after that. Members of the Committee were 
encouraged to come and speak to this item at the FOP Committee meeting on the fourth Thursday of 
September. Ms. Fortson said she would send out the red-lined version of the Community Power 
Program’s proposed changes via email." 
 
Page 186 of 210

 
2026-317 
 
 
CITY OF KEENE 
NEW HAMPSHIRE 
 
ITEM #H.1. 
 
  
   
Meeting Date: 
September 17, 2026 
  
  
To: 
Mayor and Keene City Council 
  
  
From: 
Planning, Licenses and Development Committee, Standing Committee 
  
  
Through: 
  
  
  
 
Subject: 
Councilor Williams – Request to Consider Restricting the Sale of 7-
Hydroxymitragynine (7-OH) and Concentrated Kratom Products 
  
  
 
  
Recommendation: 
On a vote of 5 to 0, the Planning, Licenses and Development Committee recommends placing 
Councilor Williams’ Request to Consider Restricting the Sale of 7-Hydroxymitragynine (7-OH) and 
Concentrated Kratom Products on More Time. 
  
Attachments: 
None  
  
Background: 
Chair Filiault requested opening comments from the petitioner, Councilor Bobby Williams. Councilor 
Williams noted this was about a letter he wrote to the Council in July 2026, specifically concerned 
about a product called 7-Hydroxymitragynine (7-OH) and a number of related products that are quite 
similar, such as a Kratom product that he knew the Committee would hear a presentation about this 
evening. Councilor Williams said this is a very similar product to an opioid, and it is being sold over 
the counter in gas stations and convenience stores all over the City, which has not changed since the 
July meeting. He knew there had been some developments at the federal level since July but said 
that effort seemed to be moving a little slower than he thought it might. 
 
Chair Filiault noted that he had spoken with the City Attorney about this because it would involve 
legalities, so he asked the City Attorney to address what could be done about this at the City Council 
level, so they would not find themselves in a legal quagmire. City Attorney Amanda Palmeira spoke 
about the concept of preemption. As Councilor Williams mentioned, there is federal regulation in the 
works at this time. The most recent update from Deputy City Attorney Brandon Latham was that the 
Drug Enforcement Administration (DEA), the week before this meeting, added three 7-OH products 
to the Schedule I Federal Controlled Substances. So, three products are already federally prohibited. 
City Attorney Palmeira said there would always be some weird ambiguity between what is preempted 
federally under the Controlled Substances Act and what the City can regulate: marijuana is a good 
example of how states have handled that differently. She said that for the City to determine exactly 
what the federal government has regulated and where there are gaps that we could regulate, it takes 
a lot of research. She noted that other towns in New Hampshire had started regulating this product 
Page 187 of 210

 
2026-317 
 
and as far as she knew, there had not been any activity by the federal or state governments to 
invalidate those. She said it is one of those situations that does appear as though the City could give 
it a good shot. It is not something she would always say: “It looks like it is preempted, go for it.” Yet, 
given that other towns were doing it and the feds were moving on it very slowly in small portions, she 
said there would probably be some room to more broadly address it locally. So, Chair Filiault said the 
City would not be creating precedents; this has already been tried in other areas and upheld to this 
point. City Attorney Palmeira said she did not know that they had necessarily been challenged yet, so 
those in other areas were still on the books. 
 
Councilor Haas asked the City Attorney if she had information on how enforcement was going in 
other New Hampshire towns: were they enforcing it or just considering it a guideline? The City 
Attorney did not have information on that. She also did not know given the DEA was adding the three 
7-OH substances to Schedule I to be federally prohibited throughout the country. 
 
City Manager Elizabeth Ferland recalled when the City of Franklin put a similar ordinance in place for 
“Spice.” They ultimately had to change that ordinance several times as the formula for that drug 
changed. Their prevention coalition worked with all the local stores. Once the ordinance was 
adopted, the organization provided preventative information to the stores, letting them know it is no 
longer something they can sell. She thought it was pretty effective once those ordinances were 
adopted and most places complied. 
 
Chair Filiault recognized Dr. John Curtis, who indicated he is an Emergency Room Doctor with a 
background in emergency medicine and medical toxicology. Dr. Curtis noted that he knew a little bit 
about this topic, but it had not been a great focus of his own work. 
 
Dr. Curtis explained Kratom. Mitragyna speciosa is a Southeast Asian tree, which can get to be about 
70 to 80 feet tall at full maturity. It has been used for several centuries. The raw leaf or tea products 
are often chewed to give energy and relieve pain for workers. It is also used recreationally. “Kratom” 
refers to the tree or any products derived from the leaves of that tree. 
 
Dr. Curtis talked about Kratom pharmacology. The active components are chemicals called alkaloids. 
The most studied and prominent one in the leaf is “Mitragynine.” 7-OH Mitragynine is naturally 
occurring. It is probably well under 2% of the naturally occurring alkaloids in the leaf, although that 
changes during the life cycle. The more mature the plant is, the more 7-OH there is in it, but it is still 
generally a small percentage of the naturally occurring alkaloids in the leaf. 7-OH is also produced in 
the body as a metabolite of the primary alkaloid, which is the Mitragynine. 7-OH is an agonist at the 
opioid receptors. It is probably more of a partial agonist similar to buprenorphine or Suboxone. So, it 
does activate those receptors and produces opioid-like effects. However, it is not the only active 
compound in the naturally occurring leaf. 
 
Next, Dr. Curtis described Kratom effects. There are multiple neurologic systems that seem to be 
affected by this mixture of alkaloids. It works on serotonin syndrome, similar to LSD and 
antidepressants. It is active in noradrenergic receptors; that is the kind of thing responsible for your 
fight or flight response and that is also responsible for the mild stimulant effects that this can have, as 
well as the opioid effects. Dr. Curtis stated conventional wisdom is that low doses are more apt to 
produce mild stimulant effects and energy concentration, allowing one to maybe work longer or 
harder, or focus a little bit more. Whereas the higher doses tend to be the ones that cause relaxation, 
sedation, promote sleep, and offer some pain relief. He said it is seen used sometimes for pain relief 
and sometimes for its psychoactive effects. There is also a population that tends to use it to ease 
Page 188 of 210

 
2026-317 
 
opioid withdrawal effects because of the at least partial activation of opioid receptors. He stated that 
a lot of the early interest in this substance in this country was with people trying to wean themselves 
off opioids and ease those withdrawal effects. 
 
Dr. Curtis explained that Kratom is available in a variety of formulations. You can eat the raw plant 
matter by chewing the leaves; they are often dried and powdered, and in some cases fermented and 
placed in capsules. It is available as a ground leaf to make tea and a ground leaf in capsules to 
ingest without having to taste it, since most of these alkaloids are somewhat bitter. It is offered in a 
powder that is designed to be mixed into food or beverages. There are also extracts either in alcohol 
as a solvent that are sometimes used to absorb from the mucosal tissues in the mouth and placed 
under the tongue for rapid effects. 
 
Dr. Curtis also discussed concentrates and synthetics: There are also synthetic forms of this 
chemically produced 7-OH. There are a variety of these on the market and that is what has caused 
most of the controversy. Whereas the natural leaf will contain a small amount of this substance and 
the body will change some of the alkaloids into 7-OH, that is a fairly slow process, so it is hard to get 
a lot of opioid stimulation at once and the effects typically last five to eight hours after ingestion. He 
said the 7-OH opioid agonist is very gradually produced, so you do not really see with natural 
products a lot of the consequences that are sometimes seen with opioids in terms of respiratory 
suppression. Although in a lab setting, 7-OH has produced respiratory depression that can be 
reversed by opioid antagonists like Narcan. 
 
Dr. Curtis talked about the legalities of Kratom. He reiterated news about rescheduling some of these 
substances the week prior. He said in general, until very recently, there was no federal regulation on 
this. Various states have different regulations, some of which involve just concentrates and 7-OH 
products, some of which involve everything, and some of which are just age restrictions. He showed 
a map of the United States as of July 2026, which showed where 7-OH products were banned, illegal 
but leaf products are legal, and the Kratom Consumer Protection Act legal area. There are various 
regulations that vary state to state and even within states. When talking about local ordinances that 
change what can be sold, he said this is not common, but it is not rare either. A national survey in 
2021 for teens and adults showed less than 1% or 1.5 million or more people who reported using 
kratom in the last year. He called that a fair number of people and was sure those numbers had only 
increased in the past five years. 
 
Dr. Curtis discussed the potential harm of 7-OH/Kratom. Like for many herbal products, regulation 
and testing is not mandatory, although good producers will often have third party labs certified. 
However, there have been cases of heavy metal contamination that is often reported by suppliers. 
There has been bacterial contamination of products, so that is a common concern with many 
supplements and herbal products. But in terms of the Kratom itself, he cited nausea and GI side 
effects as the most common and noted that both diarrhea and constipation have been reported. 
Dizziness or drowsiness occur, particularly at high doses. Occasionally also, again with high doses, 
more serious things such as seizures have been reported, as well as confusion, high blood pressure, 
and low heart rate. There have been liver problems reported with Kratom use; it is not clear exactly 
who develops that but it is generally associated with high dose, long term use; it is not a universal 
effect, so it probably has something to do with the person taking it as well. He talked about lifestyle 
factors, noting that co-ingestance effects in pregnancy have not been studied and are not well 
known. In some cases, neonatal abstinence syndrome, similar to babies born to mothers who are 
opioid addicted, have been reported, but that has been rare, probably because it is both less 
common than opioid use and under recognized. Kratom is not detected on routine drug screens. It 
Page 189 of 210

 
2026-317 
 
would be possible, but it is not something that is routinely screened for. So, Dr. Curtis said that if 
someone does not tell you, there is not much way that you would know, even though mothers are 
routinely drug tested for the safety of the children. 
 
Dr. Curtis stated that Kratom is a lot less dangerous than a lot of other things that are on our streets. 
One report from about seven years ago said that over a period of about six years, 11 deaths were 
associated with it, but almost all of them were mixed exposures where it was used with other things. 
According to this article, it said two deaths were associated with Kratom exposure alone, although 
the underlying medical conditions of the user were not entirely clear. So, Dr. Curtis said that death 
from Kratom, while possible, seems to be extraordinarily rare. 
 
Chair Filiault said this was actually brought to his attention about one year prior and he commended 
Councilor Williams for bringing this forward. Chair Filiault said it was a Police Officer who kind of 
raised his alarm on this because he had been to a couple of calls on Kratom and said it created a 
violent atmosphere with people they encountered. He asked whether Dr. Curtis had seen that in the 
ER or if it is more prominent on the streets. Dr. Curtis said he had surprisingly not seen a lot of it 
compared to when K2 and Spice were common. He had not seen a lot of Kratom in the ER; he had 
seen people who say they use it, but no actual medical encounters driven by that use. He noted there 
is some sort of degree of Kratom users because there are three widely available types called white, 
green, and red; referring to the little veins in the stems on the leaves. On very immature plants, the 7-
OH in those veins and the leaves are white and they tend to have more stimulant effects and seem to 
be more dose-dependent. Whereas green is kind of a mixture. The mature leaves have these red 
veins in them, and they have the highest concentration of 7-OH; they are generally thought to be 
more relaxing, sedating. He reiterated that the white Kratom, which also varies depending on region 
of origin and methods of processing, tends to cause more powerful stimulant effects that might be 
more prone to being associated with agitation or violence. Dr. Curtis’ understanding is that the red 
vein substances are most used by those trying to get opioid-like sedative effects, but he said it was 
not something he had commonly encountered in his emergency department. 
 
Councilor Ruttle-Miller said she understood there is a difference between medical literature versus 
general news reporting and that those things can sound incredibly different. However, she said there 
seemed to be a big polarity between what Dr. Curtis was presenting as far as a concern and danger 
versus what you see when you look this up. She said it does seem like there has been a dramatic 
increase in the number of deaths or very dangerous situations. Specifically, an article in the NIH 
around poison control reports. She asked Dr. Curtis if there was more recent data or anything 
specific to New Hampshire in general that he could share. Dr. Curtis said no, he did not have 
anything specific to New Hampshire and the survey he looked at was about six years old. He said 
there had probably been much more usage recently. He thought the problems probably come from 
either the synthetic or concentrated 7-OH products, particularly if mixed with other sedatives such as 
alcohol or other opioids: that is also where we see more reports of addiction and withdrawal. He 
provided an analogy to demonstrate that taking active compounds and concentrating them will cause 
more dramatic psychoactive and health effects. 
 
Vice Chair Jones said he is a little naive about this but knew these products were readily available in 
convenience stores. Dr. Curtis said it is not hard to come by, showing a picture from a store in Keene 
the other day. It is like getting a pack of cigarettes or beer; you would probably have to prove your 
age. Vice Chair Jones said the packaging and labeling is called Kratom or 7-OH, or is it just 
branding? Dr. Curtis said most 7-OH is sold as 7-OH or Hydroxy, but it will usually specify Kratom on 
it depending on the producer. You can also order and have Kratom shipped to you but some of the 
Page 190 of 210

 
2026-317 
 
more reputable producers will have analysis of the alkaloids, results of heavy metal testing, and 
results of bacterial testing. He said most of it is labeled Kratom because that is how people who are 
looking for it know to buy it. 
 
Councilor Haas asked Dr. Curtis to speak about the addictive properties of Kratom and compare it to 
other opioids. Dr. Curtis again said it was not something he had seen clinically, but from reviewing 
internet reports and overall kind of experience with it, even the leaf product can cause some physical 
dependence with long enough use. The 7-OH products being more powerful at opioid receptors and 
getting that effect do have very similar withdrawal; some people have stated that withdrawal can last 
for weeks to months and can be difficult to wean off. He said it may be a lot harder to distance 
yourself from a product that might be at the gas station where you are getting your coffee as opposed 
to having to go seek it out from a dealer. So, Dr. Curtis stated that it does have potential to cause 
addiction, even though it is often used to ease withdrawal symptoms when someone no longer has 
access to opioids. 
 
Councilor Williams first wanted to speak to those three substances that were added to Schedule I. It 
was his understanding that those were not 7-OH, but chemicals closely related to 7-OH and perhaps 
not in wide circulation. He thought the 7-OH question was still out there. City Attorney Palmeira 
believed that was right. She noted that it was a struggle not only to read and pronounce, but to match 
what was being regulated and what was been identified in other places. She said there were a lot of 
skills there that she did not have the education for, but she did think the three that were on the 
Schedule I had been synthetic products of 7-OH. The City Attorney added that it is a temporary 
order: it is two years on Schedule I, with a one-year extension possible. 
 
Councilor Williams asked about patterns of usage: on the internet he saw people talking about 
spending $50–$100 per day and buying several at the store per time. He wondered whether that was 
common. Dr. Curtis thought it was very common to spend that much on it, noting that there is a 
tolerance that develops; some people will rotate types to avoid over tolerance. He said there is also 
patterns of usage. People may use the more stimulating products during the day to be more 
functional and use the more sedating products at night (e.g., to relax or as a sleep aid). Anything with 
addiction comes with people spending a lot of money. He explained the general internet subculture 
advice to rotate strains and take a few days off per week to avoid tolerance much like opioids, or it 
will require a larger dose to produce the desired effects and that necessarily involves spending more 
money. It was not Dr. Curtis’ impression that a lot of people were “going broke” from this but said 
there were certainly cases where that happens. 
 
Councilor Ruttle-Miller heard the doctor mention something about proving age and asked if there is 
an age associated with buying this (i.e., could a 15-year-old access it?). Dr. Curtis said in general it is 
18 years of age and over. Councilor Ruttle-Miller said there was no law. She asked if it depends on 
the store. Dr. Curtis thought it first would depend on the state: it is age restricted in many states, and 
he believed the age is usually 18 and not 21. He deferred to the City Attorney. There being no law on 
the books, Chair Filiault questioned how there could be any age restrictions. The City Attorney 
agreed, having not seen the restriction, she said there was not one. The federal restriction does not 
concern age. She speculated that the local shops have age restrictions on other things they sell, so 
they probably do it for this too, but she had not seen the restriction in the law. Dr. Curtis said it is 
often sold in smoke/vape shops, where other products are age restricted. Chair Filiault said he had 
personally gone around Keene and there are several convenience-type stores that have it on the 
market, so it is not just restricted to vape stores. 
 
Page 191 of 210

 
2026-317 
 
Councilor Haas noted that he had seen no national publications or education going on about this. He 
wondered if there should be some more movement toward educating  
the population/public about the dangers of this natural drug and synthetic drug before the Council 
tries legislating it. He said this would be worth the City’s effort and time since there had been no real 
widespread education. That came across the Councilor’s eyes with the young people in his life. 
 
Councilor Williams asked Dr. Curtis if he was aware of the Kratom and Kava combination. Dr. Curtis 
said he had heard the name. He added that both drugs are used for sedating effects, and both have 
been associated with some reports of liver injury. 
 
Chair Filiault opened the floor to public comments. 
 
At Large City Councilor Michele Chalice thanked the Committee and the Council for their time looking 
at this issue preemptively. She said it seems a shame to wait until there is severe community 
damage. She said things are moving so quickly in our society in addition to all those stressors. So, 
she really appreciated taking the time to deliberate and give some thought to this issue. 
 
Chair Filiault agreed with Councilors Williams and Haas, which put him somewhere in the middle. He 
thought he had more questions than answers that came up during the meeting. He was leaning 
toward an ordinance. However, at the same time, he wanted to personally give himself a few more 
weeks to do some more digging. He did not think he was quite ready for an ordinance yet, but he was 
leaning there. Personally, he wanted to place this matter on More Time and bring it back in a couple 
of weeks to take another hard look at it. He told Councilor Williams that he was not suggesting by any 
stretch of the imagination to dismiss this item. He thought the Committee was leaning in the same 
direction and asked to hear from them. He did not think they were ready to make a unanimous 
decision this evening. 
 
Councilor Ruttle-Miller was a little thrown off by the presentation because she spoke recently to 
somebody who works in a rehab facility and who said that they do not see a single person come 
through at this point who does not have some sort of usage (on top of anything else that they are 
also being treated for). She said it is viewed as a definite problem within their facility. So, Councilor 
Ruttle-Miller was expecting a little more based on that. She said there were no statistics, no study, 
and nothing behind the presentation other than somebody who works with folks who use these 
products regularly. She was not quite sure what she was anticipating for a presentation, but she 
came in thinking she knew what the Committee was going to hear. She tended to lean toward 
something, especially because there is no age regulation; that was what concerned her, like when 
kids started vaping a lot. Councilor Ruttle-Miller said she is always confused when she sees this 
weird herbal supplement and wonders what it is. She noted that she was a little more confused right 
now than she thought she would be. Chair Filiault agreed. 
 
Chair Filiault added that in the coming weeks he would like to go back to the Police Officers he had 
spoken with to hear from them more about what they have seen on the streets; Chair Filiault wants to 
dig a little deeper. He agreed with Councilor Ruttle-Miller that he came into the meeting thinking one 
way and now was a little bit more in the middle, leaning toward restriction, but he wanted to hear from 
more experts, including the Police Department. 
 
Councilor Haas agreed: more information is always good. As the City Manager mentioned, this would 
lead toward an education program. He was curious whether there were already education programs 
like that out there, which the City might adapt and start to roll out so people could get behind the City. 
Page 192 of 210

 
2026-317 
 
Councilor Haas said that addictive personalities tend to use whatever they can pile on, stating that he 
was generalizing, of course. He compared it to the health food industry. He said that if the City is 
going to regulate Kratom specifically, he thought they would want to have more of the public’s 
understanding of the problem and education around it. Councilor Haas leaned toward holding the 
item for a bit to see what the Committee could come up with. 
 
The City Manager noted that there is also the Monadnock Youth Coalition, which is like the 
prevention group that was in Franklin, New Hampshire. It was under the same federal grant, and the 
City Manager said she would love to hear from them and what they had seen. In addition to that, she 
mentioned Keene Youth Services, which works with a lot of youth who are sometimes getting into 
trouble with the Police and finding ways to divert them from that type of activity. The City Manager 
was sure both of those groups would be able to provide a great deal of information about what they 
are seeing in the use of Kratom and these types of products. 
 
Chair Filiault hoped Councilor Williams knew and could appreciate that nobody likes waiting when 
they want to see something go forward. Still, Chair Filiault agreed with the City Manager and did not 
want to send something to the full Council that could be kicked back to the Committee for more 
answers. Chair Filiault wanted to place this on More Time until the next PLD meeting so the 
Committee could get it right before sending it to Council. 
 
Councilor Williams did not mind taking the time to get it right. He thinks people know he is not 
necessarily a prohibitionist. He thinks the Council should be calculating and smart about these things. 
His general feeling is that it is a very bad idea to put seriously addictive substances in easy reach of 
just about anybody, including the youth. He noted the federal government may be doing something or 
not, so the City should be keeping an eye on that. Councilor Williams agreed that waiting a few 
weeks for this to be continued would not be such a bad thing. 
 
Vice Chair Jones also liked the idea of More Time. He said he favored legislation but did not think the 
Committee could ask staff to draft an ordinance without giving them some direction. He thought that 
the suggestions to hear from the Police and other experts would provide that direction. He said the 
Committee did not even know if they wanted to put an age limit on the substance, so he said they 
needed More Time, with the aim to give more direction. As far as educational awareness is 
concerned, Vice Chair Jones said sometimes legislation creates awareness. He hoped some of that 
could happen by creating legislation. 
 
The following motion by Councilor Williams was duly seconded by Councilor Haas. 
 
On a vote of 5 to 0, the Planning, Licenses and Development Committee recommends placing 
Councilor Williams’ Request to Consider Restricting the Sale of 7-Hydroxymitragynine (7-OH) and 
Concentrated Kratom Products on More Time. 
 
Councilor Haas asked if there was a means of requesting that the youth committees join the next 
meeting’s conversation. The City Manager said yes, she had already sent a message asking for that 
information and for someone to be present at the next meeting. 
 
Page 193 of 210

 
2026-372 
 
 
CITY OF KEENE 
NEW HAMPSHIRE 
 
ITEM #J.1. 
 
  
   
Meeting Date: 
September 17, 2026 
  
  
To: 
Mayor and Keene City Council 
  
  
From: 
Planning, Licenses and Development Committee, Standing Committee 
  
  
Through: 
  
  
  
 
Subject: 
Relating to Amendments to Article VII. - Food Service Establishments 
Ordinance O-2026-14 
  
  
 
  
Recommendation: 
On a vote of 5 to 0, the Planning, Licenses and Development Committee recommends the adoption 
of Ordinance O-2026-14. 
  
Attachments: 
1. 
O-2026-14_Food Service_Referral 
  
  
Background: 
Chair Filiault welcomed Compliance Inspector Ryan Lawliss (who also does Food Inspections) and 
Fire Marshal, Rick Wood. Mr. Lawliss said that before the Committee this evening was a proposal to 
remove and replace Chapter 46, Article 7, which would update the Keene Food Code from the 2009 
FDA Food Code to the 2022 FDA Food Code. The Food and Drug Administration (FDA) updates the 
Food Code periodically to reflect current food safety, science, and practices. So, this will bring the 
City in line with the balance of the rest of the state and most of the nation. No other jurisdiction in 
New Hampshire is currently operating under a version older than 2017. Mr. Lawliss made the 
Committee aware that the City had been notifying its food establishments over the last year that this 
would be coming and talking to them about what that may entail, as well as how City staff will be 
working with them once it is in passed to bring them into compliance. It will be a work in progress with 
them and not something that happens right away. Chair Filiault said this is basically just staying in 
compliance with state statute/code. Mr. Lawliss said no, Keene has authority as a self-inspecting 
municipality and adopts its own Ordinance along with 14 other municipalities. Keene would be the 
last one to do this update. Keene is just trying to be more in line with the rest of the state, so that as 
businesses and people are in town, they can understand that we are following the most current up-to-
date sciences. 
 
Councilor Haas thanked Mr. Lawliss for putting this forward and getting the City up to date on codes. 
Councilor Haas is always worried about the impact and what the issues will be with our existing food 
purveyors and restaurant/food establishments. He asked Mr. Lawliss to comment on what he had 
heard from them as far as what they would need to change or how this would impact them. Mr. 
Page 194 of 210

 
2026-372 
 
Lawliss said the food Code was from 2009, and this went into effect in 2017; this would also be seen 
in 2022 as well. It is called a Certified Food Protection Manager Requirement, which requires 
somebody to have training on certification as being able to handle food safely and to oversee the 
staff. This puts a responsibility for food safety on the management level, which helps to, rather than 
relying solely on inspectors, and inspectors being there all the time to make sure that the consistency 
of health and safety is contained throughout. While this is one of the largest changes, Mr. Lawliss 
said it would shock him to understand that a lot of even some of the smaller, locally owned 
establishments have somebody who has undergone this training. 
 
Councilor Haas said it is basically like an upgrade from ServSafe. Mr. Lawliss said ServSafe is 
basically the norm. In having owned food service establishments in the past, Chair Filiault said it was 
always upgraded year to year in most levels, so he did not think this was “inventing the new light bulb 
here.” Mr. Lawliss agreed that almost all the larger chains require all their supervisors and managers 
to do this, and a lot of the local restaurants too, like Sole Bar, where the owner is a trainer for 
ServSafe, so she offers training to staff throughout in different restaurants. Mr. Lawliss said this is 
nothing new, the City is just codifying the requirement. 
 
Councilor Haas said this requires some certified training to be acquired. He asked where this training 
would come from: does the City need to hire a professional agency to train and certify them? Mr. 
Lawliss said yes, ServSafe is one of the most common examples that is done online. The one the 
City is looking into is making sure they are certified. He said a lot of people with 20 years of 
experience could probably go take that test tomorrow and pass it without any issues. It is online and 
not overly burdensome. Councilor Haas asked if there is a cost associated with the training and 
certification. Mr. Lawliss thought it was a couple of hundred dollars. Councilor Haas asked how many 
years the certification is good for, and Mr. Lawliss said five years. Councilor Haas asked if any Keene 
food establishments already have this on their own. Mr. Lawliss said yes, most do; certainly, the 
chain restaurants or establishments that are franchises and other local places like Sole and Grenada. 
The City would work with the smaller establishments case-by-case to connect them with the 
resources and get them on track. Councilor Haas noted the City has a lot of smaller establishments 
in the downtown, so he would be looking to hear information back from the food purveyors. 
 
Fire Marshal Rick Wood pointed out that the enactment of this is planned for after the City’s current 
food license renewal. So, the goal is to get this enacted post-September 30, 2026, because that is 
when the City’s food licenses are renewed. That means that everybody is going to have one year 
before any of the changes really hit from that training perspective because they are already licensed. 
So, there is that one-year working period as well as the fact that some of the fee adjustments are 
going to be one year out. Fire Marshal Wood thought that was helpful to understand the context of 
implementation. 
 
Councilor Haas was a little disappointed that there was no representation from our food industry here 
to speak as to how well they can take this on or adapt it / comply with it. He asked what kind of 
communications have gone out to them about this happening. Mr. Lawliss said a lot of the new 
restaurants that came to town from Manchester or out-of-state on Main Street in the past year were 
shocked to learn that they did not have to provide certification. He said it is common practice to have 
to provide that information. He said when vendors for festivals come from out-of-state, they send him 
certifications out of habit. So, Mr. Lawliss thought this would bring the City more in line with what is a 
custom for many. He was sure there were a few they would have to work with more and staff would 
work with those establishments as they do all the time. 
 
Page 195 of 210

 
2026-372 
 
Fire Marshal Wood asked if this affects all classes of food licenses. Mr. Lawliss said there are some 
exceptions. It is based on risk. For example, a convenience store that has all prepackaged food and 
items would not be required to have this type of certification. 
 
Chair Filiault knew there were two variations: ServSafe Food and ServSafe Alcohol. He asked 
whether ServSafe Alcohol would be included in this. Mr. Lawliss said this is ServSafe Manager 
Training. 
 
Councilor Ruttle-Miller said she had experience in the restaurant industry, having spent several years 
serving and bartending, and as a consumer. She said she has no qualms with requiring additional 
safety certifications because she had worked in both places that do follow ServSafe and places that 
do not. She said she had experienced a variety of people willing to follow those rules regardless, and 
consumers always just have to kind of make choices for themselves where to go. Councilor Ruttle-
Miller said that it is not like multiple weeks of training and multiple thousands of dollars of 
investments. She did understand for smaller establishments that these are higher hoops to jump 
through. However, she thinks that making sure your staff is certified and knows how to properly 
handle food in a safe manner is an important component in owning an establishment. Fire Marshal 
Wood noted that not all staff have to be certified. There must be one person who is a Certified Food 
Safety Manager when the business is open, which he called an important delineation. Chair Filiault 
said hopefully everybody is trained by that manager. 
 
Councilor Haas said he was troubled that this was all new to him due to his own ignorance of the 
topic. So, he thanked the presenters for the update. However, without hearing the acceptance of this 
from the food service community, Councilor Haas said he was troubled with it. He said it appeared 
like another change that the City is just putting out that the stakeholders have not had a chance to 
react to. He could imagine hearing from them later about having to do a $200 training session when 
their margins are so thin; they may feel like the City is pressing them again. So, Councilor Haas said 
he was uncomfortable with this on that basis. He said it would have been great if staff had brough 
several restaurant owners to the meeting to speak about how great it is and how happy they are with 
it making their businesses better because they can put the decal in their front window. Chair Filiault 
said he would be interested in that feedback also and to hear someone say why they are not 
ServSafe. Fire Marshal Wood said another thing to realize was that staff had been talking about this 
with those restaurants for about one year as they had been working through this process; this is not 
something that had just started within the past few months. Staff had been having those 
conversations and checking to see who has credentials. Most places have Time Temperature 
Controlled Foods (TCS), so they have somebody already. Fire Marshal Wood said there are very few 
in that category who do not have somebody. Chair Filiault added that they would not have to do this 
by September 30, 2026, they would need to get their licenses by September 30 and then have one 
year to comply. 
 
City Manager Elizabeth Ferland added that it was important to remember that by adopting this, the 
City would still be behind. This is based off the 2022 FDA model food Code, which updates every five 
years. The City Manager said she thought this update is very much needed; it might have been 
needed a few years ago. It took the City a long time to get here and she did not think it would be a 
big lift for most organizations. 
 
Chair Filiault opened the floor to public comments. 
 
Councilor Laura Tobin (of Center Street) said she had worked at a food establishment and ate at 
Page 196 of 210

 
2026-372 
 
plenty in Keene. She has had food poisoning multiple times from restaurants outside of Keene. 
Councilor Tobin said she would feel very uncomfortable if the City did not make food as safe as 
possible for people to consume. She understood that there may be effort on behalf of some of the 
food establishments. However, to Councilor Tobin, this is just protecting the people who live here. 
 
The following motion by Councilor Williams was duly seconded by Vice Chair Jones. 
 
On a vote of 5 to 0, the Planning, Licenses and Development Committee recommends the adoption 
of Ordinance O-2026-14. 
 
Page 197 of 210

ORDINANCE 
O-2026-14 
CITY  OF  KEENE 
 
 
 
In the Year of Our Lord Two Thousand and              Twenty Six 
 
AN ORDINANCE    Relating to an Amendment to Article VII. - Food Service Establishments 
 
Be it ordained by the City Council of the City of Keene, as follows:  
That the Code of Ordinances of the City of Keene, New Hampshire, as amended, is hereby further 
amended by deleting in its entirety Article VII. “Food Service Establishments” and inserting in its place a 
new Article VII.; and, by updating Appendix B. “Fee Schedule” as follows: 
 
ARTICLE VII. - FOOD SERVICE ESTABLISHMENTS[6] 
State Law reference— Food service licensure, RSA 143-A:1 et seq. 
DIVISION 1. - GENERALLY 
Sec. 46-361. - Definitions. 
See He-P2301.01 for definitions. 
Sec. 46-362. - Adoption of FDA Food Code and New Hampshire Rules for the Sanitary 
Production and Distribution of Food; amendments. 
(a) The City of Keene hereby adopts by reference the 2022 FDA Food Code and New Hampshire Rules 
for the Sanitary Production and Distribution of Food, He-P 2300, and any subsequent amendments 
thereto, so as to regulate food service establishments operating within its jurisdiction as of October 
1, 2026. Where there is a conflict between this chapter and the 2022 FDA Food Code and He-P 2300, 
this chapter shall govern. 
(b) Notwithstanding, the following sections of He-P 2300 shall not be adopted into the Code of the City 
of Keene: He-P 2303.01, He-P 2304.01 through He-P 2304.05, Sections: He-P 2301.01(n)(o), He-P 
2302.01, He-P 2304.12(e), He-P 2304.14(a), He-P 2306.02(a)(19), and He-P 2306.02(c)(1). 
(c)  References in He-P 2306.06(a) regarding emergency telephone numbers shall be replaced with 
"notify the Community Development Department at 603-352-5440, or if at night or during the 
weekends, at 603-357-9815 or email Health@KeeneNH.gov.” Reference in He-P 2304.14(a) shall be 
replaced with: 
Community Development Department 
City of Keene 
Attn: Food Licensing 
3 Washington St 
Keene, NH 03431 
Page 198 of 210

(d) Section He-P 2301.01(r) shall be amended to be: “Food Code” means the US Department of Health 
and Human Services, Public Health Services, Food and Drug Administration, Food Code, 2022 
edition. 
(e) Section He-P 2301.01(ba) shall be amended to be: “Soup Kitchen” means a non-profit organization 
that prepares and distributes food to members of the public without charge 
(f) References in He-P 2311.01 to “Class H” food service license shall be replaced and inserted “Class 6 
Food Service License.” 
(g) Reference to He-P 2304.01 through He-P 2304.05 in any section of He-P 2300 shall refer to Sec 46-
363 of this Article. 
(h) Wherever there is a reference to "Commissioner" in He-P 2300, it is replaced with "Health Official of 
Keene or designee." 
(i) Wherever there is a reference to "Department" in He-P 2300, it is replaced with "Community 
Development Department." 
(j) Wherever there are references to "RSA 541-A and He-C 200," they shall be replaced with the City of 
Keene Code. 
(k) Wherever there is a reference to the New Hampshire Department of Health and Human Services in 
He-P 2300, it is replaced and inserted is City of Keene. 
(l) All fines and fees shall be made payable to the City of Keene. All applications, correspondence and 
fines shall be sent to: 
Community Development Department 
City of Keene 
Attn: Food Licensing  
3 Washington St 
Keene, NH 03431 
Sec. 46-363 - License Procedure 
It shall be unlawful for any person or entity to operate a food service establishment within the City who 
does not possess a valid license issued to them by the Health Official or their designee. Only a person or 
entity who complies with the requirements of this chapter shall be entitled to receive and retain such a 
license. Licenses shall not be transferable from one person or place to another person or place. A valid 
license shall be conspicuously posted in every food service establishment.  
(a) Issuance of licenses and fees. 
(1) Any person desiring to operate a food service establishment shall make written application 
for a license on forms provided by the Health Official. Upon receipt of such an application 
and the designated license fee, and after inspection reveals that the requirements of this 
chapter have been met, a license shall be issued to the applicant by the Health Official. All 
annual licenses expire on September 30th.  The fees shall be payable to the City of Keene 
and shall be designated as follows 
(2) Processing of Initial Applications and Issuance of Licenses 
a. Each applicant for a license shall complete and submit to the department an 
application form. 
b. In addition to submitting the completed application, in (a) above, an applicant 
shall also submit the following: 
Page 199 of 210

1. Check, money order, or on-line payment by credit card; 
2. Water system documentation, in accordance with He-P 2304.06, except that 
food establishments applying to be licensed as a farm store, home delivery 
services, pushcart and other mobile units, retail markets selling only non-
Time/Temperature Control for Safety (TCS) prepackaged items, institutions 
including state, county, and municipal institutions, schools, private schools, 
and schools whose food service is operated by a caterer, and sellers of pre-
packaged frozen meat or poultry that is processed in a United States 
Department of Agriculture (USDA) plant shall not be required to submit such 
documentation;  
3. Wastewater system documentation, in accordance with He-P 2304.07, 
except, that food establishments applying to be licensed as a mobile food 
unit, farm store, home delivery services, pushcart and other mobile units, 
retail markets selling only non- Time/Temperature Control for Safety (TCS) 
prepackaged items, institutions including state, county, and municipal 
institutions, schools, private schools, and schools whose food service is 
operated by a caterer, non-exempt homestead food operations, senior meal 
sites, retail food stores with no food preparation areas, and sellers of pre-
packaged frozen meat or poultry that is processed in a United States 
Department of Agriculture (USDA) plant shall not be required to submit such 
documentation;  
4. If the application is for a mobile food unit that uses a service area, one of 
the following: 
a. A separate license application for the facility to be used as a 
servicing area; or 
b. A copy of the food establishment license, from the appropriate 
regulatory authority, of the facility being used as a servicing area. 
5. A hazard analysis and critical control point (HACCP) plan required by He-P 
2304.13; and 
6. A proposed menu or list of food and beverages is to be offered. 
c. Applicants seeking a change in license class, a new license, or a new license due to 
a change of ownership, shall contact the department to arrange for an inspection 
of the establishment no later than 30 days from the date of mailing or delivering 
the fee and application. 
(3) License Expirations and Procedures for Renewals 
a. Each licensee shall apply to renew his or her license at least 30 days prior to the 
expiration of the current license. 
b. The licensee shall submit a renewal application that includes the following: 
1. Completed Application, and  
2. A check, money order, or on-line payment by credit card.  
c. A license shall be renewed if the department determines that the licensee: 
1. Submitted an application containing all the items required by (b) above, as 
applicable, at least 30 days prior to the expiration of the current license;  
2. Submitted a Corrective Action Plan (CAP) that has been accepted by the 
department and implemented by the licensee if deficiencies were cited at 
the last licensing inspection; 
Page 200 of 210

3. Is found to be in compliance with He-P 2300 and all applicable regulations at 
a renewal inspection, as applicable; and 
4. Has paid any outstanding fees or fines in full. 
d.  If a license holder fails to submit a complete application for renewal as required 
under (a) and (b) above, the food establishment shall cease operation the day 
after the license expires and shall not operate until a license is obtained. 
e. Any food establishment wishing to submit an application for a renewal license 
whose previous license has been expired in excess of 30 days shall apply in 
accordance with the requirements of an initial license in Sec 46-363(A)(2). 
 
(b) Classification of Food Service Establishments/License Fees 
(1) Class 1A: Food Service Establishment with 200 seats or more; retail food store with 4 or more 
food prep areas 
(2) Class 1: Food Service Establishment with seating capacity 100-199 seats; food service 
establishment with extensive menus; serve raw ingredients (sushi, oysters, etc.), salad bar 
and/or food buffet; retail stores with 2 to 3 food preparation areas; nursing homes; hospitals; 
commercial food processing operations processing more than 100,000 packages of food per 
year 
(3) Class 2: Food Service Establishment with 25-99 seats; retail food store with one food prep area; 
bakeries; food distributors of Time/Temperature Control for Safety (TCS) foods; beverage 
manufacturers; commissaries; caterer; mobile food unit selling/serving Time/Temperature 
Control for Safety (TCS); commercial food processing operations processing less than 100,000 
packages of food per year  
(4) Class 3: Food Service Establishment with 0-24 seats; retail food store-self services and no food 
prep area; commercial food processing operations of non-Time/Temperature Control for Safety 
(TCS) bulk foods; bakeries which do not serve Time/Temperature Control for Safety (TCS)  food; 
non- Time/Temperature Control for Safety (TCS)  mobile food units; retail markets selling only 
prepackaged items; bed and breakfast; private clubs; mobile venders, childcare facilities serving 
Time/Temperature Control for Safety (TCS); farmers market vendor selling/serving 
Time/Temperature Control for Safety (TCS)  food; Wholesalers/distributors Time/Temperature 
Control for Safety (TCS)  food 
(5) Class 4: Temporary licenses see Sec. 46-363(e). 
(6) Class 5: Public schools; private and parochial schools; not for profit organizations not holding a 
liquor license; governmental facilities that operate more than 4 times in a 28-day period 
(7) Class 6: Sellers of prepackaged frozen USDA meat or poultry; retail markets selling only non- 
Time/Temperature Control for Safety (TCS)  prepackaged items; non-exempt homestead 
kitchens; arena/theater concessions selling/serving non- Time/Temperature Control for Safety 
(TCS)  food 
License Fees are established in accordance with the schedule of fees set forth in Appendix B of the City 
Code of Ordinances. 
The Health Official or designee has final determination of all classifications of food service 
establishments. When a food service establishment has an additional food processing business, each 
shall be licensed separately, requiring separate applications and separate fees. When a hospital or 
school offers food to the general public in addition to its population, then the license class shall be 
determined by the number of seats the food service establishment has. 
Page 201 of 210

(c) Late Fine  
(1) License Renewal Applications received after the 10th day of the month following license date of 
expiration – Fees are established in accordance with the schedule of fees set forth in Appendix B 
of the City Code of Ordinances.  
(d) Mobile food units and mobile venders 
(1) Any person desiring to operate a mobile food unit shall meet all applicable City of Keene land 
use regulations. The applicant shall also meet all Building, Health, Fire Codes as adopted by the 
City of Keene and the State of New Hampshire. 
(2) For mobile venders selling exclusively prepackaged goods, please cross-reference Hawkers, 
Peddlers. 
(e) Temporary license. 
(1) A temporary license means a food-service establishment which operates at a fixed location for a 
temporary period of time, not exceeding three (3) consecutive days, whether or not there is a 
charge for food. 
(2) Authorization of the site location is necessary prior to conducting business in the city. 
(3) A temporary food service application shall be submitted to the Health Official at least seven (7) 
days before the day of the event. If licensed by another agency, state, or municipality, you must 
provide a copy of the operator's current food-service license and most recent food inspection 
report. 
(4) Licenses shall be displayed in public view. 
(5) The operator is subject to inspection at any time. 
(6) Food preparation and handling practices for food establishments are to be in compliance with 
this Chapter. Including but not limited to following the Temp Event Guide Food Safety and Temp 
Event Checklist. 
(7) Temporary Food Service License Fees are established in accordance with the schedule of fees 
set forth in Appendix B of the City Code of Ordinances. 
Sec. 46-364 - Notice of alleged violation. 
(a) Whenever the Health Official or their designee , based upon an on-site inspection, determines that 
there are reasonable grounds to believe that violations of this chapter or the regulations adopted 
have occurred, notice of such alleged violations shall be given to the owner or their agent. Such 
notice shall: 
(1) Be in writing; 
(2) Include statements enumerating alleged violations and identifying the basis of the violation; 
(3) Where appropriate, indicate corrective actions to be taken; 
(4) Allow a reasonable time for the performance of any act require; 
a. In the case of a temporary food service establishment, the violations must be corrected 
within a specified period of time, not to exceed 24 hours. Failure to comply with such 
notice shall result in immediate suspension of the license;  
(5) And be served upon the owner or their agent as the case may require, provided that such notice 
or order shall be deemed to have been properly served upon such owner or their agent when 
the inspection report form containing information required by Subsections 2, 3, and 4 above has 
been completed and signed by the inspecting official and the owner or their agent and a copy 
thereof has been provided to the owner or their agent. 
Sec. 46-366 - Reinstatement of license. 
Page 202 of 210

Any person whose license under this chapter has been suspended may at any time make application for 
a reinspection for the purpose of reinstating the license. Within ten (10) days following receipt of a 
written request, including a statement signed by the applicant that in his opinion the conditions causing 
suspension of the license have been corrected, the Health Official shall make a reinspection. If the 
applicant is complying with the requirements of this chapter and regulations promulgated hereunder, 
the license shall be reinstated. 
Sec. 46-369 - Inspections. 
(a) The operation and facilities of all licensees under this chapter shall be inspected in accordance with 
He-P2305 as follows: 
(1) Classes 1A, 1, 2, 3, and 5 - twice every license cycle. 
(2) Class 6 - once every license cycle. 
(b) The cost of reinspection shall be established in accordance with the schedule of fees set forth in 
Appendix B of the City Code of Ordinances. 
Sec. 46-370 - Approval of plans; fees. 
(A) When a food service establishment is constructed, is remodeled, or changes owners, or when an 
existing structure is converted for use as a food-service establishment, properly prepared plans and 
specifications for such construction, remodeling, or alteration, showing layout arrangement and 
construction of materials of work areas, and the location, size, and type of fixed equipment and 
facilities shall be submitted to the Health Official or their designee for approval before such work is 
begun. 
(B) Fees for the mandatory food-service plan review and associated inspection(s) are established in 
accordance with the schedule of fees set forth in Appendix B of the City Code of Ordinances. 
Sec. 46-371 – Incorporation of the 2022 Food Code. 
The following amendments shall apply to the document incorporated: 
Delete following subsections: 
1-201.10 Food Establishment. 
Delete following subsections: 
1-201.10 Temporary Food Establishment. 
Change subsection to read as follows: 
3-301.11 Preventing Contamination from Hands. 
(B) Except when washing fruits and vegetables as specified under 3-302.15 Food 
Employees may not contact exposed, READY-TO-EAT FOOD with their bare hands 
and shall use suitable UTENSILS such as deli tissue, spatulas, tongs, single-use 
gloves, or dispensing EQUIPMENT. 
(D) Delete 
Delete following subsection in its entirety: 
Page 203 of 210

3-305.13 Vended Potentially Hazardous Food (Time/Temperature Control for Safety 
Food, TCS), Original Container. 
Delete following subsection: 
3-306.12 Condiments Protection. 
(B) Delete 
Delete following subsection: 
3-801.11 Pasteurized Foods, Prohibited Re-Service, and Prohibited Food. 
(D) Delete 
Delete following subsection: 
4.204.14 (A) (B) Vending Machines, Vending Stage Closure. 
Delete following subsection: 
4-204.19 Can Openers on Vending Machines. 
Delete following subsection: 
4-204.111 Vending Machines, Automatic Shutoff. 
Add new subsection to read as follows: 
4-301.13 Drainboards. 
Dual drainboards must be integral to warewashing sinks, in addition, UTENSIL 
racks, or tables large enough to accommodate all soiled and cleaned items that 
may accumulate during hours of operation shall be provided per necessary 
UTENSIL holding before cleaning and after SANITIZING. 
Add new subsection to read as follows: 
4-301.16 Food Prep Sink. 
A Food Prep sink that meets the requirements specified in 4-205.10, 5-202.13 and 
5-402.11 shall be provided for washing/thawing of foods, and drawing of potable 
water, to be used for no other purposes. 
Delete following subsections: 
4-301.12 Manual Warewashing, Sink Compartment Requirements. 
(C)(5) Delete 
(C)(6) Delete 
Page 204 of 210

(D) Delete 
Add new subsection to read as follows: 
4-302.12 Food Temperature Measuring Devices. 
(A) Digital food temperature measuring devices shall be provided and readily 
accessible for use in ensuring attainment in maintenance of food temperatures as 
specified under Chapter 3. 
Change subsection to read as follows: 
4-501.16 Warewashing Sinks, Use Limitation. 
(A) A warewashing sink may not be used for handwashing as specified under §2-
301.15, or drawing potable water, wash produce, or thaw foods. 
Delete following subsections: 
4-603.16 Rinsing Procedures. 
(C) Delete 
(D) Delete 
(E) Delete 
Change subsection to read as follows: 
5-104.12 Alternative Water Supply. 
Water meeting the requirements specified under Subparts 5-101, 5-102, and 5- 103 
shall be made available for a mobile facility, for a temporary food establishment 
without a permanent water supply, and for a food establishment with a two-hour 
interruption of its water supply through: 
Change subsections to read as follows: 
5-203.11 Handwashing Sinks. 
A handwashing sink shall be located within 20 unobstructed feet: 
(A) To allow convenient use by employees in food preparation, food dispensing, and 
warewashing areas; and 
(B) In toilet rooms. 
Change subsection to read as follows: 
6-501.115 Prohibiting Animals. 
Page 205 of 210

(A) Except as specified in (B) and (C) of this section, live animals may not be allowed 
on the premises of a food establishment, unless allowed by variance pursuant to 8-
103.10 through 8-103.12 for outdoor decks. 
Delete following subsection: 
7-202.12 Conditions of Use. 
(A) (2) Delete 
Add new subsection to read as follows: 
8-201.11 When Plans Are Required. 
(D) Change of owner. 
Delete Chapter 8: 
Those food establishments applying for licensure or that are licensed as a bed and 
breakfast shall comply with the Food Code. However, the exceptions to the Food Code 
listed in He-P 2308.02 shall also be exceptions to the Food Code as it applies to bed and 
breakfasts. 
Those food establishments applying for licensure or which are licensed as food processing 
plants or non-exempt homestead food operations shall be exempt from the requirements 
of the Food Code and shall comply with the requirements in, He-P 2309 and He-P 2311, 
respectively. 
 
Repeal and replace the contents of Appendix B, Section 46-363 with the content below: 
Appendix B- Fee Schedule  
Chapter 46 Licenses and Permits 
Sec. 46-363 – Food Service Establishment License Procedure and Fees 
License Fees 
(8) Class 1A: Food Service Establishment with 200 seats or more; retail food store with 4 or more 
food prep areas - $650  
(9) Class 1: Food Service Establishment with seating capacity 100-199 seats; food service 
establishment with extensive menus; serve raw ingredients (sushi, oysters, etc.), salad bar 
and/or food buffet; retail stores with 2 to 3 food preparation areas; nursing homes; hospitals; 
commercial food processing operations processing more than 100,000 packages of food per 
year - $450  
(10) Class 2: Food Service Establishment with 25-99 seats; retail food store with one food prep area; 
bakeries; food distributors of Time/Temperature Control for Safety (TCS) foods; beverage 
manufacturers; commissaries; caterer; mobile food unit selling/serving Time/Temperature 
Page 206 of 210

Control for Safety (TCS); commercial food processing operations processing less than 100,000 
packages of food per year - $400  
(11) Class 3: Food Service Establishment with 0-24 seats; retail food store-self services and no food 
prep area; commercial food processing operations of non-Time/Temperature Control for Safety 
(TCS) bulk foods; bakeries which do not serve Time/Temperature Control for Safety (TCS)  food; 
non- Time/Temperature Control for Safety (TCS)  mobile food units; retail markets selling only 
prepackaged items; bed and breakfast; private clubs; mobile venders, childcare facilities serving 
Time/Temperature Control for Safety (TCS); farmers market vendor selling/serving 
Time/Temperature Control for Safety (TCS)  food; Wholesalers/distributors Time/Temperature 
Control for Safety (TCS)  food - $300 
(12) Class 4: Temporary licenses see Sec. 46-363(e). - Temporary Food Service License Fees - $75  
a. Additional $25 expedite fee for applications received less than 7 days prior to the event.  
(13) Class 5: Public schools; private and parochial schools; not for profit organizations not holding a 
liquor license; governmental facilities that operate more than 4 times in a 28-day period – No 
Fee 
(14) Class 6: Sellers of prepackaged frozen USDA meat or poultry; retail markets selling only non- 
Time/Temperature Control for Safety (TCS)  prepackaged items; non-exempt homestead 
kitchens; arena/theater concessions selling/serving non- Time/Temperature Control for Safety 
(TCS)  food - $200 
Late Fine  
(1) License Renewal Applications received after the 10th day of the month following license date of 
expiration - $75  
 
Sec. 46-369 - Inspections. 
The cost of reinspection shall be: 
(1) Reinspection fee for failed routine inspection - Classes 1A, 1, and 2 - $200 
(2) Reinspection fee for failed routine inspection - Class 3 - $100  
(3) Reinspection fee for failed routine inspection – Class 6 - $50 
 
Sec. 46-370 - Approval of plans; fees. 
Fees for the mandatory food-service plan review and associated inspection(s) are established in 
accordance with the following schedule: 
a. Major remodeling of existing establishment: $100 
b. Remodeling of existing establishments limited to equipment change and minor 
structural modifications: $50 
c. Floor Plan review for a food establishment changing ownership- $75 
d. Class 1A new food service establishment - $200 
e. Class 1 or 2 new food service establishment - $150 
f. 
Class 3, 4, 5, or 6 new food service establishment - $100. 
 
 
Page 207 of 210

 
 
_________________________________ 
Jay V. Kahn, Mayor 
 
In City Council August 6, 2026. 
Referred to the Planning, Licenses 
and Development Committee. 
 
Assistant Clerk 
 
Page 208 of 210

 
2026-376 
 
 
CITY OF KEENE 
NEW HAMPSHIRE 
 
ITEM #K.1. 
 
  
   
Meeting Date: 
September 17, 2026 
  
  
To: 
Mayor and Keene City Council 
  
  
From: 
Finance, Organization and Personnel Committee, Standing Committee 
  
  
Through: 
  
  
  
 
Subject: 
Relating to the Appropriation of funds for the Marlboro Street & Cheshire 
Rail Trail Improvements Project  
Resolution R-2026-40 
  
  
 
  
Recommendation: 
On a vote of 4 to 0, the Finance, Organization and Personnel Committee recommends the adoption 
of Resolution R-2026-40. 
  
Attachments: 
1. 
R-2026-40 _Referral 
  
  
Background: 
Mr. Ruoff addressed the next item as well. This item relates to a Resolution for appropriations of 
funds for the Marlboro Street and Cheshire Rail Trail Improvements project. 
He explained what was designed and included in the contract documents for bidding, as far as 
sidewalk removal and replacement and granite curb removal and resetting was not a sufficient to 
complete all issues discovered during construction. 
 
He stated once Marlboro Street Corridor is completed it will be ADA compliant, which is a 
requirement of DOT. DOT understands that these additional scope of work is needed for the project 
and has agreed to pay for their share. This resolution essentially covers the City’s match. 
 
The actual change order is approximately $265,000. The City’s 20% match is slightly less than the 
amount that is being requested but it is to ensure there is sufficient money to complete the project. 
 
The following motion by Councilor Roberts was duly seconded by Councilor Chalice. 
 
On a vote of 4 to 0, the Finance, Organization and Personnel Committee recommends the adoption 
of Resolution R-2026-40. 
 
Page 209 of 210

 
R-2026-40 
CITY  OF  KEENE 
 
 
 
In the Year of Our Lord Two Thousand and              Twenty Six 
 
A RESOLUTION     Relating to the Appropriation of funds for the Marlboro Street & Cheshire Rail Trail 
Improvements Project 
 
Resolved by the City Council of the City of Keene, as follows: 
Related to an Appropriation of funds for the Marlboro Street & Cheshire Rail Trail Improvements 
Project NHDOT#42515 (75J0018B)  
 WHEREAS, The City has been awarded Federal, Transportation Alternative Project (TAP) 
funding, administered through NHDOT for the construction of our Marlboro Street & Cheshire 
Rail Trail Improvements Project, NHDOT#42515 (75J0018B); and,  
  
WHEREAS, The funding agreement for the project includes eighty percent (80%) federal 
funding and a twenty percent (20%) City funding match for the qualifying costs for the projects; 
and,  
WHEREAS, The City is required as part of the project to bring all sidewalks within the project 
limits in compliance with the applicable City, State and Federal standards; and,  
WHEREAS, The City desires to maximize the benefits of this project for the community;   
NOW THEREFORE BE IT RESOLVED That the sum of Eight thousand dollars ($80,000), is 
hereby appropriated from the unallocated General Fund balance for the purpose of allocating the 
additional necessary funds, from what has been previously allocated in the CIP to pay for the City’s 
required twenty percent (20%) funding, described in the federal funding agreement, for the 
Marlboro Street & Cheshire Rail Trail Improvements Project, NHDOT#42515, City of Keene 
Project#75J0018B. 
 
_________________________________ 
Jay V. Kahn, Mayor 
In City Council August 6, 2026. 
Referred to the Finance, Organization and 
Personnel Committee. 
 
Assistant Clerk 