PBMIN 2026-09-01 APPROVED - WORK SESSION

The Milford Planning Board held a work session on September 1, 2026. The Board reviewed the Capital Improvements Program (CIP) draft for 2027-2032, with Kyle Finnell recommending 15 projects totaling $15 million; however, the Board agreed to hold only one public hearing on the CIP and aimed to have a draft ready for review by October 6, 2026. Regarding RSA 79-E, the Board discussed potential amendments following the adoption of HB 1103 to expand tax relief criteria beyond the downtown area. The Downtown Improvement Program update presented preliminary construction costs of $2.3 million for the oval, $846,000 for Wadleigh Library parking, and $343,000 for South Street parking, with the Board deciding to schedule a joint meeting with the Select Board and EDAC to review costs. A motion to approve the minutes from August 18, 2026 passed with all in favor and C. Labonte abstaining. Future meetings are set for September 15, 2026, and October 6, 2026. Source: https://www.milford.nh.gov/api/blob/viewBlob?i=Lr8fmMNex8uhDL6feichD5M8ZMbBgQ2xmPw0wHbOuKvTx5DPoD%2F3kQvQpxjjY0ce

Document

MILFORD PLANNING BOARD WORK SESSION MINUTES ~ APPROVED 
1 
September 1, 2026 - Board of Selectmen Meeting Room, 6:30 PM 
2 
 
3 
Members Present: 
 
 
 
 
 
 
Staff: 
4 
Tim Finan, Chair 
 
 
 
                                    Terrey Dolan, Town Planner 
5 
Janet Langdell, Vice Chair                                                                 Blake Desmarais, Videographer 
6 
Justin Demontigny, Member                                                              Kyle Finnell, CommDev Director 
7 
Andrew Ciardelli, Member  
8 
Susan Robinson, Member  
9 
Paul Amato, Alternate 
10 
Chris Labonte, Selectboard Representative 
11 
Mike Thornton, Alternate Member 
12 
 
 
 
 
 
 
  
13 
VIA Zoom: 
 
14 
Excused: Pete Basiliere, Member                                                             
15 
 
16 
 
17 
 
18 
  1. Call to order: Chair Tim Finan called the meeting to order at 6:30 p.m. He introduced Planning Board 
19 
members that were present and staff. There will likely not be any votes taken this evening, but in case of 
20 
that, Paul Amato will be voting for the absence of Pete Basiliere. If S. Robinson does not show up, M. 
21 
Thornton will be voting for the absent S. Robinson. S. Robinson later showed up. 
22 
 
23 
 2. Public Hearing: The first order of business this evening is an update on the Capital Improvements 
24 
Program which will be presented by Kyle Finnell the Director of Community Development. 
25 
 
26 
 A. Capital Improvements Program – CIP (2027-2032) Draft Report Update. The CIP Committee 
27 
reviewed 21 total requests from seven departments this year, going through the process of ranking and 
28 
scoring those projects based on the 12 criteria for eligibility and also an urgency ranking.  The 
29 
Committee has finalized its scorecard which is provided for you today and has identified 15 projects that 
30 
they have recommended accepting for the 2027-2032 CIP plan.  To orient all with the scorecard, all 21 
31 
projects are listed which also includes the total cost and all are color coded for the cost and impact; the 
32 
15 projects are listed in descending order, the 15 are to be funded in FY2027, 4 in FY2028 and 2 to 
33 
begin funding in FY2032. 
34 
 
35 
To Mr. Amato’s comment (specifically that an ambulance can be replaced with no tax impact?), K. 
36 
Finnell explained there are four items highlighted in blue, Mr. Finnell explained 3 of those are for water 
37 
utilities, and are expected to be paid from rate user fees, the Ambulance is set up through their Capital 
38 
Reserve Fund for which monies come from the revenues generated from using the Ambulance Services 
39 
and the billing for those services.  Those ambulances are paid for out of the Capital Revolving Fund 
40 
where currently there is $140,000.  P. Amato asked how much is taken into those accounts per year?  K. 
41 
Finnell was told by the Finance Director that the threshold is usually met in Quarter one.  C. Labonte 
42 
commented that the Ambulance Department brings in between $900K and $1 million per year. C. 
43 
Labonte indicated that over the past couple of years, the ambulance billing laws have changed, the town 
44 
raised its rates in order to collect the maximum amount and that should bring in more as a net positive. 
45 
P. Amato asked what happens if someone does not have insurance? C. Labonte said there is a process to 
46 
go through to get the cost lowered. There are a lot of options and then there are some charges that are 
47 
un-collectable. J. Langdell said the $900 - $1 million is from billing?  C. Labonte said that is actually 
48 
collected. Actual revenue or anticipated revenue and it mostly goes into General Revenue.  C. Labonte 
49 
did have one question on the CIP projects; the DPW Truck was originally put in as DPW4, the town got 
50 
a grant which was a match and I believe we are getting another truck for DPW and the truck will be able 
51 
to be bought out of budget money. Mr. Labonte asked if Kyle Finnell could follow up on that to see if 
52 

Planning Board Work Session minutes 09.01.2026 ~ APPROVED 
 
2 
that DPW truck comes off the CIP list because DES awarded a grant that is funding 80% of the truck, so 
53 
that will be two trucks from DES in the last two years so that will eliminate a Warrant Article for the 
54 
vehicle. Kyle Finnell noted to check on that project in the CIP.  This year we are trying a new software 
55 
called ClearGov to prepare the CIP, as you can see on the screen (he is not able to print it out) and it 
56 
includes three budgeting modules and the first one we brought on line was Capital Budgeting so this is 
57 
how we have had the Department Heads submit their requests, fill out their financials and articulate how 
58 
they anticipate funding it, what years are anticipated funding it for the six years of the CIP or if it is 
59 
further out and this is also the platform which will be used to build out the CIP. Currently on the screen, 
60 
is the Dashboard that the CIP Committee has committed to using and if all of the presented projects 
61 
were to be approved as presented it would total $15 million over the full length of the CIP, that is not 
62 
what the taxpayers will be on the hook for and keep in mind this is based on initial estimates. This 
63 
software will, Mr. Finnell believes, give the Town a more robust CIP process that will follow year to 
64 
year as a planning document.  
65 
 
66 
T. Finan asked if all requests are in this software? K. Finnell responded all 21 requests are in the 
67 
program right now, based on the recommendations of the CIP Committee; K. Finnell has included the 15 
68 
projects to the CIP, the other projects were put into a category identified as “deferred.”  This way, those 
69 
deferred projects stay in the system and the Department Head that created it can go in and edit it or 
70 
tweak the numbers or the years and come back to it in another year to resubmit to the CIP. T. Finan 
71 
asked if the report will be generated from this software? And will all 21 projects be included? K. Finnell 
72 
responded they when the report is generated, we can include all 21 projects. J. Langdell indicated the 
73 
dashboard can probably be adjusted to show all 21 projects too. K. Finnell responded that he knows that 
74 
we can, but we are all just learning the software so he cannot make that change quickly at this point.  C. 
75 
Labonte stated that he hopes ClearGov will be a good tool for the town, and in the past he has not felt 
76 
that the CIP was a good tool for him since it only did one year at a time, so now with the new software, 
77 
it shows that nothing has been but in the years after the six year timeframe. C. Labonte feels that having 
78 
the longer list of projects shows what the town actually needs and the CIP has done over the past ten 
79 
years has really not been a strategic planning tool.  J. Langdell responded by stating that in the past there 
80 
was a BOS member that wanted to prioritize a list for the BOS looking at one year.  C. Labonte feels 
81 
that is a disservice to the Town.  J. Langdell agrees and wants to go back to the intention of the CIP over 
82 
a multi-year period.   
83 
 
84 
T. Finan said this is the conversation that has been happening for many years and it is a shame for 
85 
volunteers to put in so much time on the committee.  All agreed this software may in the end be a more 
86 
proactive tool.  P. Amato asked where is the school input?  K. Finnell said he will do his best to answer 
87 
that stating the Superintendent and School Business Administrator have been invited to use this 
88 
platform, they were included at the very beginning of this process with all Department Heads, when 
89 
Kyle reached out to the School Board Chair and asked who would be representing the School District on 
90 
the CIP Committee, he was told they are already over extended and did not want to further stress the 
91 
Board.  They have developed their own CIP process; the last Kyle has seen they met in late June and 
92 
have not met since then and he has not gotten any updates.  K. Finnell has one informal meeting with the 
93 
Superintendent in mid-August and at that time she indicated they only have one project for the short 
94 
term moving forward and he has not received any information or numbers related to that project so he 
95 
cannot really speak to it but he is hopeful that numbers will be provided so that it can be included.  T. 
96 
Finan said so there is one project that they would have on the CIP? K. Finnell clarified that there is one 
97 
project that they would bring to the voters in 2027.  M. Thornton indicated the Town is doing its best to 
98 
identify the needs and until the School meets with the Town to identify all the needs in town, we will not 
99 
get to a clear outcome.  T. Finan sees this as a disservice to the Town and he would love to see their 
100 
report so that we can look at both CIPs (School and Town).  In the conversation with the Superintendent, 
101 
K. Finnell stressed that he would like to get the town and school synchronized so that we can be 
102 
supportive and a spreadsheet would be helpful.  K. Finnell had been told that there would be a line of 
103 

Planning Board Work Session minutes 09.01.2026 ~ APPROVED 
 
3 
communication but he has not heard from anyone during the summer.  Because of that, we will circle 
104 
back now that we have a Finance Director that has been getting oriented and attending the CIP meetings 
105 
and she will be assisting in the cleanup of some of the financials; remembering this is a new tool and the 
106 
Department Heads submitted information on projects without the assistance of a Finance Director in the 
107 
beginning so Kyle has been learning but is not a Finance person but he is doing his best. Based on the 
108 
urgency scores from the CIP Committee we are trying to go back into the requests and anything that 
109 
scored less than a 5, which ends up being six projects that will be looked at and will try to push those out 
110 
to future years to try to address that concern of a really heavy hit in tax year 2027 and 2028. 
111 
 
112 
J. Langdell asked if there will be a report produced in the end that goes out several years similar to what 
113 
the Planning Board used to get?  K. Finnell responded that the historical CIP report had 3 tables attached 
114 
to it, Anticipated Impact to Taxpayers, in talking with ClearGov they will give the town access to new 
115 
functionality to test it out and allow us to go in and build out that table that we are accustomed to seeing, 
116 
add those categories and then run a single report for all of those projects to see the anticipated tax impact 
117 
year to year since the cost is not necessarily the impact year to year.  The software is still very new and 
118 
something that Kyle and Jennifer the Finance Director will work through and because of that we may 
119 
not have a draft CIP to present to the Planning Board until October since it will take a couple weeks to 
120 
get through that. Additionally, with ClearGov the CIP report can be generated but there will still be a 
121 
need to provide some of the tables that ClearGov is not set up to generate.  P. Amato asked if the 
122 
progress and status is available throughout the year with the budgeting module?  K. Finnell responded 
123 
that there is “Budget Tracking” so that once it is approved through the CIP, those financials are 
124 
transferred into the Budget Tracking piece.  We are not yet trained on that portion, but in year two there 
125 
will be training done in order to utilize that module. J. Langdell asked if that can also be used to track 
126 
any Government Projects?  K. Finnell answered that would be very helpful and he will explore that.  P. 
127 
Amato asked if ClearGov will be used for the Town Budget this year?  C. Labonte said that was the 
128 
intent however, with the disruption of the computers in July 2026, K. Finnell is unsure if that will 
129 
happen in 2026 or 2027.  Additionally, K. Finnell mentioned that another new software the Town is 
130 
launching this year, BS&A, is the Accounting software that goes live in December 2026. 
131 
 
132 
J. Langdell asked if the two software products (ClearGov and BS&A) talk to each other?  K. Finnell 
133 
responded that they do, when we upload the data from ClearGov to BS&A they have to essentially code 
134 
where the numbers are (ESR).  The current system (MUNIS) does not line up with what the DRA wants 
135 
us to have so we are considering pausing the budgeting rollout until next year.  P. Amato confirmed that 
136 
ClearGov is a budgeting tool? And BS&A is an Operational Tool to do the Accounting? K. Finnell 
137 
agreed and until we get BS&A cleaned up and recoded to match the DRA, he does not see ClearGov 
138 
being used for Operational or Personnel for this year but we were already underway with Capital so we 
139 
are pushing through with CIP and getting Department Heads used to the platform since the platform will 
140 
be very similar.  P. Amato asked about this year’s CIP and this list shows projects for this year, were the 
141 
other projects for future years?  The guidance that K. Finnell gave Department Heads was to provide 
142 
him with all past projects and projects not adopted or put to future years, knowing that ClearGov can put 
143 
projects into future years he felt it would be easier.  C. Labonte said thank you to Kyle Finnell to taking 
144 
on the CIP project and understands that it is a lot to take on in one year.  K. Finnell explained that he and 
145 
the Finance Director Jennifer need to sit down to review the projects and determine what can be pushed 
146 
off to another year or years.  He did not have that information at the CIP Committee meetings so the 
147 
scorings were based on what was presented and he has left the scorings and arrangement to the Finance 
148 
Director and Community Development Director.  T. Finan indicated that after this year, going forward 
149 
that should not be on those two people.  K. Finnell agreed and stated that going forward that information 
150 
will be built into the CIP. 
151 
 
152 
C. Labonte asked about Project DPW3 that has a price of $5.6 million? K. Finnell said that is the total 
153 
over the number of years.  The Director is presenting the $5.6 million over a number of years for paving.  
154 

Planning Board Work Session minutes 09.01.2026 ~ APPROVED 
 
4 
K. Finnell indicated he will show how the projects can be filtered out by year to get a better grasp on the 
155 
yearly cost; new users put in the total for one year, but that does not show the tax impact for taxpayers it 
156 
just shows the total cost; that is where Kyle and Jennifer need to go through to clean up the data that was 
157 
submitted to the CIP this is currently a living document that needs cleanup work.  J. Langdell also would 
158 
like to have the Capital Reserve Funds identified for any projects that have them.  A list of the projects 
159 
that have a Capital Reserve Fund and a list of the Capital Reserve Funds and balances; this will be 
160 
needed for Town Meeting as well, said J. Langdell.  K. Finnell just saw that list last night and will try to 
161 
include it in the final report.  K. Finnell said the Finance Director is hoping budget numbers will be 
162 
complete next week.  K. Finnell is hoping to have a draft CIP by the third week of September to have a 
163 
look before the first public hearing. T. Finan asked if there are two public hearings needed? K. Finnell 
164 
answered he believes historically there have been two public hearings. T. Finan commented it sounds 
165 
like there is a lot on Kyle’s plate, would it be better to have the first public hearing later in October? K. 
166 
Finnell said if the Board is okay with having only one public hearing, that would be okay for him. K. 
167 
Finnell said he is anticipating having the draft CIP for the Planning Board Work Session October 6. P. 
168 
Amato said if there is only one meeting to review the draft CIP it needs to be ready to go.  T. Finan 
169 
noted that there could always be a public hearing at a joint meeting with the BOS. 
170 
 
171 
Paul Amato asked C. Labonte how comfortable is the BOS with the to date spent numbers versus the 
172 
budget? It is hard to create a budget if you don’t know the spent to date numbers.  C. Labonte said that is 
173 
hard to answer; starting with having a lot of changes whether software changes, some different things so 
174 
burn rates might not have been available or distributed timely so we would look forward to seeing those 
175 
burn rates.  One year ago, there was a burn rate each month and then that faded off, there is a burn rate 
176 
for every department by line item; so we have been working through new staff, new processes, new 
177 
software to get a more detailed, accurate report to know where we are.  P. Amato that is so you can start 
178 
on next year’s budget.  C. Labonte state that happens behind the scenes at the Town Administrator level.  
179 
P. Amato added that they need to know that the numbers are good enough.  The tax rate will be set fairly 
180 
soon in October and the State needs accurate numbers (burn rates) to decide what the tax rate it.  Not 
181 
necessarily the expenses but the revenue, we can’t exceed the numbers.  But P. Amato asked how do 
182 
you know you are not exceeding the budgeted number if you don’t have your burn rates? C. Labonte 
183 
said as a municipality, you cannot exceed what is budgeted.  J. Langdell said but it has happened, not in 
184 
Milford, but it has happened. C. Labonte said he has to trust the Finance Department for those numbers.  
185 
P. Amato noted that as Selectmen, that Board is fiscally responsible.  The last burn rate seen by C. 
186 
Labonte showed that the burn rate was not out of whack. 
187 
 
188 
K. Finnell wanted to show members what the CIP document from the new software generates.  It would 
189 
give a one-year report and then it can also give the full 6-year breakdown with funding sources (which 
190 
needs clean up). Once all the data is cleaned up, T. Finan commented it looks like it will be great. Once 
191 
the data is alright, the document can be public facing so members can go into it to get comfortable with 
192 
the new layout. K. Finnell asked the Board if it would be okay with getting read-only access? The CIP 
193 
Committee was granted more interactive access.  His one request would be that members not use the 
194 
Comment Feature as was recommended by NHMA. J. Langdell asked if the comment feature can be 
195 
turned off?  K. Finnell said it cannot, but he will look into that to see if there is another way to keep it 
196 
read only. C. Labonte said in the past the town used capital reserve funds for bigger projects and now we 
197 
have changed to inconsistent use of them, is there a function in ClearGov that can utilize those Capital 
198 
Reserve Funds with the budget? K. Finnell answered that he and Jennifer are looking to find that 
199 
function in the system.  J. Langdell said it seems like the previous Finance Director used that ability to 
200 
select ClearGov.  M. Thornton asked if one of the functions of ClearGov was that the public could go in 
201 
to look at the numbers in the “Budget Book”? K. Finnell said yes that is one of the features that attracted 
202 
the Town to this software. 
203 
 
204 

Planning Board Work Session minutes 09.01.2026 ~ APPROVED 
 
5 
T. Finan asked if consensus of the Board is to only hold one CIP public hearing?  J. Langdell said yes it 
205 
seems that as long as that one public hearing is a complete hearing. All concurred. There were no other 
206 
comments on the CIP. 
207 
 
208 
B. Amended New Hampshire RSA 79-E Discussion  
209 
S. Robinson asked if there was someone planned to come in to talk to the Board on 79E?  T. Finan 
210 
responded that there was a plan, but Kyle had an intern do some work for him on this.  K. Finnell provided 
211 
the background on the 79-E which was adopted in Milford in 2017 and also some new processes that are 
212 
now in effect thanks to House Bill 1103 which the town may be interested in adopting.  Currently the 79E 
213 
program allows tax relief for meeting the criteria. With the passage of HB 1103, the town is able to allow 
214 
additional criteria.  K. Finnell read the current language in HB1103. There is an upcoming Webinar 9/17 
215 
at noon; speaking to this new language so we will be getting guidance on how we can implement the 
216 
changes.  The current 79E in Milford is limited to only the downtown area.  With HB1103 there is more 
217 
flexibility in what the town can adopt.  C. Labonte said now if there is new housing built, the town needs 
218 
to decide how that bill can be implemented in Milford. Also if new housing is built, who ends up getting 
219 
the tax benefit?  Is it the developer, the builder, the owner?  K. Finnell offered that 79E is there and there 
220 
are projects that would not happen if it were not for 79E; the town needs to make sure that the program is 
221 
good for the town. The webinar is on September 17.  K. Finnell noted that we will send out that link for 
222 
anyone to join.  J. Langdell would like to see the ability for this bill to open up more housing availability.  
223 
K. Finnell pointed out that Keene has opened up a lot of the provisions of this bill to include mixed use, 
224 
and going to the maximum of tax relief, over time the district has built out according to the 79E regulations.  
225 
They area not re-zoning, they are only expanding it.  J. Langdell asked how Keene defines Affordable 
226 
Housing?  K. Finnell said he will find that out.   
227 
 
228 
P. Amato asked how this will be incorporated into the schedule? T. Finan maybe we take a look at what 
229 
is available and take small portions? J. Langdell asked if the Board wants to take a look at the Zoning first.  
230 
K. Finnell suggested this is just an introduction, maybe start with looking at the maps, that includes 
231 
water/sewer, then a map with zones and look at housing opportunities.  By using the maps to start, we can 
232 
identify what aligns the most to allow provisions.  He understands that this is just the beginning of the 
233 
conversations.  J. Langdell indicated there is a lot of information out there and would it be beneficial to 
234 
invited Conservation, EDAC, BOS, and have it upstairs.  A. Ciardelli thanked Kyle for the information 
235 
and feels it is a great start to create our thoughts and bring that back to the next meeting to discuss.  There 
236 
are a lot of layers to this, so everyone needs to read it over again and then schedule a Charrette to further 
237 
reach out.  Kyle commended the Intern, Ryan, that supported Community Development and provided a 
238 
lot of this information for tonight’s meeting.   
239 
 
240 
C. Downtown Improvement Program Update.   K. Finnell summarized a memo to the Chair of the 
241 
status of this project.  The Preliminary Engineering Phase is just being concluded.  The Cost estimates are 
242 
being compiled and in an update provided this morning.  DOT is still waiting on traffic data.  The BOS 
243 
needs those details to make decisions.  There are two sections of the Downtown, Middle Street to Putnam 
244 
and Nashua Street to School St.  Expanding the Wadleigh Library parking is another element. And the 
245 
parking lot on South Street/Clinton Street is another element.  The Final Prelim plans downtown oval cost 
246 
construction is estimated is $2.3 million, the Library Parking Lot will be $846,000 and the South/Clinton 
247 
Street parking lot will be $343,000.  The recommendation from town staff is similar to what as presented 
248 
to the BOS last night, based on the estimates and including a generous contingency, the town must decide 
249 
whether to advance the project in full as designed and programmed or otherwise to lower certain elements 
250 
to remove costs and more closely align with the funding cap. Without the DOT costs, town staff cannot 
251 
identify items that could be removed or amended, the was clarified this morning with the DOT project 
252 
manager; we are not at risk of losing any of these funds as that cap is set. Unfortunately, understanding 
253 
inflation and the rising costs of materials, the longer this project goes out, the less that buys us. K. Finnell’s 
254 
understanding is that if the town were to begin to remove elements in order to find cost savings, DOT does 
255 

Planning Board Work Session minutes 09.01.2026 ~ APPROVED 
 
6 
not think that the town would be at risk of losing those funds in full. That was the guidance he and town 
256 
staff heard today on the call that everything here is designed for pedestrian and traffic safety so if were 
257 
were to start to remove things we would not be at risk of losing program critical elements. K. Finnell will 
258 
do his best to get that in writing. A. Ciardelli asked if the elements of the project include the Wadleigh 
259 
parking and the South Street parking areas or is it just the oval? J. Langdell answered that the original 
260 
monies that Milford got were part of the original Oval and Nashua Street project to be used for the oval 
261 
and Nashua Street improvement but there was additional money for that too. South Street, meaning from 
262 
the crosswalk here at the corner of Café on the Oval down to before the railroad crossing. T. Finan asked 
263 
if the suggestion is that the South Street parking lot is to add to the project cause people would be walking 
264 
back and forth to the oval? A. Ciardelli said he is just suggesting, well they are not on this plan. J. Langdell 
265 
said it is not on that plan. A Ciardelli indicated that we are partly over budget because of the Wadleigh 
266 
parking lot and the South Street parking lot.  J. Langdell said that is one of her questions she had, where 
267 
is the plan that shows what Milford is requesting as part of the $343,000 to do a parking lot at the corner 
268 
of South Street and Clinton Street? K. Finnell indicated it is on sheet 24 of the total package, the very last 
269 
sheet. J. Langdell found the 11x 17” sheet in the middle of the table. P. Amato does not think they can do 
270 
what we want to do to the Oval if you don’t add more parking; we are trying to make it safer and prettier 
271 
but we can do it with less parking. J. Langdell said she agrees and feels the Wadleigh parking is far more 
272 
important than the South/Clinton Street parking. 
273 
 
274 
Janet Langdell said there are a lot of suggestions and this is the first pick of what we want to do for public 
275 
safety but there are many ways to provide public safety and walkability using different types of structures 
276 
that may be less costly to put in play. Seeing how we are $1.4million off, she thinks that VHB could come 
277 
back with suggestions.  C. Labonte explained that the are other options, such as taking out the trip hazard 
278 
brick running along the sidewalk and replacing it will a colored concrete in lieu of the bricks; just that 
279 
change would reduce the costs significantly. Further, C. Labonte suggested having a sit down with 
280 
Planning Board, BOS, EDAC and VHB to flush out some of the items to save costs, but until we have 
281 
costs from DOT we are spinning our wheels. J. Langdell stated that these costs are causing budget 
282 
constraints at the town level, and Concord needs to know that. K. Finnell shared that in conversations with 
283 
VHB, they expressed that they are willing to provide a cost estimate for each element of the project to 
284 
analyze what can be put off or amended.  J. Langdell asked if that is a push of a button on is that going to 
285 
take months? K. Finnell said they asked for some lead time on that and he will coordinate with Greg this 
286 
week to make it very clear what the Board is looking for so that he can provide that before the joint 
287 
meeting.  J. Demontigny stated that he imagines it will take about a week to break out each of the items 
288 
with cost estimates. J. Langdell said the lack of communication with the State and that the town asked for 
289 
this before in July and we still do not have it, which is why we need to get back with our consultant. 
290 
 
291 
Andrea Kokko, resident, said it was 2022 when she was part of the design plan and she has not followed 
292 
it but at that time, DOT was regularly talking to Concord and every time there was a squabble about how 
293 
ridiculous is a crosswalk because people could not agree, so DOT would send recommendations, the 
294 
consultant would say no you have to stay with these items and then the town added the Wadleigh parking 
295 
because so much parking was being lost and at the tail end South Street came into play due to the 
296 
possibility of more grant money if that was added. There were also some questions on that South Street 
297 
site about drainage.  J. Langdell remembers that timing and was under the impression that the drainage 
298 
issues had been addressed. K. Finnell’s understanding of the required monitoring of the ground water 
299 
because of the brownfield funding that cleaned up the site, those monitoring wells have to be accessible 
300 
through October 2027. The plan as presented identifies at least 3 to monitor so that the environmental 
301 
monitoring can still be conducted. If this site is not developed until after October 2027, those wells should 
302 
not be adjusted, there would not longer be a need for them. J. Langdell asked if it is still considered a 
303 
Brownfields area?  K. Finnell said yes because of the monitoring wells. J. Langdell said there may be 
304 
monies available through NRPC that could be explored for that. K. Finnell is not sure that a municipal lot 
305 

Planning Board Work Session minutes 09.01.2026 ~ APPROVED 
 
7 
would qualify but he can explore that. We have completed the two phases of clean up and he was under 
306 
the impression that there were no further monies available. 
307 
 
308 
Andrea Kokko, resident, asked when the town receives the cost estimates for this type of work, how does 
309 
the town go about getting the contractors, is the town capable to get bids on the work or do we have to use 
310 
a consulting firm or does the town hire the consulting firm to do the hiring?  The understanding of K. 
311 
Finnell is that VHB is the consultant and they would not be the construction engineer. J. Langdell asked 
312 
if the town would be the project manager is it at the State level?  K. Finnell need to clarify that. A. Kokko, 
313 
resident, compared what the estimate for a condominium roof as compared to the actual costs was very 
314 
different, so we need to be careful with any estimated numbers being put out there, when the numbers 
315 
may not be as bad as what is being portrayed. She believes that the first thing to go from this project will 
316 
be the South Street parking lot.  The Wadleigh is favored with an Oval improvement. 
317 
 
318 
Justin Demontigny responded to the questions from Andrea Kokko about who will get the costs from 
319 
contractors? C. Labonte believes that will be done by the State. J. Langdell said they usually will have the 
320 
local engineers review the plans and provide estimates; the process she has seen is that the local engineer 
321 
will review the plans and then it goes to the State who questions some of the numbers.  C. Labonte asked 
322 
if the Oval was done with the same monies 25 years ago? Who was that project manager? J. Langdell 
323 
thinks the funding source at the time may have been different.  P. Amato would like to see the Wadleigh 
324 
Parking done first before the Oval gets broken into.  K. Finnell commented that the Wadleigh Parking 
325 
would be done first so that the new gained parking spaces will be ready to accommodate the disruptions 
326 
to the Oval. 
327 
 
328 
Chris Labonte indicated that the Swing Bridge work will be done in 2028 and if this project goes into 
329 
2028, we are looking at gridlock in Milford; we should look at the time here. P. Amato offered maybe 
330 
looking at doing one of the parking lots in 2027, the State does not have anything to do with either parking 
331 
lot. K. Finnell offered that through the project, there are engineered plans for both projects, but for the 
332 
construction phase, DOT does not have a lot of say when it comes to the parking lots.  P. Amato said he 
333 
just did work on a parking lot that is significantly bigger than South Street, it was taken down 12”, put 
334 
loam and gravel in and drainage, paved and striped it for under $200,000 in two weeks. C. Labonte asked 
335 
if any foundation was removed, since the South Street lot still has a foundation under the asphalt.  P. 
336 
Amato said why would it need to be removed? It is just asphalt going over it, if something happens you 
337 
just dig it up.  So, if one of the parking lots can be taken out of the Oval project and gets put on a Warrant, 
338 
said J. Langdell, that would get this much closer to the $1.4 million.  J. Demontigny has been looking at 
339 
the estimates and said the cost of a changeable electronic sign is in the estimates for $80,000, maybe we 
340 
could get a better price locally, or just buy one for that money.  This entire project has been reviewed, and 
341 
re-reviewed by the Town Engineer, Director of DPW and Community Development staff, it is not just the 
342 
Board sitting here tonight. 
343 
 
344 
In terms of next steps, the recommendation was made to the Select Board and they seem amenable that 
345 
upon receipt of DOT comments they would review and look forward to collaborating with the Planning 
346 
Board to schedule a joint meeting; he recommended that other Boards be invited especially members of 
347 
EDAC with whom are property owners or business owners that would be directly impacted by the project. 
348 
K. Finnell has heard clearly and thinks it is important and necessary to invite VHB, Engineering 
349 
Consultant, to be present, he will do his part to get that next piece coordinated with them. J. Langdell 
350 
noted invite the Library Trustees to that meeting too and should be done in the Town Hall Auditorium. K. 
351 
Finnell noted to invite them as well, so we can discuss things.  J. Langdell asked if this presentation could 
352 
be put on the Active Projects Page of the Website. K. Finnell responded that the plans are on the Planning 
353 
Board and Select Board pages and he will take the action to add them to the Active Projects page. C. 
354 
Labonte asked at what point to any business owners affected or property owners affect get notified? K. 
355 
Finnell said during any Right of Way hearings there will be public hearings and those owners and 
356 

Planning Board Work Session minutes 09.01.2026 ~ APPROVED 
 
8 
businesses would be notified, and those abutters would be identified by DOT.  K. Finnell noted that his 
357 
predecessor Camille Pattison and Greg Bakos at the State of NH, have met multiple times and he has 
358 
access to those notes and distributions of abutters.  J. Langdell feels it might be appropriate to send out an 
359 
e-mail to those to alert them of what will be coming up. 
360 
 
361 
D. Other Business.                                                                                                              
362 
The town has coordinated a Site Walk with the Conservation Commission tomorrow evening for MD’s 
363 
Trash Removal for the Major Site Plan Application coming before the Planning Board September 15, 
364 
2026. This is a public site walk hosted by the Conservation Commission and there can be no discussion 
365 
of the plan, nor decisions made at the Site Walk. 
366 
 
367 
3. Other Business:.   
368 
T. Dolan asked that all members please respond when asked about being present at a meeting or not, it is 
369 
critical that Administration know who is or is not planned for attendance. Kindly please confirm your 
370 
attendance, it is slipping a lot lately. Do not REPLY all just sent a quick “I will be there” or “I will not be 
371 
there”. 
372 
 
373 
4. Meeting Minutes Approval:  
374 
T. Finan asked for a motion to approve the minutes from 8/18/2026. A. Ciardelli made the motion and J. 
375 
Demontigny seconded. All were in favor with none opposed and C. Labonte abstaining. Motion passed. 
376 
 
377 
5. Future Planning Board Meeting Dates: 09/15/2026 MD’s Trash & 10/06/2026 Work Session.  
378 
 
379 
6.  Adjournment:  
380 
T. Finan asked for a motion to adjourn the meeting. P. Amato made the motion to adjourn at 8:56 pm; A. 
381 
Ciardelli seconded. All were in favor with none opposed and no abstentions. Meeting adjourned at 8:56 
382 
pm.  
383 
 
384 
 
385 
Respectfully submitted by: Darlene Bouffard 